Sistering Next To Cracked Joist - Building & Construction - DIY Chatroom Home Improvement Forum


Go Back   DIY Chatroom Home Improvement Forum > Home Improvement > Building & Construction

CLICK HERE AND JOIN OUR COMMUNITY TODAY...IT'S FREE!

Reply
 
Thread Tools Display Modes
Old 05-13-2010, 05:20 PM   #1
Member
 
Join Date: Nov 2009
Posts: 83
Rewards Points: 75
Default

Sistering Next to Cracked Joist


I have a cracked joist in my basement. My house was built in 1914, and one of the 2x10 joists above the basement, under the kitchen is cracked 3/4 of the way through where there is a big knot in the wood. My plan was to sister new 2x10s on each side of the crack, extending 4-5 feet on either side of the crack, but neither end resting on any support (foundation, or main center beam).

This is about a 15' span, and my question is will this be sufficient, or do I need to run the sistered joist the full length of the span, and rest it on the foundation on one side, and the load bearing center beam on the other?

I "might" be able to get the full 15' spanned, but wiring/piping/ducting is running all over the basement, and I think even getting 10' of sistered boards in there will be difficult, and if this is all that is needed I'm not going to bother with trying to go the full length.

Also, what should I use to fasten the joists together? I was going to use liquid nails as well as either bolts or nails, and I wasn't sure which would be best.

Lastly there is maybe a 2 inch crack (at another smaller knot) in this same joist at right near where the joist rests on the foundation. Is this something that should be addressed as well? For this one if anything needs to be done could I just rest the one side next to it on the foundation, and the other side extend 4ish feet past the crack?

Thanks,

Richard

Advertisement

rjschwar is offline   Reply With Quote
Old 05-13-2010, 05:22 PM   #2
Member
 
Join Date: Nov 2009
Location: central virginia mountains
Posts: 1,857
Rewards Points: 1,000
Default

Sistering Next to Cracked Joist


should be fine with thru bolts

Advertisement

__________________
The older I get the better I was
tpolk is offline   Reply With Quote
Old 05-13-2010, 06:13 PM   #3
Civil Engineer
 
Join Date: Mar 2009
Location: Boston
Posts: 4,306
Rewards Points: 2,190
Default

Sistering Next to Cracked Joist


Personally I like bolts, I typically use 1/2 inch diameter through steel bolts with nuts and washers. Glue is not necessary, if the bolts are spaced about 6" OC, are predrilled, properly nutted off, and staggered (1 in upper third, next in lower third of joist). This is overkill, but I don't believe most codes are going to give the sizing and spacing for sistering joists using bolts, so this should be acceptable. Your overlap is OK, and it is not necessary to extend the sistered joist to the wall, unless there are other problems with the damaged joist.

By the way, some jurisdictions may require a building permit, you might want to check.
Daniel Holzman is offline   Reply With Quote
Old 05-13-2010, 06:19 PM   #4
Member
 
Join Date: Nov 2009
Posts: 83
Rewards Points: 75
Default

Sistering Next to Cracked Joist


Thanks for the responses. Dumb question...what is OC? off center? I assume you are saying bolt upper 1/3rd, 6" over, bolt lower 1/3rd, 6" over upper 1/3rd again. Is this correct?

What about the crack at the end of the joist?

Thanks,

Richard
rjschwar is offline   Reply With Quote
Old 05-13-2010, 07:18 PM   #5
Member
 
Join Date: Mar 2010
Location: New York
Posts: 1,764
Rewards Points: 42
Default

Sistering Next to Cracked Joist


OC is on center. It seems like a good idea to sister that area as well. Some on here have mentioned sandwiching a piece of plywood in between the sister and the original joist if bounce is an issue.
Jim F is offline   Reply With Quote
Old 05-14-2010, 10:44 AM   #6
Member
 
Join Date: Nov 2009
Posts: 83
Rewards Points: 75
Default

Sistering Next to Cracked Joist


So I found some 1/2" 6" bolts, but they are threaded the full length of the bolt rather than just the last 1"-1.5". The ones that aren't threaded the full length don't quite fit. The 5" is too short, and the 6" is just a bit too long as I could hit the end of the thread. I couldn't find any 5.5". I'm sure I can from somewhere around here, but will the fully threaded bolts have the strength (shear?) necessary for this application?

