Foundation bolts


I am building a new garage (attached) on a monolithic pour. The walls will be framed and covered with plywood then stood up into place. My question is this:Can I use anchor bolts (wedge or epoxy) to anchor the wall to the foundation after the wall is up instead of placing the 'J' type anchors into the pour? I do not want to have to deal with the anchors being in the way when the wall is raised. The walls are 22' and 32' long and 9'6" tall. One contractor tells me no problem, another says he doesn't think so. The IRC doesn't make this clear and only uses the phrase 'anchor bolts'. Any opinions on this? Thanks for your help.

cheyenne is offline   Reply With Quote
Old 02-27-2008, 12:31 PM   #2
Crabby Bastard
 
terri_and_jj's Avatar
 
Join Date: Feb 2008
Posts: 150
Rewards Points: 75
Default

Foundation bolts


unless you have a local building code that specifies precast anchors, i don't see why you couldn't use a post-pour anchor system. for a wall you may want to go with epoxy since you will be close to an unsupported slab edge.

if you are in florida or an area prone to hurricanes and tornados you really want to look into this. there is a whole seperate rule book for these areas and everything is pretty clearly spec'd out with little room for variation

terri_and_jj is offline   Reply With Quote
Old 02-27-2008, 12:46 PM   #3
Newbie
 
Join Date: Jan 2008
Posts: 13
Rewards Points: 10
Default

Foundation bolts


Thanks. The area is Wyoming. From some engineering papers I read the determining factor in all this is not the anchor shear but the sill plate shear, about 850 lbs. As long as the anchor is at or above that protection level it shouldn't matter if it is pre or post pour. How do professionals deal with standing a wall up on a flat slab with pre-placed J bolt anchors? I can't picture how you would do this!
cheyenne is offline   Reply With Quote
Old 02-27-2008, 01:19 PM   #4
Crabby Bastard
 
terri_and_jj's Avatar
 
Join Date: Feb 2008
Posts: 150
Rewards Points: 75
Default

Foundation bolts


as long as the holes are spotted correctly iall you need to do is tilt it in place , put up some temp bracing, and screw on the nuts and washers.

It's a breeze IF the anchors are exactly where the engineer said they should be, which is seldom the case (although it's much better now with all the new technology)!!

If you ever get the chance to see a commercial tilt wall job going up, stop and check it out, its wild to see it first hand. it's very similiar to playing with Legos, just on a MUCH larger scale
terri_and_jj is offline   Reply With Quote
Old 02-27-2008, 02:16 PM   #5
Member
 
Join Date: Nov 2007
Posts: 561
Rewards Points: 500
Default

Foundation bolts


Quote:
Originally Posted by cheyenne View Post
Thanks. The area is Wyoming. From some engineering papers I read the determining factor in all this is not the anchor shear but the sill plate shear, about 850 lbs. As long as the anchor is at or above that protection level it shouldn't matter if it is pre or post pour. How do professionals deal with standing a wall up on a flat slab with pre-placed J bolt anchors? I can't picture how you would do this!
It's done BEFORE the plywood is attached. One person can do it if there's no wind...
LawnGuyLandSparky is offline   Reply With Quote
Old 02-27-2008, 03:37 PM   #6
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Rewards Points: 2,000
Default

Foundation bolts


Why don't you just ask your local building inspector what is acceptable in your township/county/region?
AtlanticWBConst. is offline   Reply With Quote
Old 02-27-2008, 08:22 PM   #7
ICF Construction
 
Join Date: Oct 2007
Posts: 314
Rewards Points: 250
Default

Foundation bolts


Epoxy setting of threaded rod is common, although more expensive then using J-bolts during the initial pour.

Worse case scenario building department may want an engineer to spec the depth/size of rod and strength of epoxy (normally SET-22 costing $ 24.00 a tube for the doubles)

__________________
Chris
Chris Johnson is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Floor Joists Lifting Off Foundation Walls?! cbeingessner Building & Construction 2 06-12-2008 08:39 AM
How important is plastic vapor barrier on foundation wall? slatergrl Remodeling 5 02-18-2008 12:49 PM
Foundation drain and sump pump slatergrl Plumbing 3 02-10-2008 09:36 AM
Stone foundation for a small shack andrgo Building & Construction 10 09-13-2007 01:49 PM
Addition Foundation /Build. advice wannabuild Remodeling 3 12-15-2006 06:28 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.