Hi All:

I am in the process of installing the DWV system in our house that I am building. The house if framed and the outside is all done. I have 2 - 3" vents poked out of the roof and there is a 4" septic pipe in the basement leading out to the tank and division box then into the drain field.

I think I am going over board with this installation and would appreciate any comments and suggestions. I have calculated the drain units as well as the fixture units and have decided to run separate 2" vent lines for each trap which connect as close as possible to the trap. All these vents which is a total of 12 will all tap into a 3" header that will run across the attic via sanitary "T"s. At each end of the 3" header I will install a "T" with a clean out and tie each end into the 3" pipe that is poked through the roof.

As for the drain all the drains run into the basement and I will install a clean out "T" for each drain then plumb it into the 4" header with sanitary "T"s. This 4" header will terminate into the septic pipe. I will also be installing a 3" vent from this 4" drain header to the 3" vent header.

So there it is. I think I might have over designed things. Okay l appreciate your comments and suggestions and the time to respond.
Sincere Thanks
Joe

joebart is offline   Reply With Quote
Old 01-29-2009, 06:19 AM   #2
Member
 
Join Date: Dec 2008
Location: Wilmington, DE
Posts: 3,118
Rewards Points: 2,000
Default

Installing DWV system new construction


What does your inspector think??? Overdesigning is not necessarily a bad thing. Usually fewer chances for problems, and more vents are definitely better that not enough.

Just Bill is offline   Reply With Quote
Old 01-29-2009, 07:45 AM   #3
Newbie
 
Join Date: Jan 2009
Posts: 6
Rewards Points: 10
Default

Installing DWV system new construction


Hi Bill:

The inspector loves it! I want to be sure to do a good job with this installation. I also wanted to know what my peers think!

I attended a night class on plumbing which was helpful. I then purchased some books which were also helpful and away I went. As I'm doing the work I am coming up with all kinds of questions so I dip into the books and make sure I understand the intent and go from there. There is one thing I am not 100% sure of and thats cleanouts. I will be installing a cleanout at the bottom of each drain pipe before it goes into the drain header or should they be positioned as close to the trap as possible? Naturally I would not put a cleanout in the finished areas.

Thanks for your comment Bill.
joebart is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
installing new bathtub, secure using construction adhesive or mortar? bsd Plumbing 24 03-05-2009 01:47 PM
Sprinkler System - Installing Valve Box tazmajazz Plumbing 3 01-06-2009 09:14 AM
installing a split system Jacques HVAC 6 07-10-2008 08:50 AM
Is 1/2 Pex more restrictive than 1/2 copper? twilightcall Plumbing 19 06-24-2008 07:32 AM
Installing a mini split ductless system agenkin HVAC 1 06-14-2008 09:33 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.