Repairing basement stair opening (and stairs)


Just purchased my home. I knew it had issues with the stairs, but when I got the U&O they pointed out there was bigger issues with the structure. The doubled header joist (2 - 2x10's) are notched and sitting on a short ledger strip (2x4). I believe the failure was due to the lack of nails in the ledger supporting the header into the trimmer joists (I can only see on nail in the ledger, but suspect there is only a total of 3 nails at most).

Here's the staircase:




Here's the ledgers holding the header to the trim joist:




I need to repair this and get it re-inspected. My thoughts are to essentially rebuild everything with new 2x10's and joist hangers (instead of notching/ledger strips). I would probably leave the existing floor joist and either figure out a way to either sister in new boards or use an extra header plate (to make up for the ledger strip holding them up).

Of course, I would also need to address the first step/landing as it ties into the header (overlaps by an inch or so).

Any ideas or thoughts?


Last edited by ScrewLooseDan; 05-26-2011 at 03:29 AM.
ScrewLooseDan is offline   Reply With Quote
Old 05-26-2011, 08:14 AM   #2
Member
 
Join Date: Mar 2007
Location: Long Island, NY
Posts: 9,519
Default

Repairing basement stair opening (and stairs)


I'd triple up the ledger where the 2x4 is, by removing the 2x4 and hanging the current notched joist with a joist hanger.
Ron

Ron6519 is offline   Reply With Quote
Old 05-26-2011, 08:40 AM   #3
Framing Contractor
 
Join Date: Feb 2009
Location: NE Ohio
Posts: 1,059
Default

Repairing basement stair opening (and stairs)


Build a wall underneath the stairs and landing.
sixeightten is offline   Reply With Quote
Old 05-26-2011, 11:37 PM   #4
Newbie
 
Join Date: May 2011
Location: Collegeville, PA
Posts: 3
Default

Repairing basement stair opening (and stairs)


Thanks guys for the responses. A few follow-up questions...

Quote:
Originally Posted by Ron6519 View Post
I'd triple up the ledger where the 2x4 is, by removing the 2x4 and hanging the current notched joist with a joist hanger.
Ron
I'm not sure I completely follow you as far as tripling the ledger? Are you refering to the 2x4 that is holding up the floor joists or the 2x4 that is holding up the header plate (which is the one that has failed)? I'm not sure I have room to use hangers to hold up the double header joist. I have thought about using hangers on the floor joist to header connection, as that would be easy enough to do (but isn't where the problem is currently).

Quote:
Originally Posted by sixeightten View Post
Build a wall underneath the stairs and landing.
Wouldn't a wall in this case become a load structure, requiring a footer? I had contemplated this idea as it wouldn't take much to construct a wall and I suspect it would provide plenty of support. But, I'm concerned the inspector isn't going to like it.
ScrewLooseDan is offline   Reply With Quote
Old 05-27-2011, 06:56 AM   #5
Member
 
Join Date: Mar 2007
Location: Long Island, NY
Posts: 9,519
Default

Repairing basement stair opening (and stairs)


Okay, I see it now.
Replace the 2x10 framing members that are notched.
Ron
Ron6519 is offline   Reply With Quote
Old 05-27-2011, 10:25 PM   #6
Registered User
 
Join Date: Mar 2009
Posts: 9,968
Default

Repairing basement stair opening (and stairs)


Yep, 2-3/8" maximum notch, not 3-1/2': http://publicecodes.citation.com/ico...002_par028.htm

Gary

__________________
If any ads are present in my answer above, I do not condone/support/use the product or services listed, they are there against my permission.
Gary in WA is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Framing for New Stair opening Clearance builderjohn Carpentry 3 02-11-2010 10:36 AM
Basement stair wall load bearing? (pictures) barlav Building & Construction 13 09-23-2009 05:01 AM
water comes down basement walkout stairs carriepartlan Building & Construction 1 07-09-2009 06:13 PM
Reinforcing Former Stair Opening amakarevic Building & Construction 2 06-06-2008 09:56 AM
Opening for attic stairs sk8z Remodeling 16 03-17-2008 12:52 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.