All,
Wondering if I could get some feed back on the wiring plan for my attached garage. The garage walls are finished, so I'm running 1/2" EMT to replace all of the existing wiring and fixtures (3 ungrounded receptacles and 2 overhead ceramic bases).
The power will come from a new sub-panel that I'm installing in my basement next to the existing panel. I had been debating the sub vs service upgrade issue, but I'm not 100% comfortable that I understand the grounding implications of a service upgrade, so I'm going to go with a sub for now, as I'm doing some other work in the house, and need to use the garage for sawing, etc, and am tired of running extension cords into the house to do it.
My original plan was that the sub would be in the garage, but now I'm going to put it in the basement and start moving circuits over to it to get rid of all of the Aluminum in the house assuming that I'll upgrade the service at some point and will then move the sub elsewhere.
Anyway, my plan was to run 12 ga romex through the unfinished part of the basement to a junction box where I'll splice into 12 ga THHN that will run across the ceiling of a small finished hallway in the basement and then throughout the garage.
I'm using 12 ga. for both circuits because I figure I only need about 150' total (if that) of each color, but may end up needing to buy 500' spools to be cost effective at the local box store, so don't want to do that for both 14 and 12 ga.
Questions that come to mind:
Are there too many outlets feeding off of the GFI on the red circuit? I had heard that 5-6 was preferred. I can throw another into the mix if needed.
Is the garage door circuit ok on the lighting circuit, or should it be by itself?
The new lighting will be overhead fluorescent shop lights.
Thanks,
Mike
Wondering if I could get some feed back on the wiring plan for my attached garage. The garage walls are finished, so I'm running 1/2" EMT to replace all of the existing wiring and fixtures (3 ungrounded receptacles and 2 overhead ceramic bases).
The power will come from a new sub-panel that I'm installing in my basement next to the existing panel. I had been debating the sub vs service upgrade issue, but I'm not 100% comfortable that I understand the grounding implications of a service upgrade, so I'm going to go with a sub for now, as I'm doing some other work in the house, and need to use the garage for sawing, etc, and am tired of running extension cords into the house to do it.
My original plan was that the sub would be in the garage, but now I'm going to put it in the basement and start moving circuits over to it to get rid of all of the Aluminum in the house assuming that I'll upgrade the service at some point and will then move the sub elsewhere.
Anyway, my plan was to run 12 ga romex through the unfinished part of the basement to a junction box where I'll splice into 12 ga THHN that will run across the ceiling of a small finished hallway in the basement and then throughout the garage.
I'm using 12 ga. for both circuits because I figure I only need about 150' total (if that) of each color, but may end up needing to buy 500' spools to be cost effective at the local box store, so don't want to do that for both 14 and 12 ga.
Questions that come to mind:
Are there too many outlets feeding off of the GFI on the red circuit? I had heard that 5-6 was preferred. I can throw another into the mix if needed.
Is the garage door circuit ok on the lighting circuit, or should it be by itself?
The new lighting will be overhead fluorescent shop lights.
Thanks,
Mike
