DIY Home Improvement Forum banner

Most logical order of steps to resolve laying foundation

1.6K views 9 replies 3 participants last post by  Nealtw  
#1 · (Edited)
We're owner builder (probably in hindsight should not have chosen this path). Never again!!!

Building a house on a slopy land. So far we have done
  • cut and fill to make a level ground
  • poured retaining wall concrete footing
  • installed retaining walls.
  • digged footings ready for the concrete slab (slab not poured yet)
After speaking with plumber today, we identified an issue that the levels are not right and will cause water issue in the future. Will try my best to explain.
  • land sloped downwards higher from the back towards the street.
  • land has rocks (sandstone) bedding underneath the soil/dirt.
  • after installing the retaining wall (& core filled), we realised the levels next to the retaining wall conccrete footing are in fact higher than the concrete footings itself (an oversight from us). This creates water backflow issue where the retaining wall footing should have been higher to allow water flow towards the street.
Here are what we think the solutions may be required.

1. further dig the area next the retaining wall footing such that the surroudning levels become lower than the retaining wall footing (some surounding areas are exposed rocks so need to break the rocks)
2. overlay the existing retaining wall footing with a thin layer of concrete such that it creates a proper sloping to allow proper water flow down to the street. because there are certain areas of retaing wall footing with collection of water after rain because the footing is not leveled properly at the time of pouring.

Question for us is (as we do not have much prior experience with building house on a slopy land)

a: do we pour the concrete slab first and followed by the suggested solution above

OR

b: we should finish the suggested solution (1 & 2) before pouring the concrete slab.

Any share of experience, verification, commentary that put us in the right direction will be much appreciated.
 
#2 ·
Is there any way for you to post pictures of this so we can see what you see? Difficult to imagine what you have from the description.
 
#3 ·
Attached picture shows the level issues (hopefully it makes sense).

- area surrouding retaining wall footing (orange) currently is higher than the retaining wall footing (blue). therefore, water flows backwards to the retaining wall.
- need to dig the orange area to ensure the its level become lower than blue &
- overlay the footing (blue) with a thin layer of concrete with finishing slope that will divert the water away from retaining wall. (already seeing pockets of green mould growing at the bottom of the retaining wall)

Question for us is
a: whether to pour the conrete slab first (to ascertain the level of the slab) before carrying the rectification works above

or

b: carrying out the rectification works first before pouring the concrete slab
 

Attachments

#4 ·
Attached picture shows the level issues (hopefully it makes sense).

  • area surrouding retaining wall footing (orange) currently is higher than the retaining wall footing (blue). therefore, water flows backwards to the retaining wall.
  • need to dig the orange area to ensure the its level become lower than blue &
  • overlay the footing (blue) with a thin layer of concrete with finishing slope that will divert the water away from retaining wall. (already seeing pockets of green mould growing at the bottom of the retaining wall)

Question for us is
a: whether to pour the conrete slab first (to ascertain the level of the slab) before carrying the rectification works above

or

b: carrying out the rectification works first before pouring the concrete slab
Did you put drainage behind the retaining wall?