Multiple projects - what order?


First- thanks for all of the great info here. Hours of reading...
We plan to do/contract a variety of projects, and I would like to get some opinions on the best order of the projects. Moving out and doing them all at once isn't really an option (or is it?? Hmm.) Thanks!

The house is a 1600 ft/sq, single story.
-Strip cieling popcorn, texture & paint
-Paint all inside walls
-Replace all carpets (6 rooms)
-Tile entry, 2 bathroom, and kitchen floors
-Remove brick/rebuild fireplace and mantle
-Install Recessed and other Lighting fixtures
-Paint Outside

dsr3 is offline   Reply With Quote
Old 06-29-2007, 04:30 AM   #2
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Default

Multiple projects - what order?


Quote:
Originally Posted by dsr3 View Post
First- thanks for all of the great info here. Hours of reading...
We plan to do/contract a variety of projects, and I would like to get some opinions on the best order of the projects. Moving out and doing them all at once isn't really an option (or is it?? Hmm.) Thanks!

The house is a 1600 ft/sq, single story.
-Strip cieling popcorn, texture & paint
-Paint all inside walls
-Replace all carpets (6 rooms)
-Tile entry, 2 bathroom, and kitchen floors
-Remove brick/rebuild fireplace and mantle
-Install Recessed and other Lighting fixtures
-Paint Outside

1.) Remove brick and rebuild Fireplace.
2.) (Cove Poly over over new Fireplace Brick) -Then strip ceiling popcorn, texture & paint.
--) Install Fireplace Mantel
3.) Paint all inside walls.
4.) Tile entry, 2 bathroom, and kitchen floors.
5.) Replace all carpets (6 rooms).
6.) Install Recessed and other Lighting fixtures.
7.) Paint Outside.

AtlanticWBConst. is offline   Reply With Quote
Old 06-29-2007, 09:15 AM   #3
Handyguy
 
Brik's Avatar
 
Join Date: Jan 2007
Location: SE PA
Posts: 803
Send a message via Skype™ to Brik
Default

Multiple projects - what order?


I may disagree somewhat. Given your list as a final list and the only things that need to be done then Atlantice may have the order. Generally I like to make sure the OUTSIDE is done first. By outside, I'm talking more than just aesthetics. Roof repairs, gutters, windows, caulking, drainage, etc. If all those things are fine and you are just changing colors outside then the order should be...
  • -Remove brick/rebuild fireplace and mantle
  • -Install Recessed and other Lighting fixtures (rough-in)
  • -Strip ceiling popcorn, texture & paint
  • -Paint all inside walls
  • -Tile entry, 2 bathroom, and kitchen floors
  • -Replace all carpets (6 rooms)
  • -Install Recessed and other Lighting fixtures (fixture install)
  • -Paint Outside
My order is similar to Atlantics but with one major change. I moved the electrical up early in the project. There could need to be disturbances in drywall for new fixture locations. So, I broke out electrical into two phases. Rough-in is setting boxes, recessed lights, running wires, etc. Once everything is painted you put in the final fixtures, recessed light trims, etc.

My rule of thumb is to paint before floors go in. Old carpet makes good drop cloths and no need to worry about getting paint on tile. You just need to plan for it.

Last edited by Brik; 06-29-2007 at 09:22 AM.
Brik is offline   Reply With Quote
Old 06-29-2007, 06:41 PM   #4
Newbie
 
Join Date: Jun 2007
Posts: 3
Default

Multiple projects - what order?


Thanks Guys!
dsr3 is offline   Reply With Quote
Old 07-01-2007, 03:45 PM   #5
Contractor
 
Dan101's Avatar
 
Join Date: Jul 2007
Location: Chicago, Illinois
Posts: 60
Default

Multiple projects - what order?


I agree with Brik. If you do the electrical first you will be better off. You never know when you may have to change locations of a new fixture or even add in an extra unplanned switch. Always better to do this before you patch and paint.
__________________
Dan101
Owner
J.& D. Remodeling
Chicago, IL
Dan101 is offline   Reply With Quote
Old 07-01-2007, 04:58 PM   #6
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Default

Multiple projects - what order?


Quote:
Originally Posted by Brik View Post
....I moved the electrical up early in the project. There could need to be disturbances in drywall for new fixture locations. So, I broke out electrical into two phases. Rough-in is setting boxes, recessed lights, running wires, etc...
Good Point Catching: the rough-in phase of the fixtures....
AtlanticWBConst. is offline   Reply With Quote
Old 07-10-2007, 02:56 PM   #7
Member
 
Join Date: Aug 2006
Posts: 174
Default

Multiple projects - what order?


I would adjust the painting of the walls (which I assume also means trim) to last. Yes, it's easier to paint over old floors but a friend of mine ended up repairing freshly painted walls when the floors went in after the paint. Just a few too many dings from the install plus a lot of dust stuck to the paint (from the saws when cutting the wood flooring) which hadn't had time to fully cure. It was just some extra work that could have been avoided by painting after.
Dusty is offline   Reply With Quote
Old 07-10-2007, 06:35 PM   #8
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Default

Multiple projects - what order?


I agree, generally, it is best to paint the walls last, as sighted, because if there is ANY kind of ongoing work in the home, materials and tools will be heaved around, usually creating small knicks and dents.

It's inevitable that you will have to do some spackling "touch up". We usually always leave the paint for last in any areas where work is still ongong (regardless if the drywall is completed).

Last edited by AtlanticWBConst.; 07-10-2007 at 06:37 PM.
AtlanticWBConst. is offline   Reply With Quote
Old 07-10-2007, 07:10 PM   #9
Member
 
Join Date: Mar 2006
Location: Austin, TX
Posts: 1,214
Default

Multiple projects - what order?


My Daddy always taught me to restore cars in this order:

Fix all the mechanicals.
Fix the interior.
Finish the exterior.

The same concept applies to a house, a car, or a backyard, unless you are a flipper.
Tscarborough is online now   Reply With Quote
Old 07-10-2007, 10:36 PM   #10
Newbie
 
Join Date: Jun 2007
Posts: 3
Default

Multiple projects - what order?


Thanks again for some great feedback.
The fireplace "front" brick is off, electrical is scheduled, we're off and running!
dsr3 is offline   Reply With Quote
Old 07-11-2007, 08:14 PM   #11
carpentry
 
WNYcarpenter's Avatar
 
Join Date: Jun 2007
Location: Jamestown N.Y.
Posts: 48
Default

Multiple projects - what order?


I would save having the carpet layed until last. You have to be extremely vigilant to keep dirty feet off new carpet.

Finish paint
electrical trim
carpet
move in furnishings
touch up paint

If you're using the same painting contractor for the interier and exterior, I would schedule them to start on the exterior while the interior is under construction. On rain days they can come inside and do prep work...filling holes, sanding trim etc... while the other contractors are doing their thing.

just my 2 cents

WNYcarpenter is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
What order 4 bst results shotdown Painting 6 06-27-2007 09:19 PM
Multiple lights/ceiling fans on 14/2?? sleepy23 Electrical 5 05-10-2007 10:27 AM
Exterior Paint Prep Order utdel Painting 2 06-24-2006 01:56 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.