Old 08-23-2012, 02:14 PM   #1
Newbie
 
Join Date: Jun 2012
Location: Wisconsin
Posts: 29
Rewards Points: 25
Default

easy LVL/joist hanger question


Well, easy for you guys.

I need to install a doubled up 2x8 LVL header above a basement window, and then some joist hangers on the face. The header will sit parallel to the rim joist and on top of the treated sill plate.

Should I build the doubled up LVL beam first and then from the outside of the rim joist nail to the header (and possibly toenail it into the sill/mud plate) or should I nail the first LVL to the rim joist and then nail the 2nd LVL to that?

I guess we're not talking end of the world here since the joist will keep everything pretty well sandwiched together, but I'd like to do it in the best way.

Advertisement

DIY1 is offline   Reply With Quote
Old 08-23-2012, 02:32 PM   #2
AHH, SPANS!!!
 
Join Date: Apr 2012
Location: Durham NC
Posts: 1,684
Rewards Points: 1,032
Default

easy LVL/joist hanger question


it will be easier to put them in one at a time most likely... be sure to get plenty of bearing on top of the sill plates either side of the window and prepare to deal with nails in the way that stick down through the sub floor

Advertisement

hand drive is offline   Reply With Quote
Old 08-23-2012, 03:42 PM   #3
Newbie
 
Join Date: Jun 2012
Location: Wisconsin
Posts: 29
Rewards Points: 25
Default

easy LVL/joist hanger question


It's a home addition so there won't be any subfloor on yet. I figured I'd go for at least 6 inches of bearing on each side of the window.

Is it taboo to nail into the doubled-up header from the outside of the rim joist?
DIY1 is offline   Reply With Quote
Old 08-23-2012, 05:53 PM   #4
Framing Contractor
 
Join Date: Apr 2006
Location: Caldwell, NJ
Posts: 1,758
Rewards Points: 1,000
Default

easy LVL/joist hanger question


Quote:
Originally Posted by DIY1
Well, easy for you guys.

I need to install a doubled up 2x8 LVL header above a basement window, and then some joist hangers on the face. The header will sit parallel to the rim joist and on top of the treated sill plate.

Should I build the doubled up LVL beam first and then from the outside of the rim joist nail to the header (and possibly toenail it into the sill/mud plate) or should I nail the first LVL to the rim joist and then nail the 2nd LVL to that?

I guess we're not talking end of the world here since the joist will keep everything pretty well sandwiched together, but I'd like to do it in the best way.
Why a rim board and double lvls for a header? How wide is the opening?
__________________
Joe Carola
Joe Carola is offline   Reply With Quote
Old 08-27-2012, 12:04 PM   #5
Newbie
 
Join Date: Jun 2012
Location: Wisconsin
Posts: 29
Rewards Points: 25
Default

easy LVL/joist hanger question


It's only in the ballpark of 4' wide. I'm just following the architect's orders.

I am, however, only using 1 3/4" LVL's and not the 1 7/8" LVL's that the architect spec'd.
DIY1 is offline   Reply With Quote
Reply

Tags
header , joist


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
LP / NG - Unusual Question... Peter B. Appliances 8 04-09-2011 09:59 AM
Easy Basement Insulation Question koz123 Building & Construction 0 02-06-2011 09:43 AM
Joist Hanger Question? mopowers Carpentry 11 08-22-2010 02:56 AM
hrv question indep HVAC 3 07-17-2008 11:39 PM
Easy Drywall Question hohandy Building & Construction 10 12-16-2005 01:18 AM




Top of Page | View New Posts