DIY Home Improvement Forum banner

Replacing my big o

991 views 4 replies 3 participants last post by  tlgwills 
#1 ·
Am trying to figure out how many yards of 3/4 gravel I will need to cover 150 liner feet of new big o
 
#2 ·
Not mind readers, what a big O?
Google concrete calulator. Volume is volume no mater what the materail is.
It will ask length, width, thickness and figure it out in cubic yards.
 
#4 ·
well if you place in into a 1' x 1' trench that would be roughly 150 cubic feet. 150 cubic feet/27 cubic feet per cubic yard = 5.56 cubic yards ...... so I'd say 6

of course if you want a larger trench ..... it takes more
 
#5 ·
GBrackins said:
well if you place in into a 1' x 1' trench that would be roughly 150 cubic feet. 150 cubic feet/27 cubic feet per cubic yard = 5.56 cubic yards ...... so I'd say 6

of course if you want a larger trench ..... it takes more
Thank you I did a calculation and I had 7. 4 yards but that was converting from tones. But 7 seemed a little high. Thank you very much for your help
 
This is an older thread, you may not receive a response, and could be reviving an old thread. Please consider creating a new thread.