General Steps to a bathroom remodel
Hi all,
I'm about to undertake a bathroom remodel. I've purchased numerous books, and have been reading and researching this for some time. However, one rather important detail eludes me: the order of the major parts of the process. My understanding, at the moment, is something like this: (where the a's and the b's could be done at the same time)
1. Gut
2. Drywall on ceiling (only hang it to keep the heat in while we remodel)
2a. Electrical rough-in / redo if needed
2b. Plumbing rough-in
3. Tub and tub surround installation
4. Hang drywall on the walls
5. Mud and tape
6. Install flooring
7. Seal/prime and paint (maybe do this before floors are installed?)
8a. Install vanity & sink
8b. Install commode
Your help, experience, and advice are most appreciated.
|