My 17kw generac generator is currently picking up 4 circuits from my main panel, and 8 circuits (all 15 or 20a) from my sub panel. When this was originally installed, there were 8 - 12gauge thhn wires run in 3/4 seal tite from my generator panel to my sub panel. The seal tite ran through the exterior wall where my main panel is located, underground, and then back in the house where my sub panel is, about 30' away. Now that my basement is gutted. I want to run this inside the house. Can I run all 8 - 12gauge thhn wires in a 3/4 flexible metal conduit? I looked up conduit fill, and that seems fine. What concerns me is the derating. Should I run 2 -3/4" conduits and run 4 in each or am I ok with all 8 in one? All 8 wires will be carrying a load. Thank you!!