okay, so here is another conundrum:

i left an 8x12-in rectangular opening in concrete under where the bath tub drain hole is supposed to be. the 1.5-in pipe ends about a foot below the surface in the middle of the hole, i.e. is ready to get a P-trap attached to it.

once i set the framing around the supposed tub so that i can fit the tub, is there a trick to how to calibrate the P-trap, i.e. adjust the length of the protruding pipe. seems to me like it would be simply trial and error but was wondering if you all pros would know of a quicker and preciser way ?

thanks,

- a -

amakarevic is online now   Reply With Quote
Old 02-05-2008, 01:10 PM   #2
remodeling pro
 
Join Date: Sep 2006
Posts: 1,399
Default

calibrating a bath tub P-trap set in concrete


That's about it, just dry fit together and cut lengths as needed. Put registration marks, a line with a Sharpie or such, on both pieces of fittings that have to be glued at a rotated position.


Last edited by troubleseeker; 02-05-2008 at 06:39 PM.
troubleseeker is offline   Reply With Quote
Old 02-05-2008, 01:12 PM   #3
Member
 
Join Date: Apr 2007
Posts: 2,243
Default

calibrating a bath tub P-trap set in concrete


that was fast
amakarevic is online now   Reply With Quote
Old 02-05-2008, 05:42 PM   #4
Master Plumber
 
Join Date: Jan 2007
Location: Texas
Posts: 169
Default

calibrating a bath tub P-trap set in concrete


The p-trap should be on the other end of that pipe lower in the ground as the p-trap has a vertical pipe coming in and a horizontal pipe coming out. In other words the p-trap should be on before you pour concrete.
jpplumber is offline   Reply With Quote
Old 02-05-2008, 06:38 PM   #5
remodeling pro
 
Join Date: Sep 2006
Posts: 1,399
Default

calibrating a bath tub P-trap set in concrete


Quote:
Originally Posted by jpplumber View Post
The p-trap should be on the other end of that pipe lower in the ground as the p-trap has a vertical pipe coming in and a horizontal pipe coming out. In other words the p-trap should be on before you pour concrete.
That is true. I assummed that he was referring to making up the drain/overflow assembly to the stub up, since he has an existing slab.
troubleseeker is offline   Reply With Quote
Old 02-05-2008, 10:16 PM   #6
Member
 
Join Date: Apr 2007
Posts: 2,243
Question

calibrating a bath tub P-trap set in concrete


you are not understanding me.

how can i have the p-trap on before i know EXACTLY where the tub will be ? and i cannot do that before the concrete is ready and the framing has been set up.

a book that i have suggests that, when pouring concrete, i leave an 8x12 opening in concrete right below the tub drain hole. that is what i did. the PVC DWV pipe penetrates within that rectangle (horizontal, of course) about a foot below the concrete surface, i.e. is ready to have a p-trap mounted on exactly as you are describing. the pipe portion penetrating into the rectagular frame by about 3-4 in. i may need to cut off 2-3 in depending on the EXACT position of the tub.

make sense ??
amakarevic is online now   Reply With Quote
Old 02-05-2008, 10:48 PM   #7
Journeyman Plumber
 
Ron The Plumber's Avatar
 
Join Date: Jun 2006
Location: Eugene, Oregon
Posts: 1,994
Default

calibrating a bath tub P-trap set in concrete


Measure to center of tub drain, that is center from the side wall, now 99% of the time the trap will line up on the very edge of the inside wall, then make up the drain for the tub once you get lined up.

If you have to offset to the tub drain tee or down to the trap, it's ok to do an offset.
__________________
Fix it right the first time, so you won't have to fix it a 2nd time.

2008 Oregon Specialty Plumbing Codes
Ron The Plumber is offline   Reply With Quote
Old 02-05-2008, 10:56 PM   #8
Master Plumber
 
Join Date: Jan 2007
Location: Texas
Posts: 169
Default

calibrating a bath tub P-trap set in concrete


Sorry I misunderstood. You are right, I thought the pipe was coming up vertically, and the p- trap on the bottom of the vertical pipe, but yours sounds like it is going horizontal to a sanitary tee that probably has a vent. So just figure out where the waste and overflow drain will end up before you cut the horizontal pipe and glue the p-trap. You will be able to swing the p-trap (where the street 90 connects to the "u" portion of the trap) to find the right spot before you glue it all up.


Last edited by jpplumber; 02-05-2008 at 10:59 PM.
jpplumber is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Sleeve options for plumbing through concrete? Bruce L Plumbing 6 06-14-2008 09:38 AM
Complex challenge with bath exhaust fan - need help with solution! Honest Bill Electrical 6 11-02-2007 02:52 PM
new concrete floor next to old concrete floor mattroos Building & Construction 10 08-28-2007 01:32 PM
Need Help with double bath sink trap after remodel cmontel Plumbing 13 12-03-2006 06:06 PM
Need to expand existing concrete pad for A/C unit miketegra Building & Construction 2 07-03-2005 10:27 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.