I want to give my contractor the benefit of the doubt...thoughts?
Basics:
-less than 900 square feet of 3/4"x3" solid pre-finished maple nail down installation in a 5year old house purchased end of May and waiting to move in.
-Contract and deposit $7k of $12,500 (so he can order the wood floors) signed/paid on 5/29 paid with floor store owner.
-says 6/9 to start prep work. 6/11 floors scheduled to arrive/sit in house to acclimatize.
-6/13 planned to start install (says 2-3 days, 2-3 guys...1 guy so far, but figure better one craftsman than adding a couple of day laborers to the mix)
-6/12 p.m. (day late, not bad...) *most* of wood floors delivered 34 boxes
-*later found out 10 more boxes; I had to ask where they were 3 days later, he did not mention the shortage when delivered and I couldn't help but wonder if he was keeping them in case there was not as much waste as expected and could then keep them or return them and keep the refund for the materials for himself.
-last told the additional boxes would be put in house yesterday 6/16 (not done, no call, so I call this a.m. and says they will be delivered today, not done, called 5:45pm says he is busy before I can ask a question and says that he would call me back in a *few minutes* but still has not called so far after 2 1/2 hours). These 10 boxes also need to acclimatize before installing them.
-Installer is still on the prepping stage (no wood nailed down) but may be close to being done prepping and seems to be taking his time and preparing it properly.
-Also no sign of the other materials (especially stair nosing).
-Is this normal? I do not want to be mean period..but especially if it led to him walking out on the job with my $7k and the rest of my wood (or doing a poor job).
-I think I am patient, however it does look to be done (if I am lucky) by the following weekend 6/28 which would be a month after contract/paying $7k and 15 days after install was originally scheduled to start (versus 2-3 days). Of course I am excited to move in to my new home and I am paying a mortgage for a house that I can't live in yet (I know it is to be expected, but this long for less than 900 square feet of installation?)
-Again I am still giving him the benefit of the doubt, but am I being too nice or gullible?
-I did not go with the lowest bid (which was lumber liquidators and who only asked for 50% of material cost to order materials but their contract with "The Home Store" does not require a dime in labor until the job is done).
*My feeling tonight is to call tomorrow morining, stay friendly, tell him I understand delays are normal and tell him I will check back on Friday, and need to move in by next weekend. Staying friendly so that he feels he has a reason (keeping a happy, referring customer) to finish the job and finish it properly.
This is my first dealing with a contractor, so yes I am newbie. Sorry so long.
Basics:
-less than 900 square feet of 3/4"x3" solid pre-finished maple nail down installation in a 5year old house purchased end of May and waiting to move in.
-Contract and deposit $7k of $12,500 (so he can order the wood floors) signed/paid on 5/29 paid with floor store owner.
-says 6/9 to start prep work. 6/11 floors scheduled to arrive/sit in house to acclimatize.
-6/13 planned to start install (says 2-3 days, 2-3 guys...1 guy so far, but figure better one craftsman than adding a couple of day laborers to the mix)
-6/12 p.m. (day late, not bad...) *most* of wood floors delivered 34 boxes
-*later found out 10 more boxes; I had to ask where they were 3 days later, he did not mention the shortage when delivered and I couldn't help but wonder if he was keeping them in case there was not as much waste as expected and could then keep them or return them and keep the refund for the materials for himself.
-last told the additional boxes would be put in house yesterday 6/16 (not done, no call, so I call this a.m. and says they will be delivered today, not done, called 5:45pm says he is busy before I can ask a question and says that he would call me back in a *few minutes* but still has not called so far after 2 1/2 hours). These 10 boxes also need to acclimatize before installing them.
-Installer is still on the prepping stage (no wood nailed down) but may be close to being done prepping and seems to be taking his time and preparing it properly.
-Also no sign of the other materials (especially stair nosing).
-Is this normal? I do not want to be mean period..but especially if it led to him walking out on the job with my $7k and the rest of my wood (or doing a poor job).
-I think I am patient, however it does look to be done (if I am lucky) by the following weekend 6/28 which would be a month after contract/paying $7k and 15 days after install was originally scheduled to start (versus 2-3 days). Of course I am excited to move in to my new home and I am paying a mortgage for a house that I can't live in yet (I know it is to be expected, but this long for less than 900 square feet of installation?)
-Again I am still giving him the benefit of the doubt, but am I being too nice or gullible?
-I did not go with the lowest bid (which was lumber liquidators and who only asked for 50% of material cost to order materials but their contract with "The Home Store" does not require a dime in labor until the job is done).
*My feeling tonight is to call tomorrow morining, stay friendly, tell him I understand delays are normal and tell him I will check back on Friday, and need to move in by next weekend. Staying friendly so that he feels he has a reason (keeping a happy, referring customer) to finish the job and finish it properly.
This is my first dealing with a contractor, so yes I am newbie. Sorry so long.