In reference to this thread: http://www.diychatroom.com/f18/max-cable-length-between-padmounted-transformer-structures-398362/
I have reconfigured my site layout so that the max cable run to any planned structure is about 120 ft. The site layout can be seen here: http://i.imgur.com/FLW8BjW.jpg
I would like to have a shop someday and be able to fill it up with equipment I get at auction, which means it will likely be 3 phase. I also want to have an overhead 5-7.5 ton crane, which will be 3 phase.
There is 3 phase available at the road, and I'd need to have a transformer installed with ~525 ft of HV cable.
The 3 ph options are:
1) 4-wire 208 wye/120 300 kVA max load
2) 4-wire 208 wye/120 1000 kVA max load
3) 4-wire 480 wye/277 500 kVA max load
4) 4-wire 480 wye/277 2500 kVA max load
I have a few questions:
1) The HV cable from the road to the transformer, from single ph to 3 ph, that becomes 3 cables? So likely 3X the cost of installation? I was quoted $17 ft for the power company to install the transformer and lay the cable in a trench I dig and backfill myself. That's 525 X $17 = $8,925. I have asked the power company about 3 ph costing, but they have not answered me yet. Would it really be ~$27k? Would I also pay a higher commercial rate for the power?
2) Once I have a 3 ph transformer installed, how do I get single phase out of it for my house etc? Would each structure need a separate transformer to get single phase? Or would I have an out building with a transformer in it to supply all the structures with single phase? Or do they make 3ph transformers that have a single ph tap? Delta-WYE transformer would give me all options?
3) Is it wiser to just have single ph installed and then if I get 3 ph equipment someday buy a converter?
I have reconfigured my site layout so that the max cable run to any planned structure is about 120 ft. The site layout can be seen here: http://i.imgur.com/FLW8BjW.jpg
I would like to have a shop someday and be able to fill it up with equipment I get at auction, which means it will likely be 3 phase. I also want to have an overhead 5-7.5 ton crane, which will be 3 phase.
There is 3 phase available at the road, and I'd need to have a transformer installed with ~525 ft of HV cable.
The 3 ph options are:
1) 4-wire 208 wye/120 300 kVA max load
2) 4-wire 208 wye/120 1000 kVA max load
3) 4-wire 480 wye/277 500 kVA max load
4) 4-wire 480 wye/277 2500 kVA max load
I have a few questions:
1) The HV cable from the road to the transformer, from single ph to 3 ph, that becomes 3 cables? So likely 3X the cost of installation? I was quoted $17 ft for the power company to install the transformer and lay the cable in a trench I dig and backfill myself. That's 525 X $17 = $8,925. I have asked the power company about 3 ph costing, but they have not answered me yet. Would it really be ~$27k? Would I also pay a higher commercial rate for the power?
2) Once I have a 3 ph transformer installed, how do I get single phase out of it for my house etc? Would each structure need a separate transformer to get single phase? Or would I have an out building with a transformer in it to supply all the structures with single phase? Or do they make 3ph transformers that have a single ph tap? Delta-WYE transformer would give me all options?
3) Is it wiser to just have single ph installed and then if I get 3 ph equipment someday buy a converter?