12-18-2011, 08:13 PM
|
#1
|
|
Member
Join Date: May 2011
Posts: 83
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
According to the architects construction documents, in order to take out a load bearing wall on the 1st floor I have to install a concrete footing & lolly column in the basement as well as a microllam beam on the 1st floor.
As I go about taking on this arduous task I'd like to get everyone's advice and suggestions.
First up is digging the concrete footing. I have to dig a 30" x 24" x 12" deep concrete footing. The plate and lolly column sit on that footing and is covered by a 4" slab. So in essence, I have to dig 16" below the floor tile.
Any advice to doing this properly and as clean as possible? The lolly column would sit in a basement bathroom. :-/ What tool should I rent? Jackhammer?
Thanks in advance. Once I start pictures will be posted.
|
|
|
|
The Following User Says Thank You to management For This Useful Post:
|
|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. DIYChatroom.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any home improvement task!
12-18-2011, 09:44 PM
|
#2
|
|
Master General ReEngineer
Join Date: Dec 2007
Location: Chaumont River, Ny.
Posts: 3,168
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Quote:
|
I have to dig a 30" x 24" x 12" deep concrete
|
Ayuh,.... Cut the hole in the slab with a demosaw, 'n bust it out with a sledgehammer...
Then a pickax, 'n shovel will get that little hole dug in no time...
Throw the waste into 5gal. pails, 'n tote it off...
Get the bottom, nice, 'n flat, true, 'n plumb,...
Then back fill it with bagged mix...
Maybe buy a bag of portland to sweeten the bag mix abit, seein's it's a footer...
|
|
|
12-19-2011, 06:45 AM
|
#3
|
|
Member
Join Date: May 2011
Posts: 83
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
What if there is pipes running under the floor? It is in a basement bathroom.
|
|
|
12-19-2011, 05:56 PM
|
#4
|
|
Master General ReEngineer
Join Date: Dec 2007
Location: Chaumont River, Ny.
Posts: 3,168
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Quote:
Originally Posted by management
What if there is pipes running under the floor? It is in a basement bathroom.
|
Ayuh,... If so, you'll be diggin' a Bigger hole to move the pipes...
|
|
|
12-19-2011, 10:05 PM
|
#5
|
|
Member
Join Date: Feb 2009
Location: St. Louis, MO
Posts: 93
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
I have a couple column foundations in my future, too.
I settled on a hammer drill to score my concrete floor before busting it out for another recent project. I used an angle grinder with a diamond wheel and vacuum attached for a while but the dust was hideous and damaging stuff. I didn't want to create the mess (and also wasn't sure if the angle grinder was waterproof) of pouring water on it to keep the dust down. The hammer drill was slower but relatively cleaner. And that's cleaner compared to the floor covered with piles of dirt.
|
|
|
12-19-2011, 11:14 PM
|
#6
|
|
Member
Join Date: Dec 2011
Location: B.C. Canada
Posts: 1,982
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
your footing is 12" deep so is that 8" plus 4" = 12" or 12" under the 4" = 16" save some digging and concrete maybe, depending on what it is.
Usually you can do it in one pour.
How about rebar in it?
if it is a 4" floor now, we use jackhammer and 5 gal pails and carry upstairs or a couple of plastic totes out a window with someone outside.
|
|
|
12-19-2011, 11:33 PM
|
#7
|
|
Too Old
Join Date: Mar 2011
Location: South of North
Posts: 345
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
I am a little concerned that you are questioning the easy part of the remodel
This footing is an odd size, but if you are questioning how to do this. I am sure you will have more issues later. Good luck.
__________________
"Yeah, it's a nice garage, but you have to keep it heated at all times so it doesn't mess up your roof line."
|
|
|
12-19-2011, 11:47 PM
|
#8
|
|
Residential Designer
Join Date: Sep 2010
Location: Orange County CA.
Posts: 1,148
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Quote:
Originally Posted by management
According to the architects construction documents, in order to take out a load bearing wall on the 1st floor I have to install a concrete footing & lolly column in the basement as well as a microllam beam on the 1st floor.
As I go about taking on this arduous task I'd like to get everyone's advice and suggestions.
First up is digging the concrete footing. I have to dig a 30" x 24" x 12" deep concrete footing. The plate and lolly column sit on that footing and is covered by a 4" slab. So in essence, I have to dig 16" below the floor tile.
Any advice to doing this properly and as clean as possible? The lolly column would sit in a basement bathroom. :-/ What tool should I rent? Jackhammer?
Thanks in advance. Once I start pictures will be posted.
|
I felt I should put a "thanks" on your post as I think that this is really the kind of post that this site was made for.
You have the design and you are going to do the construction based on that, I doff my hat to your sir.
All too often people post things like 'what size post and beam do use' or 'can I get some input as the design for this or that'.
I just find this very refreshing.
Andy.
|
|
|
01-02-2012, 12:05 PM
|
#9
|
|
Member
Join Date: May 2011
Posts: 83
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Thanks a lot. Your words are much appreciated.
|
|
|
01-22-2012, 03:33 PM
|
#10
|
|
Member
Join Date: May 2011
Posts: 83
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Due to work and busy with other responsibilities it took me a while to get back to this but I rented a Makita 27lb jackhammer and took the slab out.
See here:
So I bought a shovel and started to dig down an additional 12" but I found a pipe with a small hole in it. I felt so dejected when I saw it and decided to turn on the water in the sink. No water came out the hole. I then built up enough confidence to flush the "empty" toilet. Nothing.
So now I think it is a phantom pipe. I have no idea where it goes and don't have the energy to jack up the entire floor looking for it.
1. What do you all think?
2. Can I just continue to dig and just cut out the portion that is in the space I need?
All I want to do now is put in this footing for the lolly column. The grand plans call for relaying out the bathroom but can't do that right now. It looks like the main drain doesn't come through where I am digging. I will continue to dig but just wanted to get the thoughts of others.
See close up in this picture. Hole is in the center ish portion of the picture. There is dirt in there as well.
Thanks.
|
|
|
01-22-2012, 04:05 PM
|
#11
|
|
Experienced
Join Date: Dec 2010
Location: Southern Michigan
Posts: 2,801
|
Concrete Footing, Lolly Column, & Microlam Beam Oh My!
Quote:
Originally Posted by AndyGump
I felt I should put a "thanks" on your post as I think that this is really the kind of post that this site was made for.
You have the design and you are going to do the construction based on that, I doff my hat to your sir.
All too often people post things like 'what size post and beam do use' or 'can I get some input as the design for this or that'.
I just find this very refreshing.
Andy.
|
That is an excellent point Andy! Sure not the A typical footing column question here is it.
Mark
__________________
When its all said and done there is usually more said than done To view links or images in signatures your post count must be 10 or greater. You currently have 0 posts.
|
|
|
-->
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Linear Mode
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|