Hello,


we are beginning to build the deck Saturday...the High is 35 and the low is 23


how concerned should I be with the concrete footings going in that day if accelerator is used?


I've heard it being very frowned upon but I have also heard of no issues with concrete setting below freezing....


it will also be quicksetting concrete and not a large surface area, just deck footings


thoughts? thanks
ny86yanks is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 02-06-2019, 07:53 PM   #2
World's Tallest Midget
 
Mort's Avatar
 
Join Date: Nov 2008
Location: Everett, WA
Posts: 1,460
Rewards Points: 696
Default

Re: concrete deck footings...below freezing question


I wouldn’t bother with accelerator. It just helps the initial set come faster, it doesn’t gain strength any faster. I’d wait at least 7 days before subjecting it to any load, unless you have concrete using Type III cement (hi-early).

As far as the temperature, eh, I’ve poured in colder. Just cover it with blankets after initial set to keep as much heat in as possible.
__________________
I hate signatures.
Mort is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 02-06-2019, 08:02 PM   #3
Member
 
Join Date: Feb 2018
Posts: 76
Rewards Points: 152
Default

Re: concrete deck footings...below freezing question


thank you

the deck footings will be down about three feet so just cover the holes after?
ny86yanks is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 02-06-2019, 08:25 PM   #4
World's Tallest Midget
 
Mort's Avatar
 
Join Date: Nov 2008
Location: Everett, WA
Posts: 1,460
Rewards Points: 696
Default

Re: concrete deck footings...below freezing question


It’d be best to cover them as closely as possible, like with a blanket, but as long as they’re covered that’s better.
ny86yanks likes this.
__________________
I hate signatures.
Mort is offline   Reply With Quote
Old 02-07-2019, 04:21 AM   #5
Newbie
 
Join Date: Feb 2019
Posts: 8
Default


Nailed it Mort. I have to recommend that you try to get to that 4 feet. Just to be safe. Concrete blankets aren’t cheap but at least use a 6 mil BLACK poly and keep it covered as long as you can.
DZthompsen is offline   Reply With Quote
Sponsored Links
Advertisement
 
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Filling voids under concrete pool deck Ralph III Concrete, Stone & Masonry 9 01-28-2019 09:47 PM
Offsetting deck "posts" on footings red92s Building & Construction 2 08-10-2017 08:49 AM
Issue with deck flashing. How concerned should I be? pasalott Building & Construction 2 09-24-2016 10:18 AM
Concrete ourcrop/bunker repair under deck BelgianBillie Concrete, Stone & Masonry 5 07-21-2015 12:43 PM
new second story deck stair, platform question walt1122 Building & Construction 10 11-12-2010 10:52 AM




Top of Page | View New Posts