Thanks,

Richard
rjschwar is offline   Reply With Quote
Old 05-14-2010, 01:25 PM   #7
Civil Engineer
 
Join Date: Mar 2009
Location: Boston
Posts: 4,306
Rewards Points: 2,190
Default

Sistering Next to Cracked Joist


Fully threaded bolts are fine. In the event that you have to shorten them due to access issues, you can grind the end down on a bench grinder, then touch up the end of the bolt using a 1/2 inch die. Or you can cut half an inch off with a Sawzall, and use the die to fix the end.

If you don't need to shorten the bolt for access, leave it long, no problem. You can double nut the end to effectively eliminate the potential of a nut backing off due to vibration, or you can use a lock washer to accomplish the same thing.

And yes, I meant to stagger the bolts upper third, lower third, upper third etc. By the way, I usually use two bolts on either end, one in the upper third, one in the lower third. Never install a bolt closer than bolt diameters from the edge. And make sure you overdrill the hole slightly, the bolt should go in freely. Snug the bolts up using a ratchet, no need to overtighten. If you use a lock washer, when the washer is squashed flat, you are good.

As for the knot on the end, if it is not cracked through, it is probably not an issue. If it is really bad, sister a 4 footer on that end. The end only carries shear, no moment, so is generally much less critical than the center, where bending moment is maximum for a joist.
Daniel Holzman is offline   Reply With Quote
Old 05-14-2010, 10:37 PM   #8
Totally screwed together
 
Join Date: Dec 2006
Location: Cypress, SoCal
Posts: 325
Rewards Points: 250
Default

Sistering Next to Cracked Joist


Honestly, that joist scares the bejeebees out of me... cracked in two places in an area with heavy appliances and lots of traffic.

If it's exposed wire and pipe you have, that's actually pretty easy to cut and repair. Ducting can be temporarily disconnected too.

If you really want to do this right, here is what I would do:

1st, Don't do this if there is a wall directly above, it will require straightening the floor above which will do harm to a wall that has settled in.

Get an accurate measurement of this beam - what are it's EXACT dimensions. Chances are it's closer to 10" than a modern 2x10. If that's the case, you should start with a 2x12. Whichever beam you get, buy it and bring it downstairs to dry out before you do anything else. Set it on something straight, flat, and dry (NOT the floor!), and make sure it has room 3/4" underneath for air to flow through. What you are doing is drying out the wood AND shrinking it. It won't shrink much lengthwise, but it will shrink on its width and depth axis. A $2 moisture meter from Harbor Freight will help you find when the wood hits >19% moisture, at this point it's stable. At this point, you can cut it to the exact dimension.

Cut the wires and pipes (shut them off first, silly goose!). When you reconnect them you can make sure they run through the center of the joist if any were notched. Pot a small box one each side of the joist for wires with a new wire connecting between, and use Sharkbite fittings to easily reconnect your copper water pipes.

You will have to do some creative jacking up of the low points, and some creative swearing as you angle the new joist into place.

After you set the joist and lower the jacks, you can toenail the joist to the floor above with screws.

When you are done, you will have a floor that will last another century.
xxPaulCPxx is offline   Reply With Quote
Old 05-15-2010, 05:24 PM   #9
Member
 
Join Date: Jan 2009
Location: Vermont
Posts: 762
Rewards Points: 500
Default

Sistering Next to Cracked Joist


You never mentioned what is above this joist other than a kitchen. Options, depending on load rating are (in order of strength): another 2x10 just tacked to the split one, two 2x10's, as before with screws and glue or bolts. as before with plywood stiffener, microlam, steel flitch plate with 2x10 all bolted together.
Talk to an engineer if there is a heavy load bearing on this joist

Advertisement

mrgins is offline   Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
YIKES !!! JOIST IS CRACKED IN TWO --how do I fix? Dyoung Building & Construction 7 02-16-2010 08:51 AM
How to repair floor joist when sistering is not an option jmagee3d General DIY Discussions 2 06-05-2009 03:33 PM
Floor bounce joist sistering joehomeowner Building & Construction 24 05-10-2009 02:50 PM
sistering in a plumber whacked joist 4just1don Building & Construction 7 02-04-2009 02:33 PM
Sistering a floor joist? teachtech Building & Construction 8 02-19-2008 10:35 PM




Top of Page | View New Posts