So due to some issues being raised in my rough inspection last Weds, and the next opportunity for reinspection being this coming Weds, I have part of my house disconnected. Let me see if I can whip up a quick diagram then explain:
So in the diagrams you'll see 3 configuraitons: current, interim and final. My question is if the interim configuration violates anything that would put my inspection at risk. I'm sure I'll have to explain that I intend to feed the 100A from the 200A panel, but until the POCO removes power from the old meter socket I cannot disconnect the 100A panel feeder.
The garage panel probably doesn't even figure into this, but it's part of the permit and in case anyone followed the other threads, I was able to reconnect both ends with the conduit without having to splice. (side note: I wanted to splice 2/0 SEU (which I already had) in anticipation that avoiding a conduit run would be cheaper, and that a conduit run would leave my cables too short. As it turns out, 2/0 was too large for the 100A breaker, and the materials needed to splice were much more expensive than a PVC conduit run.
So at any rate, the 200A panel was installed by me as a sub and runs new circuits for the kitchen and upstairs bedrooms. We've been operating on extension cords because I disconencted the feeder expecting to sail through rough inspection last Weds and get the POCO scheduled to bring in 200A.
Back to the diagram:
Current setup:
- 100A comes through the old meter socket into 100A main panel.
- 60A breaker feeds the 200A panel, this panel has circuits for kitchen and upstairs
At the point of rough inspection last weds:
- 100A comes through the old meter socket into 100A main panel.
- 200A panel is not fed by any live panel, cables disconnected at both ends
- New 200A socket is wired to 200A panel main breaker
- Garage subpanel fed from 100A breaker on 200A panel (breakers at off on both ends, no circuits connected yet in garage)
Proposed interim configuration:
- 100A comes through the old meter socket into 100A main panel.
- 200A panel is fed by 60A breaker in 100A main panel connected to a 60A breaker in the 200A panel
- New 200A socket is wired to 200A panel main breaker, main breaker is kept OFF
- Garage subpanel fed from 100A breaker on 200A panel (breakers at off on both ends, no circuits connected yet in garage)
After passing rough inspection when the POCO comes out, I will just turn off all main breakers and breakers associated with feeders for any panel. Hopefully either myself or wife can be present to turn on something that feeds the refrigerator at least.
Final configuration:
- 200A comes through the new 200A meter socket into 200A panel which is now main
- Old 100A panel is fed from the 200A panel from a 60A breaker which connects to the 100A main breaker on the 100A panel
- Garage subpanel fed from 100A breaker on 200A panel, with rough inspection passed I can insulate and drywall, paint the wall, install receptacles, put up pegboard over the drywall with furring strips, call for final and live happily ever after.
Any issues with that plan?
So in the diagrams you'll see 3 configuraitons: current, interim and final. My question is if the interim configuration violates anything that would put my inspection at risk. I'm sure I'll have to explain that I intend to feed the 100A from the 200A panel, but until the POCO removes power from the old meter socket I cannot disconnect the 100A panel feeder.
The garage panel probably doesn't even figure into this, but it's part of the permit and in case anyone followed the other threads, I was able to reconnect both ends with the conduit without having to splice. (side note: I wanted to splice 2/0 SEU (which I already had) in anticipation that avoiding a conduit run would be cheaper, and that a conduit run would leave my cables too short. As it turns out, 2/0 was too large for the 100A breaker, and the materials needed to splice were much more expensive than a PVC conduit run.
So at any rate, the 200A panel was installed by me as a sub and runs new circuits for the kitchen and upstairs bedrooms. We've been operating on extension cords because I disconencted the feeder expecting to sail through rough inspection last Weds and get the POCO scheduled to bring in 200A.
Back to the diagram:
Current setup:
- 100A comes through the old meter socket into 100A main panel.
- 60A breaker feeds the 200A panel, this panel has circuits for kitchen and upstairs
At the point of rough inspection last weds:
- 100A comes through the old meter socket into 100A main panel.
- 200A panel is not fed by any live panel, cables disconnected at both ends
- New 200A socket is wired to 200A panel main breaker
- Garage subpanel fed from 100A breaker on 200A panel (breakers at off on both ends, no circuits connected yet in garage)
Proposed interim configuration:
- 100A comes through the old meter socket into 100A main panel.
- 200A panel is fed by 60A breaker in 100A main panel connected to a 60A breaker in the 200A panel
- New 200A socket is wired to 200A panel main breaker, main breaker is kept OFF
- Garage subpanel fed from 100A breaker on 200A panel (breakers at off on both ends, no circuits connected yet in garage)
After passing rough inspection when the POCO comes out, I will just turn off all main breakers and breakers associated with feeders for any panel. Hopefully either myself or wife can be present to turn on something that feeds the refrigerator at least.
Final configuration:
- 200A comes through the new 200A meter socket into 200A panel which is now main
- Old 100A panel is fed from the 200A panel from a 60A breaker which connects to the 100A main breaker on the 100A panel
- Garage subpanel fed from 100A breaker on 200A panel, with rough inspection passed I can insulate and drywall, paint the wall, install receptacles, put up pegboard over the drywall with furring strips, call for final and live happily ever after.
Any issues with that plan?
Attachments
-
87.6 KB Views: 737