I plan to run 2/3 SE (copper) from the main disconnect in a front unit, through the attic and over a 5 foot covered breezeway (along side a 4x6), into the attic of another unit and down the wall cavity to the 125amp lug-only subpanel. To protect the SE cable, i plan to sleeve with 1.5" EMT over the 5' breezeway, and then again from the top plate down to the top of the sub panel (~30 inches). Is the sleeving arrangement OK and do you think i will be able to achieve 125amps with the copper SE cable?