Old 05-13-2009, 03:20 PM   #1
Newbie
 
Join Date: May 2009
Posts: 24
Rewards Points: 10
Question

flange 1/2 in. above finished floor- what to do


Thanks so much for the advice on this forum; it has gotten me 95% of the way through this bathroom remodel!

I replaced the waste pipes and flange and then installed a new subfloor, backboard, and laid and grouted the ceramic tile. My problem is that the flange sits about a half inch above the finished floor. I have already drilled through the tile to secure the flange to the floor but cannot get it to sit directly on top of the floor. Do I have to rip up everything and start all over with new lengths of waste pipes??? How else can I remedy this situation?

Advertisement

frgwtchr is offline   Reply With Quote
Old 05-13-2009, 05:39 PM   #2
Newbie
 
Join Date: May 2009
Location: newton county, missouri
Posts: 2
Rewards Points: 10
Default

flange 1/2 in. above finished floor- what to do


congrats on doin the job yourself to this point. when you had your subfloor in place and before you tiled , did you notice the flange being higher than the sub?? if i had i would have layed one more piece of 3/4 plywood to the floor. it cant hurt and certainly ads stability for the tile long as you cross lay it . then your flange would be 1/4 in below which is perfect for a wax ring.

in other words, sorry, but to my knowledge , i would be taking up the tile and adding more subfloor.

Advertisement

ssweeney is offline   Reply With Quote
Old 05-13-2009, 05:47 PM   #3
JDC
Plumbing Contractor
 
JDC's Avatar
 
Join Date: Mar 2008
Location: Cincinnati, OH
Posts: 392
Rewards Points: 250
Default

flange 1/2 in. above finished floor- what to do


Go to a plumbing supply house and buy a marble slab made specifically for this situation. You will need to cut spacers to go between the bottom of the flange and the tile floor. I routinely just cut 1/2" copper to length for the 4 screws. (ie four 1/2" pieces of 1/2" copper to bridge the space between your flange and floor). The marble slab comes with the flange hole already cut in it. Should remedy your problem easily.

BTW 1/4" below finished floor is NOT perfect for the flange. the bottom of the flange should sit ON TOP of the finished floor.
JDC is offline   Reply With Quote
Old 05-13-2009, 10:34 PM   #4
Member
 
Join Date: Mar 2009
Posts: 780
Rewards Points: 500
Default

flange 1/2 in. above finished floor- what to do


The first thing to do is measure the inset on the bottom of the toilet, it may be enough to work with the flange "high. If not a toilet spacer can be added.
hayewe farm is offline   Reply With Quote
Old 05-14-2009, 10:23 AM   #5
Member
 
Join Date: Sep 2006
Posts: 1,670
Rewards Points: 1,000
Default

flange 1/2 in. above finished floor- what to do


Closet flanges are made to be attached to the floor. If not, any movement of the toilet could break the flange or even the piping. If you can access the piping from under the toilet, I would cut the pipe to the correct length and use a No-hub or Fernco coupling to reconnect the pieces.
__________________
If you have never made a mistake, you haven't done much.
majakdragon is offline   Reply With Quote
Old 05-14-2009, 09:03 PM   #6
Newbie
 
Join Date: May 2009
Posts: 24
Rewards Points: 10
Smile

flange 1/2 in. above finished floor- what to do


well after searching and searching for this marble toilet slab thing and having no success I went up through the ceiling on the first floor under the bathroom to see what I could do. Because of the tight spacing and the difficulty in get a saw in the cut the pipes and start over I decided to chip away the tile ans the backer board underneath a little at a time until I could push the flange further down. Then I realized that the flange (not the floor) was actually not level so one side touches the floor and one side is about and 1/8 of an inch off the floor. I decided to run with it and see what happens. I just don't have the energy to start all over right now. So I screwed everything down, set the wax ring and the toilet and so far so good. Three flushes and no sign of leaks while watching through the hole in the ceiling underneath.

I did notice that a bit of the wax came up through the holes on the toilet where it bolts to the flange. Is that normal or cause for alarm?

I definately learned a lot from doing this from start to finish. i like the member who quotes "if you haven't made any mistakes, you haven't learned anything". Thanks again for all your help even if you didn't know you were giving it to me
frgwtchr is offline   Reply With Quote
Old 05-15-2009, 07:29 AM   #7
JDC
Plumbing Contractor
 
JDC's Avatar
 
Join Date: Mar 2008
Location: Cincinnati, OH
Posts: 392
Rewards Points: 250
Default

flange 1/2 in. above finished floor- what to do


Wax squeeze out through the bolt holes is nothing to be alarmed about.

I surprised you couldnt find a marble slab though. These are a stock item at every plumbing supply house around my area.

Advertisement

JDC is offline   Reply With Quote
Reply

Tags
bathroom tub , flooring , screw , toilet flange , wax ring


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Tiling around tub with very wide flange petsparkle Kitchen & Bath Remodeling 3 04-20-2009 04:53 PM
Closet flange: flush with finished floor, on on top of? rjhaleymd Plumbing 4 11-20-2008 07:43 PM
cast iron flange Jrebhun Plumbing 2 09-06-2008 01:45 PM