DIY Home Improvement Forum banner

Basement Bathroom Rough-in questions

32K views 17 replies 13 participants last post by  ”Hammer down” 
#1 ·
First off, I have been lurking around here off and on for the past year and really love this site. Everybody here seems very helpful and forthcoming, that's awesome! Here's my situation:

I am currently in the mid-stage of finishing my basement and am ready to work on the bathroom plumbing. I am on a septic system and the house does not have a sump pit. I am very fortunate to have a super-dry basement!

I plan on installing a sink/vanity, toilet and, tub/shower combination. I snapped some pictures of what I currently have in the way of roughed in piping.

I have been told by a reputable local plumber that the toilet flange will have to be moved out from the wall a few inches to accommodate a toilet due to the fact that the original plumber put the pipe to close to the wall. He also told me that the shower/tub drain will have to be moved as well for the same reasons.

Here are my questions:

#1 - What is the "Mystery Pipe" (labeled "Not Sure") located to the left of the Shower Drain pipe? Is this an overflow drain for a tub?
#2 - How do I vent this bathroom?

Any help would be greatly appeciated, thanks!
 

Attachments

See less See more
2
#2 ·
First, I'm not a pro plumber, just a long-time DIYer.
It appears to me that the "not sure" is an optional drain for a tub/shower unit, and the shower drain is for a "just a shower only" option. One or the other would remain capped off.
You've pegged the vanity sink and toilet drains.
The toilet drain should be centered usually at least 12" off of the finished wall (12.5" off framing with half-inch sheetrock to be added for instance). You may be breaking up concrete, replumbing a bit and re-cementing around the toilet if it isn't, or looking at a 10" center toilet, depending upon the distance now.
Remember that the flange itself should sit flush on top of the finished floor level with only the thickness of the flange itself above finished floor level. The flange should be bolted (Tapcons) to the concrete floor, and the toilet bolted to the flange, for the wax ring to seal properly.
If all of this rough-in plumbing passed inspection "back when", it all should already be vented properly. You just need to add the sink and shower traps and the toilet.
Good Luck!
Mike
 
#3 ·
Also not a pro. If you can ask the builder, it'd be better than guessing. First off, your "not sure" is quite possibly your vent. Again, not a pro, but, I've never seen a rough in for both a shower and tub in a room that can't hold them both. That's why I think it's the vent. What's in the ceiling? My builder roughed in the vent through the roof. However, it wasn't connected until I finished the bathroom. Lastly, what did your plumber say? Did he make a site inspection or just go by the pictures?
 
#5 ·
I can't read any of your labels but it appears that mystery pipe is a vent for your shower. You also appear to be roughed for a shower, not a tub. Tubs usually have a drain on either side, not in the middle unless you're going with a claw foot. If you are going with a shower their is no need to move this drain.

Their should also be a vent for the toilet waste. It may be wet vented through the sink drain (in this case the sink drain should be 2in, not 1-1/2.

How far out from the wall is the center of your toilet waste line? Their are toilets that require as little as 10" although your selection will be limited and they're mostly special order. Still cheaper then having a plumber chop the slab though.
 
#6 ·
Thanks for all of the reply's so far.

Mike/Marlin - My toilet drain is about 11 7/8" off of the wall. So it looks like I will either go with a 10" center toilet or it will be chop-chop city and relocate the drain. Thanks for the flange/toilet mounting info.

Geek - You are exactly right about guessing! Unfortunately I am not the original owner and I've been told through the grapevine that the original builder is no longer in the picture locally. Kind of stinks! After my plumber quoted the job I forgot to ask him some basic questions. I will give him a call and maybe even have him come back out to explain some things to me before I make a decision on how I will proceed.
 
#7 ·
Bmbeeson---

I am not a plumber so I can not shed any light on your plumbing questions, however being a DIYer that just finished their basement project, I would take the time to put in a sump pit and pump. It sounds like you are already doing a bit of plumbing and taking the time to put the sump in now would be a good idea in my opinion.

I have a very dry basement and no plumbing in my finished basement but I did install a pump in my pit just to be on the safe side. I think it would be wise in your case since you are adding plumbing, even though your basement is dry. One burst pipe or one clog that causes a back up could be big $$$ in repairs.

just my two cents.
 
#11 ·
I'm sorry to but in on your thread Bmbeeson but I'd like to see if someone can explain what exactly a "wet vent" is and the purpose of it.
I'm getting ready to finish off my basement bathroom as well and the wet vent is causing all sorts of confusion for me.

Thank you in advance.


-Jeff
 
#15 ·
If my old buddy Ron calls your "not sure" a vent for the shower, then that is what it is. My "guess" missed it.
You'll have to break up some concrete and do some re-plumbing for anything but a shower there. An offset will work for the toilet. Check on the local code possiblities of Air Admittance Valves for the plumbing, if that rough-in isn't already vented.
www.studor.net
Good Luck!
Mike
 
#16 ·
I agree that the mystery pipe looks like the vent for the shower, and the toilet looks to be wet vented through the lavatory drain. In plumbing a toilet, 11 7/8 is the same as 12", I think you will find that most 12" rough toilets will fit with a finished wall to center of flange of about 11 1/4". If you buy a 10" rough toilet it will sit off the wall about 3". No need to break the floor up to move the pipe or to put in an offset flange (some places disallow them) I think you will be OK with a 12" but if not get a 10"
 
#17 ·
11 7/8" will work just fine with a 10" rough bowl, as for the line behind the shower (it's the vent), I would bet the original plumber was going to start off with a test tee there as a clean out for the shower drain.
 
#18 ·
First off, I have been lurking around here off and on for the past year and really love this site. Everybody here seems very helpful and forthcoming, that's awesome! Here's my situation:

I am currently in the mid-stage of finishing my basement and am ready to work on the bathroom plumbing. I am on a septic system and the house does not have a sump pit. I am very fortunate to have a super-dry basement!

I plan on installing a sink/vanity, toilet and, tub/shower combination. I snapped some pictures of what I currently have in the way of roughed in piping.

I have been told by a reputable local plumber that the toilet flange will have to be moved out from the wall a few inches to accommodate a toilet due to the fact that the original plumber put the pipe to close to the wall. He also told me that the shower/tub drain will have to be moved as well for the same reasons.

Here are my questions:

#1 - What is the "Mystery Pipe" (labeled "Not Sure") located to the left of the Shower Drain pipe? Is this an overflow drain for a tub?
#2 - How do I vent this bathroom?

Any help would be greatly appeciated, thanks!
From what I am seeing in the pictures, the not sure appears to be a vent pipe for the shower to allow air to pass through the master drain line without siphoning the pee trap in the shower and before you start busting up concrete to move a toilet pipe check to see if an offset flange will work. I have worked with some screwed up rough ins and the offsets have saved me a lot of head and back aches.
 
This is an older thread, you may not receive a response, and could be reviving an old thread. Please consider creating a new thread.
Top