concrete slab


hello all, I am in the midst of building a concrete slab foundation for my new garage. I have dug out the site, put up my boards, and have dug the trench for my footers around ther perimeter, but what I need to know is how to backfill on the outside of the boards so that the cement will not flow out underneath them. There is a wide gap at the back corner where the ground landscape is very low in comparrison to the other side. I also need to know how much cement to order if the pad itself is going to be 6 inches thick, but i have to account for the cement which will fill the trenches around the perimeter.
GarageGuy09 is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 05-19-2009, 09:32 PM   #2
Old School
 
Willie T's Avatar
 
Join Date: Jan 2009
Location: St. Petersburg, FL Minds of moderate caliber ordinarily condemn everything which is beyond them.
Posts: 3,634
Rewards Points: 2,000
Default


Quote:
Originally Posted by GarageGuy09 View Post
hello all, I am in the midst of building a concrete slab foundation for my new garage. I have dug out the site, put up my boards, and have dug the trench for my footers around ther perimeter, but what I need to know is how to backfill on the outside of the boards so that the cement will not flow out underneath them. There is a wide gap at the back corner where the ground landscape is very low in comparrison to the other side. I also need to know how much cement to order if the pad itself is going to be 6 inches thick, but i have to account for the cement which will fill the trenches around the perimeter.
The math is:

Length in feet x width in feet x .5 (for 6" slab), then the answer is divided by 27 to = cubic yards.

If it is a larger slab, figure your whole "trench" (it's a footing) area this same way, right from the top to the bottom. You do it this way on a big slab (especially 6") because it is too easy to underestimate on a larger slab.

You can be more precise and calculate closer on a small slab...

If it is a small slab, figure your "trench" area only from 4" to 6" lower than the top of the slab to the bottom. In other words, don't count in most of the part that the 6" slab will be occupying above the "trench".

Backfilling: Just shovel the dirt up against the outsides of the boards, and let it go down into the gap... Stomp it in down there. Now pack it back into the gap from the inside with your hand or feet. If there is some still inside the form, shave it off neatly with a flat nosed shovel. If there are some cupped holes toward the outside, don't worry about that little bit of under flow... as long as you have a fair amount of dirt tightly banked up there to stop the concrete. The dirt, itself, will act like a form board.
__________________
"True eloquence consists in saying all that is necessary, and only that which is."
François Duc de La Rochefoucauld
Willie T

Last edited by Willie T; 05-19-2009 at 10:07 PM.
Willie T is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 05-19-2009, 09:45 PM   #3
 
Join Date: Mar 2009
Posts: 4
Rewards Points: 10
Default

thanks


the slab is going to measure 22feet long by 18 feet wide, with a top depth of 6 inches, not including the trenches ie footings, this works out to 7.3 cubic yards, now how would i calculate the footings?
GarageGuy09 is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 05-19-2009, 09:54 PM   #4
Old School
 
Willie T's Avatar
 
Join Date: Jan 2009
Location: St. Petersburg, FL Minds of moderate caliber ordinarily condemn everything which is beyond them.
Posts: 3,634
Rewards Points: 2,000
Default


Quote:
Originally Posted by GarageGuy09 View Post
the slab is going to measure 22feet long by 18 feet wide, with a top depth of 6 inches, not including the trenches ie footings, this works out to 7.3 cubic yards, now how would i calculate the footings?
Width of the trench is pretty clear to see and measure... probably about 16"? (1.333 feet)

The length will be the running length, all the way around your house, couple hundred feet?

And the depth? What? About 42" (3.5 feet) in the North, and maybe 24" (2 feet) in the South? since this is a big pour, I wouldn't measure short. Take the measurement of the depth all the way from the top of the form board, right down to the dirt at the bottom.

Same formula: L x W x D (all done in "feet") divided by 27.

It is true you could end up with a little extra concrete. But far better a little over than find yourself short. For the chance of some extra left over, go ahead and form for that little garbage can pad you've always wanted... or that pad just outside the shop door. Be prepared not to waste the extra.
__________________
"True eloquence consists in saying all that is necessary, and only that which is."
François Duc de La Rochefoucauld
Willie T

Last edited by Willie T; 05-19-2009 at 10:04 PM.
Willie T is offline   Reply With Quote
Old 05-20-2009, 12:00 AM   #5
Concrete & Masonry
 
Join Date: Nov 2008
Location: Wisconsin
Posts: 3,740
Rewards Points: 426
Default


Quote:
Originally Posted by GarageGuy09 View Post
hello all, I am in the midst of building a concrete slab foundation for my new garage. I have dug out the site, put up my boards, and have dug the trench for my footers around ther perimeter, but what I need to know is how to backfill on the outside of the boards so that the cement will not flow out underneath them. There is a wide gap at the back corner where the ground landscape is very low in comparrison to the other side. I also need to know how much cement to order if the pad itself is going to be 6 inches thick, but i have to account for the cement which will fill the trenches around the perimeter.

If there's a large gap left under the boards, you're not done forming yet. Fill that gap in with more lumber to save on concrete.
jomama45 is online now   Reply With Quote
Old 05-20-2009, 08:27 PM   #6
 
Join Date: Mar 2009
Posts: 4
Rewards Points: 10
Default

so


so I fill the gaps with more boards, brace it, then backfill over it to meat the top of the forming boards, then once the concrete has cured, dig it out and pull the boards off? Seems like a lot of work for something that has to be taken apart again. Are these steps correct?
GarageGuy09 is offline   Reply With Quote
Sponsored Links
Advertisement
 
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Cork or engineered wood over concrete slab w/ Radiant heat, HELP! newdyier Flooring 9 11-04-2008 05:11 PM
Extending Concrete Patio Slab bobo Building & Construction 6 04-17-2008 01:17 PM
Filling hole in carport (concrete slab) chaddihimself Building & Construction 2 08-10-2007 01:50 PM
Remodel over sloped concrete slab PSL_Hokie Building & Construction 11 07-11-2007 06:14 PM
Concrete slab weeps moisture dale h Flooring 2 04-30-2005 11:29 AM