Hi everyone I just contracted a deck to be built by a local contractor in my area with very high reviews. I have been away while the built the deck and they built the stairs in the wrong spot, but thats another story. My wife noticed they didn't even pour the support footings yet. I am not sure what right looks like so I came here to see if this is normal. The deck is still under construction, but I want to make sure it will be safe. We live in Maryland if that makes any difference. Thanks again!
Attached Thumbnails
Deck being built before footings?-994798_10152870750525386_1278736072_n.jpg   Deck being built before footings?-10604_10152870754125386_130320295_n.jpg  

untilcomplete is offline   Reply With Quote
Old 06-09-2013, 11:18 AM   #2
journeyman carpenter
 
woodworkbykirk's Avatar
 
Join Date: Sep 2011
Location: nova scotia canada
Posts: 2,670
Default

Deck being built before footings?


quite a few deck builders do frame the deck before the footings are in place without any issue.. however those posts your builder has in place is less than sufficient... the post should be one piece that sits on a 2x6 foot without any scabbed on pieces

woodworkbykirk is offline   Reply With Quote
Old 06-09-2013, 11:33 AM   #3
Member
 
Join Date: Oct 2008
Location: Ontario
Posts: 777
Default

Deck being built before footings?


Quote:
Originally Posted by woodworkbykirk View Post
those posts your builder has in place is less than sufficient
The posts on the outside look temporary. My guess is the ones on the inside will be the final posts.
SPS-1 is offline   Reply With Quote
Old 06-09-2013, 12:49 PM   #4
Member
 
Join Date: Nov 2011
Location: Hartfield VA
Posts: 26,246
Default

Deck being built before footings?


I've never once heard of or seen anyone build one that way.
How do they expect to dig a footing below the frost line and fill it with the deck in the way.
Makes no since to me.
__________________
When posting in forums, letting us know your location will help others give better feedback/advice/solutions to your questions
joecaption is offline   Reply With Quote
The Following User Says Thank You to joecaption For This Useful Post:
firehawkmph (06-09-2013)
Old 06-09-2013, 12:51 PM   #5
DIY staff
 
Join Date: Sep 2009
Location: Kane county,Illinois
Posts: 21,451
Default

Deck being built before footings?


Fairly common to frame up before the footings are poured in this area also--

The inspection process of the holes is the main reason---why stop work and wait a day or two for the inspector to look at the holes?

Dig--call for inspection--then start framing---this allows for the sonotubes to be centered under the posts--another good reason to pour after framing--
__________________
New members: Adding your location to your profile helps in many ways.--M--
oh'mike is online now   Reply With Quote
The Following 2 Users Say Thank You to oh'mike For This Useful Post:
funfool (06-09-2013), Willie T (06-09-2013)
Old 06-09-2013, 12:59 PM   #6
Member
 
funfool's Avatar
 
Join Date: Oct 2012
Location: Albuquerque NM
Posts: 700
Default

Deck being built before footings?


The only reason I can think of doing it this way.
If they poured the footings first, which I would do. Then they can not work on it for a few days while the concrete cures and gains strength.
Looks like they dug adequate size footings depending how deep they are, pour it last which will be a pain working under the deck.

But he is getting in there, building it full steam ahead, will pour last and tell you to stay off of it for a week while the concrete cures and then come back and remove the temp supports.
Different, but I suppose will work just fine also.
__________________
If it was easy, we would not call it work!
funfool is offline   Reply With Quote
Old 06-09-2013, 01:01 PM   #7
Member
 
funfool's Avatar
 
Join Date: Oct 2012
Location: Albuquerque NM
Posts: 700
Default

Deck being built before footings?


The inspection process makes sense.
And they already have the footings dug, will just be pouring dry cement in the hole and mixing water as you go, a pain but very doable.
__________________
If it was easy, we would not call it work!
funfool is offline   Reply With Quote
Old 06-09-2013, 01:12 PM   #8
DIY staff
 
Join Date: Sep 2009
Location: Kane county,Illinois
Posts: 21,451
Default

Deck being built before footings?


Inspections can do that----I need to build a little 4x6 patio door landing and two steps---

Hole inspection would take two days----digging four holes will take ,what an hour? When call it a day and drive to another job?

Best to dig--build and then call---in this area anyways---
__________________
New members: Adding your location to your profile helps in many ways.--M--
oh'mike is online now   Reply With Quote
Old 06-09-2013, 02:06 PM   #9
Member
 
Join Date: May 2012
Location: Sarasota,Florida
Posts: 1,506
Default

Deck being built before footings?


Quote:
Originally Posted by funfool View Post
The inspection process makes sense.
And they already have the footings dug, will just be pouring dry cement in the hole and mixing water as you go, a pain but very doable.


