For 15' span and the future roof in mind, you probably will need triple 2x12 beam, each 2x must be one piece, you can't join 8', and if you join them, you must have a footing and post under the joint.
Below ground post may resist racking movement but will rot faster. Above ground post will need bracing.
Permit doesn't last that long. It's best if you get the permit within a year of the work.
What youre asking are fairly significant work, and needs details that shouldn't be confirmed in a forum. You need a professional, carpenter or engineer to get the permit.
Below ground post may resist racking movement but will rot faster. Above ground post will need bracing.
Permit doesn't last that long. It's best if you get the permit within a year of the work.
What youre asking are fairly significant work, and needs details that shouldn't be confirmed in a forum. You need a professional, carpenter or engineer to get the permit.