Hard to describe, so I've included pics and a sketch. I have two related problems.
The footing/piers in my crawl were poured on top of the material heaped up after the foundation was complete. So leveling and installing a vapor barrier is one project. (And don't get me started as to why the other piers under the "I" beam are not centered!)
The problem footer in the picture is at a critical transition in the house, carrying the end of the "I" beam that bisects the main living area. Two problems:
(1) because it is where the access to the crawl is, the soil has been excavated around it, down to the level of the foundation footers. Either because of this (or water damage) it has also started to tip towards the back of the house (away from the well tank you can see in the pictures)
So first question is how/what procedure I might use to stabilize this?
I had thought about pouring a small footer (level with the foundation wall footer), with vertical rebar embedded. Then use narrow CBU to build a low wall. Parge. Finish with vacuuming the fines off/around the rock & then a slurry coat of mortar to keep things from moving. Since I want to preserve that access area, I thought about building this as a "U" so I can stabilize all the sides & finish with a little floor.
For this project, I am interested in any suggestions--this is something of the likes I have never done, although I have mixed concrete by hand before, & dread carrying it down into the crawl...
(2) the second problem is what I started to try to solve in the first place. (Ain't it always the way!) I have a page of the original plans that show the "I" beam running to the end of that pier, and catching the last joist coming from the back of the house, & a double joist coming from the other side, both supported by the "I" beam.
For some reason, they left the joist ledger off the end wall, so although that last joist runs tight to wall, & although it does line up with where they ended the steel, it doesn't come far enough towards the access area. The 2x8 from the other direction is single & face nailed and not supported by the I beam. (there is an extra block--you can see the new wood--that is temporary until I can redo the floor in the furnace room above the access door)
The result of these two decisions leaves the wall above this area (a bearing wall--and in fact a post for the post & beam above--with not enough support below!
Unsurprisingly, this is a spot where the roof failed, and water has leaked, etc & there is evidence that the wall has dropped a little. I've fixed the rotted floor (partially) replaced the plate and blocking above. (Roof was redone before purchase, but water ponds in that area...)
So assuming I can come up with a reasonable plan for #1, & stabilize the pier and footing, can I get away with jacking on the edge of that footing--I thought right in the center of the nailed joists--and then place a couple of 6x6 fir blocks to raise that joist combination slightly. I'm not shooting for fully level, but would like the plate of the wall above to be tight, and have the bearing wall tight to the beam it is supporting...
(of course all the wiring in the house crosses that little section--I mean why wouldn't it be hard?)
Cheers,
Dean
The footing/piers in my crawl were poured on top of the material heaped up after the foundation was complete. So leveling and installing a vapor barrier is one project. (And don't get me started as to why the other piers under the "I" beam are not centered!)
The problem footer in the picture is at a critical transition in the house, carrying the end of the "I" beam that bisects the main living area. Two problems:
(1) because it is where the access to the crawl is, the soil has been excavated around it, down to the level of the foundation footers. Either because of this (or water damage) it has also started to tip towards the back of the house (away from the well tank you can see in the pictures)
So first question is how/what procedure I might use to stabilize this?
I had thought about pouring a small footer (level with the foundation wall footer), with vertical rebar embedded. Then use narrow CBU to build a low wall. Parge. Finish with vacuuming the fines off/around the rock & then a slurry coat of mortar to keep things from moving. Since I want to preserve that access area, I thought about building this as a "U" so I can stabilize all the sides & finish with a little floor.
For this project, I am interested in any suggestions--this is something of the likes I have never done, although I have mixed concrete by hand before, & dread carrying it down into the crawl...
(2) the second problem is what I started to try to solve in the first place. (Ain't it always the way!) I have a page of the original plans that show the "I" beam running to the end of that pier, and catching the last joist coming from the back of the house, & a double joist coming from the other side, both supported by the "I" beam.
For some reason, they left the joist ledger off the end wall, so although that last joist runs tight to wall, & although it does line up with where they ended the steel, it doesn't come far enough towards the access area. The 2x8 from the other direction is single & face nailed and not supported by the I beam. (there is an extra block--you can see the new wood--that is temporary until I can redo the floor in the furnace room above the access door)
The result of these two decisions leaves the wall above this area (a bearing wall--and in fact a post for the post & beam above--with not enough support below!
Unsurprisingly, this is a spot where the roof failed, and water has leaked, etc & there is evidence that the wall has dropped a little. I've fixed the rotted floor (partially) replaced the plate and blocking above. (Roof was redone before purchase, but water ponds in that area...)
So assuming I can come up with a reasonable plan for #1, & stabilize the pier and footing, can I get away with jacking on the edge of that footing--I thought right in the center of the nailed joists--and then place a couple of 6x6 fir blocks to raise that joist combination slightly. I'm not shooting for fully level, but would like the plate of the wall above to be tight, and have the bearing wall tight to the beam it is supporting...
(of course all the wiring in the house crosses that little section--I mean why wouldn't it be hard?)
Cheers,
Dean
Attachments
-
30.2 KB Views: 331
-
47.6 KB Views: 333
-
41.1 KB Views: 294
-
33.5 KB Views: 245
-
75.4 KB Views: 355