DIY Home Improvement Forum banner
1 - 20 of 24 Posts

· Registered
Joined
·
171 Posts
Discussion Starter · #1 · (Edited)
Looking for suggestions and advice on what to do with this front porch. Its a concrete slab with slate set on top. Most of the slate slabs are loose.

I’m hoping to do this myself but dont have a lot of experience with stone/concrete work but not afraid to try.

If I pull up all the slate I’m left with a rough, uneven surface.. Not sure what To do with it. Reuse the slate? Bricks? Something else?

Help me out so I can stay busy and not go out of my mind while I’m furloughed! Thanks!



Sent from my iPhone using Tapatalk
 

· Super Moderator
Joined
·
24,985 Posts
You could reuse the slate if that is the look you want. I would try to number the pieces and take a picture so you can fit them back together.
The concrete needs to be solid if you will be doing over again. Rough surface is fine but it can't be crumbling and breaking up.
 

· Registered
Joined
·
171 Posts
Discussion Starter · #4 ·
Honestly, I would rather do something else with it but not sure what.. The porch is low and could be raised up closer to the bottom of the front door. Can the slate be removed along with loose material and then a layer of fresh concrete poured on top?

Was thinking about making it level with a fresh layer and then possibly use bricks or some other stone/blocks to make a new surface. Is that possible?
 

· Registered
Joined
·
171 Posts
Discussion Starter · #6 ·
Lets say I remove all the slate and loose mortar.. I'll be left with a rough bumpy , uneven surface. Us it ok to just make a form around it and pour over top of it a couple inches? If so, what should I use?
 

· Registered
Joined
·
6,737 Posts
if placing 2" doesn't get you too close to the sill, i'm ok w/it,,, think the best method's to chop out the old & place NEW conc,,, if you want overlay, recommend using either polymer-modified cement extended w/2gal of pea stone per bag or 5,000psi bagg'd conc mix,,, you can find either on shelves @ favorite apron/vest store,,, plan on priming w/grout b4 placing reg conc.
you'll likely find the existing slab's got cracks but no original joint(s),,, if that's the case, the cracks MAY be acting as joints,,, tough call w/o seeing pics of the slab w/cover stone removed & then pressure washed to clean condition
 

· Registered
Joined
·
171 Posts
Discussion Starter · #10 ·
if placing 2" doesn't get you too close to the sill, i'm ok w/it,,, think the best method's to chop out the old & place NEW conc,,, if you want overlay, recommend using either polymer-modified cement extended w/2gal of pea stone per bag or 5,000psi bagg'd conc mix,,, you can find either on shelves @ favorite apron/vest store,,, plan on priming w/grout b4 placing reg conc.
you'll likely find the existing slab's got cracks but no original joint(s),,, if that's the case, the cracks MAY be acting as joints,,, tough call w/o seeing pics of the slab w/cover stone removed & then pressure washed to clean condition
Thanks for the advice! I'll look into that further. I'd rather not remove the entire pad if I dont have to so I'll probably try to work off of it assuming its not too bad once I remove all the stone on top.
 

· Registered
Joined
·
171 Posts
Discussion Starter · #12 ·
OK, so here’s where I’m at. I removed all the slate and the loose mortar that was below it and there was also a bout an inch thick pour on top of the original slab that mostly came up. The 4 x 4‘s on the corners were actually run all the way down into the ground. Of course they were rotten at the bottom and surprisingly weren’t even holding any weight at all.

I was thinking about just making a form around the existing slab and pouring maybe a couple inches on top of what’s there now. Would it be OK to fill in those corners once I’ve make a form around it?



Sent from my iPhone using Tapatalk
 

· Registered
Joined
·
5,708 Posts
I have poured 2" caps a few times where doing otherwise for more than I cared to do. So far they are holding.


As for those post area, I would get at lest 1 rebar pin into the slab for each of them, pour them level to the existing slab and pour the cap.


Chance are the caps will give us both problems down the road and is not as good as a new slab. Sometimes you got to do what you got to do.


How much clearance to the bottom of the siding with the 2" cap?


Enen though those posts did not appear to be holding anything I would get some temp braces in place.
 

· Registered
Joined
·
171 Posts
Discussion Starter · #14 ·
I have poured 2" caps a few times where doing otherwise for more than I cared to do. So far they are holding.


As for those post area, I would get at lest 1 rebar pin into the slab for each of them, pour them level to the existing slab and pour the cap.


Chance are the caps will give us both problems down the road and is not as good as a new slab. Sometimes you got to do what you got to do.


How much clearance to the bottom of the siding with the 2" cap?


Enen though those posts did not appear to be holding anything I would get some temp braces in place.


I’ll still have a few inches of clearance at the siding if I go about 2 inches thick.

I do have some bracing



Sent from my iPhone using Tapatalk
 

· Registered
Joined
·
171 Posts
Discussion Starter · #15 ·
Finally got some good weather today so I’ll be working on this some more.

Question.. Should I pour the corners flush with the existing slab first, wait some time for it to set and then pour the top up 2 “? Or should I pour it all at once?

If 2 steps are better, how long should I wait before pouring over the top?

Thanks!


Sent from my iPhone using Tapatalk
 

· Registered
Joined
·
171 Posts
Discussion Starter · #17 ·
i'd form the whole thing then place starting w/corners keeping in mind what colby posted,,, are you placing a bonded OR unbonded overlay ? in either case, i think we'd use mechanical anchors


I’ll be pitting rebar into the sides of the existing corners with epoxy. I also have a paint on bonding agent to put over the existing pad first.


Sent from my iPhone using Tapatalk
 

· Registered
Joined
·
5,708 Posts
Question.. Should I pour the corners flush with the existing slab first, wait some time for it to set and then pour the top up 2 “? Or should I pour it all at once?

If 2 steps are better, how long should I wait before pouring over the top?

I would do it in 2 steps with 24 hours between them.
 
  • Like
Reactions: Maine1

· Super Moderator
Joined
·
24,985 Posts
If you pour it all at once it will almost certainly crack at the edges.
Pouring separately will have a better chance of not cracking but no guarantee.
Assuming you are going to put the post back in those corner positions, the concrete under them should be more than just a slab extension. It should be dug down below frost with a post hole digger.
 
1 - 20 of 24 Posts
This is an older thread, you may not receive a response, and could be reviving an old thread. Please consider creating a new thread.
Top