They wouldn't be putting dry mix and water in the footings in my back yard,do they actually let you do that where you live????
Canarywood1 is offline   Reply With Quote
Old 06-09-2013, 08:33 PM   #10
journeyman carpenter
 
woodworkbykirk's Avatar
 
Join Date: Sep 2011
Location: nova scotia canada
Posts: 2,670
Default

Deck being built before footings?


honestly it seems to be more of an american thing.. ive never seen anyone do it this way in canada. having the posts already in place as shown would make it difficult to get the post saddles properly in position not only in the concete while it sets up but also around the post itself

we always locate the piers first.. and pour them. then build off of that. as long as the piers are in a straight line it doesnt really matter if their off by 1/2" from the foundation of hte house
woodworkbykirk is offline   Reply With Quote
Old 06-09-2013, 08:44 PM   #11
Member
 
Msradell's Avatar
 
Join Date: Sep 2011
Location: Louisville Kentucky
Posts: 1,130
Default

Deck being built before footings?


Quote:
Originally Posted by funfool View Post
The inspection process makes sense.
And they already have the footings dug, will just be pouring dry cement in the hole and mixing water as you go, a pain but very doable.
I hope this is not what they are planning on doing. I don't know of any place that will allow loadbearing piers to have the concrete placed in that way. It must be premixed in order to ensure proper mixing and slump in order to ensure the final strength is correct. The only time you ever used dry cement and then add water is when setting posts!
Msradell is offline   Reply With Quote
Old 06-09-2013, 08:48 PM   #12
Member
 
Msradell's Avatar
 
Join Date: Sep 2011
Location: Louisville Kentucky
Posts: 1,130
Default

Deck being built before footings?


Quote:
Originally Posted by oh'mike View Post
Inspections can do that----I need to build a little 4x6 patio door landing and two steps---

hole inspection would take two days----digging four holes will take ,what an hour? When call it a day and drive to another job?

Best to dig--build and then call---in this area anyways---
I'm surprised the inspectors will get under the deck to inspect the excavations. Or do they just see there's a hole and be done with it? If they don't pass the excavation for some reason it would certainly be a pain to do any rework.
Msradell is offline   Reply With Quote
Old 06-09-2013, 08:54 PM   #13
Roofmaster
 
Join Date: Oct 2012
Location: Maryland
Posts: 3,530
Default

Deck being built before footings?


Im in Maryland too. Ive never done it this way but it does make sense if you think about it, I dont like how they temped them though. I seriously do not get how the steps ended up in the wrong place, you need plans for a permit. The steps are shown on the plans, so How can they end up in the wrong place?????
__________________
" A lot of men build things, and a lot of things fall down "

jagans is offline   Reply With Quote
Old 06-09-2013, 09:16 PM   #14
Remodel and New Build GC
 
MTN REMODEL LLC's Avatar
 
Join Date: Sep 2010
Location: Colorado @ 7651'
Posts: 2,765
Default

Deck being built before footings?


Quote:
Originally Posted by joecaption View Post
I've never once heard of or seen anyone build one that way.
How do they expect to dig a footing below the frost line and fill it with the deck in the way.
Makes no since to me.
Joe... Done all the time out here in Co. With significant elevation changes, it's easier and more accurate to drop a plumb line for your pier, than to do your staked layout.

Your supporting posts, prior to setting your piers and actual posts, are offset from your designed posting. Thus you can dig your piers without obstruction.

Your supporting posts, if you call them that, are just scab lumber. I guess we've never had OSHA show up.

Sounds crazy, I know, but actually works pretty well.

Best

Peter

EDIT.... Oh Joe, you only do it on elevated decks where you can still dig below it.
__________________
Never stop learning (xcep fer speling en typeing)
MTN REMODEL LLC is offline   Reply With Quote
The Following User Says Thank You to MTN REMODEL LLC For This Useful Post:
kwikfishron (06-10-2013)
Old 06-09-2013, 09:55 PM   #15
Member
 
Davejss's Avatar
 
Join Date: May 2012
Location: Northern Massachusetts
Posts: 335
Default

Deck being built before footings?


Quote:
Originally Posted by joecaption View Post
I've never once heard of or seen anyone build one that way.
How do they expect to dig a footing below the frost line and fill it with the deck in the way.
Makes no since to me.
We do all ours this way. We build the box ( rim joists) square it up, build our beam, drop plumb bobs and dig our holes. 48" deep is code up my way.

Davejss is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
temporary exteriors steps until deck is built jrschneider9904 Building & Construction 13 10-04-2012 10:08 AM
Deck built by builder: mains supports for the hand rail going around deck is pickets? mrrich01 Building & Construction 10 10-04-2012 10:06 AM
Master Bedroom built on Deck BeMurda Insulation 9 12-03-2011 11:34 AM
Proper sizing for deck footings stubits Building & Construction 14 02-11-2010 11:26 AM
Concrete Deck Footings Bumpy Melanie337 Building & Construction 6 09-24-2007 08:11 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.