One of my competators got the bid to build a 20' tall garage right down the street from me, I lost the job over $100.00 and suggesting he go with a 36" door instead of a 2-8.
We where working on another house almost right across the street so we could see what was going on.
He gets all the walls up but never installed any of the sheathing on the walls.
I see the truck roll up with all the trusses with a crane right behind him.
They went ahead and set all the trusses and quit for the day.
No cross bracing, no sheathing, looked like a stack of cards.
Want to guess what happened when a thunder storm rolled through that night with 40 MPH winds?
The whole thing was one big pile the next day.
The bad part is he had the same thing happen to him before on another job.
We where working on another house almost right across the street so we could see what was going on.
He gets all the walls up but never installed any of the sheathing on the walls.
I see the truck roll up with all the trusses with a crane right behind him.
They went ahead and set all the trusses and quit for the day.
No cross bracing, no sheathing, looked like a stack of cards.
Want to guess what happened when a thunder storm rolled through that night with 40 MPH winds?
The whole thing was one big pile the next day.
The bad part is he had the same thing happen to him before on another job.