I'm installing two floor drains in my 32 x 44' thickened edge slab. Slab is still not poured and I still need to add 5-6" of stone inside my forms before I'm ready to pour. Should I wait until stone is in place before I install drains or try and add them first?

I know I'd have to dig part of a trench in the stone but stone trench would also help hold everything in place.
 

· Concrete & Masonry
Joined
·
4,069 Posts
I'd get enough stone in that they're full supported, and everything around and below them is compacted already. Really, either way will work, a little trenching in compacted gravel never killed anybody.......
 