Three nails in each stud, two on one side and one in the middle in the other side.
There should be no need for any lags in the bottom plates. Should have been just 2, 3" nails between each stud should work.
All there doing is keeping the bottom of the wall from moving in or out, not preventing it from moving up and down.
Far more likly your dealing with under sized floor joist or under sized of fastened subflooring, so as you walk by somethings moving.
 
Are they still exposted?
Georgia Pacfic suggest adding 3/4 plywood or OSB in the webbing using constrution adhesive and nails to take out the flex.