I'm renovating an old farm house. At some point they created a room out of a porch, then much later someone added a small attic to it. The attic and newer roof are fine as is the side of the original house it's attached to, but the floor and one outside wall were rotted to the point of having to be completely removed. An engineer advised us to build a stem wall/footer around the perimeter of the room, replace the outside wall and frame a new deck for the floor.
We have the stem walls, we replaced the outside wall, now I'm dealing with the floor system. The stem wall surrounds soil (remember, this was originally a porch), so we have put down 6 mil. plastic over the soil and up all sides of the cavity created by the stem wall, stapling it to the inside edge of the new sill plates, and sill of the original house.
My question is, when I put in insulation between the floor joists, should I put in another vapor barrier? Essentially, it seems that the 6 mil. I have already would be enough, but then remembering the rule of thumb that the vapor barrier goes on the warm side of walls and floors, I'm confused. Any advice?
We have the stem walls, we replaced the outside wall, now I'm dealing with the floor system. The stem wall surrounds soil (remember, this was originally a porch), so we have put down 6 mil. plastic over the soil and up all sides of the cavity created by the stem wall, stapling it to the inside edge of the new sill plates, and sill of the original house.
My question is, when I put in insulation between the floor joists, should I put in another vapor barrier? Essentially, it seems that the 6 mil. I have already would be enough, but then remembering the rule of thumb that the vapor barrier goes on the warm side of walls and floors, I'm confused. Any advice?