12-10-2012, 10:58 PM
|
#1
|
|
Member
Join Date: Nov 2012
Location: Toledo, OH
Posts: 182
|
Cross beams in ceiling joists
Can these cross beams be removed completely or should they be put back up once i'm done?
|
|
|
Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. DIYChatroom.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any home improvement task!
12-10-2012, 11:35 PM
|
#2
|
|
Haverhill Trade 1965
Join Date: Mar 2012
Location: New Hampshire
Posts: 405
|
Cross beams in ceiling joists
These are called bridging. They transfer a load by compression from the top of one joist to the bottom of one on either side. They reduce flexing, (some bouncing of the floor), of one joist at a time so they should go back in.
|
|
|
12-11-2012, 09:48 AM
|
#3
|
|
Member
Join Date: Nov 2011
Location: Hartfield VA
Posts: 18,179
|
Cross beams in ceiling joists
You also need to look into getting that mold treated that's growing on the joist.
http://www.doyourownpestcontrol.com/timbor.htm
Is there a 6 mil. vaper barrier on the ground?
|
|
|
12-11-2012, 01:47 PM
|
#4
|
|
Moderator
Join Date: Mar 2009
Posts: 8,775
|
Cross beams in ceiling joists
If you pulled them out completely, you may want to buy some metal replacements http://www.strongtie.com/products/co...tb.asp#tables2 as the existing wood cross-bridging (9% effective for deflection) are almost impossible to re-nail at the top of joist, high enough. OR, just add a full size blocking (15% effective) between the removed ones, or add 1x4 strapping to the bottoms (25% effective/deflection)of all after replacing; http://www.ewpa.com/Archive/2004/jun/Paper_278.pdf
Gary
__________________
Clothes taking longer to dry?
Clean the dryer screen in HOT water if using fabric softener sheets.
They leave a residue that impedes air-flow, costing you money.
Clean the ducting in the last six months? 17,000 dryer fires annually!
|
|
|
12-15-2012, 02:41 AM
|
#5
|
|
Member
Join Date: Nov 2012
Location: Toledo, OH
Posts: 182
|
Cross beams in ceiling joists
Wow thanks guys for all your responses. Can the cross beams be glued back between the joists?
No there is just a concrete slab. But I am in the process of insulating it very well now(walls, rim joists, ceiling)
I'm putting drywall up in between the joists so can the cross beams be lowered to accommodate the 5/8" drywall?
|
|
|
12-15-2012, 08:47 AM
|
#6
|
|
Civil Engineer
Join Date: Mar 2009
Location: Boston
Posts: 3,559
|
Cross beams in ceiling joists
Those are not cross beams, they are X bracing as previously described. There is no effective way to glue wooden X bracing in place. If you need to get the bracing out of the way to allow installation of drywall, you can install steel X bracing as previously discussed by GBR.
|
|
|
12-15-2012, 09:00 PM
|
#7
|
|
Moderator
Join Date: Mar 2009
Posts: 8,775
|
Cross beams in ceiling joists
"I'm putting drywall up in between the joists so can the cross beams be lowered to accommodate the 5/8" drywall?"---------- I don't understand. Why would you install drywall above the cross-bridging? Why against the flooring? I must be missing a thought here.....
Gary
__________________
Clothes taking longer to dry?
Clean the dryer screen in HOT water if using fabric softener sheets.
They leave a residue that impedes air-flow, costing you money.
Clean the ducting in the last six months? 17,000 dryer fires annually!
|
|
|
12-15-2012, 09:59 PM
|
#8
|
|
Member
Join Date: Nov 2012
Location: Toledo, OH
Posts: 182
|
Cross beams in ceiling joists
It's for soundproofing purposes. Drywall and Greenglue against the subflooring. So can they go back up just a little lower 5/8" because of the drywall?
|
|
|
12-15-2012, 10:14 PM
|
#9
|
|
Moderator
Join Date: Mar 2009
Posts: 8,775
|
Cross beams in ceiling joists
Ahh... Appears you need to shorten a few that flush at the joist bottom. Leave a space between opposing ones so they don't rub/squeak. I usually clip the "air-nails" or "shiners" that miss the joist from above, same reason.
Gary
__________________
Clothes taking longer to dry?
Clean the dryer screen in HOT water if using fabric softener sheets.
They leave a residue that impedes air-flow, costing you money.
Clean the ducting in the last six months? 17,000 dryer fires annually!
|
|
|
12-15-2012, 10:17 PM
|
#10
|
|
Member
Join Date: Nov 2012
Location: Toledo, OH
Posts: 182
|
Cross beams in ceiling joists
awesome thank you very much.
|
|
|
-->
| Thread Tools |
Search this Thread |
|
|
|
| Display Modes |
Linear Mode
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
|
|