Well guess the first question is, what is considered good enough in leveling a basement ceiling with furring to be drywalled?...

that said...

I am TRYING to level a basement ceiling as good as possible before it is drywalled with 5/8" drywall

I furred down the ceiling with 2x material (had to go around a iron pipe that couldn't be moved into the joists)..

I have all the furring up now screwed so I can change it as needed. All 16" O.C.

I have a rotray laser level which is leveled out, then I made a pole device that I can go around and compare positions where it hits on that pole as it touches the furring on the ceiling. kinda like a survayer would do, just on the ceiling instead of the ground... well everything seems ok, but the house has a slight slope to it, probably because the steel beam going down the center of the house has a slight bow due to the weight, but we are talking 1/8" over 10 ft maybe.. the basement area being drywalled is 38 ft wide and 25 ft deep.. so that isn't a horrible slope right?...

well on one end the 2x10 material must be deeper on the ceiling joists... almost all them are like 9 and 1/2" but then you suddenly get one that is 9 11/16" which causes a warp in the furring...

best to cut a groove in the furrning strip to level this out? and not cut the joist?

any better ways to level a ceiling? am I being to critical with the leveling? This is the first time I've ever tried to do this so I'm not sure what is "ok" to ignore, I know 5/8" drywall will hide some of the differences, but like any first timer, not sure what to expect

__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 01-07-2013, 09:57 AM   #2
Member
 
Join Date: Nov 2011
Location: Hartfield VA
Posts: 25,784
Default

leveling basement ceiling driving me nuts


I just use a piece of brick string pulled tight instead of my lazer.
Set them all to the lowest joist. If there's only one that's low I'd use my eletric planer to trim off the joist.

joecaption is online now   Reply With Quote
Old 01-07-2013, 09:58 AM   #3
A "Handy Husband"
 
rjniles's Avatar
 
Join Date: Feb 2007
Location: South Carolina Low Country
Posts: 3,936
Default

leveling basement ceiling driving me nuts


Identify the low point and shim the rest of the furring down to that point. Since you screwed the furring to the joist it should be easy. Loosen the screw and insert a shim between the joist and the furring, re tighten screw
__________________
Location:
Coastal South Carolina
rjniles is offline   Reply With Quote
Old 01-07-2013, 10:08 AM   #4
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,294
Default

leveling basement ceiling driving me nuts


Quote:
Originally Posted by joecaption View Post
I just use a piece of brick string pulled tight instead of my lazer.
Set them all to the lowest joist. If there's only one that's low I'd use my eletric planer to trim off the joist.
I think there is 3 that are the lowest in the whole thing (the ones that are slightly deeper)

leveling even with a 8 ft level and a rotary laser still drives me nuts

was using the rotary one to find the low parts, and using the 8ft level has a "flat" surface to look for waves in the strips and compare them on a diagonal for height differences
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 01-07-2013, 10:18 AM   #5
Member
 
Join Date: Nov 2011
Location: Hartfield VA
Posts: 25,784
Default

leveling basement ceiling driving me nuts


Using the string can avarage out the whole ceiling not just a short section of it.
joecaption is online now   Reply With Quote
Old 01-07-2013, 10:34 AM   #6
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,294
Default

leveling basement ceiling driving me nuts


Quote:
Originally Posted by joecaption View Post
Using the string can avarage out the whole ceiling not just a short section of it.
yeah, I'm going to have to try the string method tonight... thankfully bought a spool of the thinner stuff when I put a drop ceiling in that I never used, rotary laser level worked too well on the drop ceiling to need it
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 01-07-2013, 10:44 AM   #7
Roofmaster
 
Join Date: Oct 2012
Location: Maryland
Posts: 3,453
Default

leveling basement ceiling driving me nuts


Yeah, generally you would find the lowest point, and go from there A good idea to get your furring all level is to drill through holes in the furring and use compressible foam next to the screw. Then with a ratchet and proper bit, you can really dial in exactly level, hard shim and screw for effect. When you hang your drywall ceiling, use two screws together about 3/4 inch apart to gain a great deal more holding power, as the cone of influence is about 6 times that of a single screw.

1/8 inch in 10 ft is not squat.

If you are well into this, Joe has a good idea with a power plane, as 3/16 wont make much difference in structural value. Just need to chisel the ends.
__________________
" A lot of men build things, and a lot of things fall down "

jagans is offline   Reply With Quote
Old 01-07-2013, 10:45 AM   #8
Member
 
joed's Avatar
 
Join Date: Mar 2005
Location: Welland, Ontario
Posts: 7,374
Default

leveling basement ceiling driving me nuts


If you only have three lower joists then I think I would trim the furring instead of shimming all the rest. Run the furring through a table saw and make it thinner. Quicker than cutting notches at each joist. Stop half way if it extends to the section where no trimming is needed.
__________________
Do not PM with questions that can be asked in a forum. I will not respond.
joed is offline   Reply With Quote
Old 02-07-2013, 02:46 PM   #9
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,294
Default

leveling basement ceiling driving me nuts


well.. finally getting this done after some delays.. Iwent back to the rotary laser method... tried a string method but with the way the framing is, didn't work so well

I got the rotary laser going and leveled out, then I took my tape measure and picked random joists around the room measured from the top of the furring down to the laser line, and used it kind of like a plumb bob, let the tape measure hang from its top end and the bottom work as a weight so it self plumbed... then read the measurement... did that randomly, figured out an average distance from the top and that the center of the room was all the same, it was just the ends that where off by +/- 1/4" one end was up, the other was down... 90% of the joists where at the same height... so just shimmed one end, checked it again with the laser and tape measure... marked that joist off as "level" with a check mark... moved on until every one was marked off... other end, had to notch the boards up to 1/4" which took more time... but still faster then taking that side and shimming out everything to match that one part

__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling a Basement Cement floor Tinkertom67 Flooring 0 08-14-2011 12:49 PM
framing basement walls with furred ceiling BlueBSH Building & Construction 10 08-05-2011 12:44 PM
Basement drywall ceiling and walls questions enero Drywall & Plaster 6 06-05-2010 03:13 PM
Lighting Options for a dropped ceiling basement markronz Electrical 11 04-20-2010 02:20 PM
Drywalling my basement ceiling luweee Remodeling 5 03-24-2009 06:58 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.