Basement addition foundation questions


I am putting a 16'x16' addition on my house. I have decided to go with a full basement addition under it, which will be connected to my existing unfinished basement. I have 8" thick poured walls with brick facing. The new addition will also be done with brick faced forms. I have a few questions about this process and the contractor seems to be pretty non-chalant about it, so I thought I'd get some other opinions.

1. How should the new addition be attached? Bolts, rebar? Should the existing walls be notched out and the new ones poured within them, or just butted up?

2. My existing foundation has Form-A-Drain on the inside and socked 3" tile/rock around the outside. My soil is very sandy, and I've never had a problem with leaking in the 5 years we've been here. I have never noticed the sump pump running, even during heavy rainfall periods. So, what should I do for drainage around the addition?

3. What should I do for waterproofing on the new walls? The existing foundation has damproofing to grade.

I appreciate any info anyone can provide!

hoggin03 is offline   Reply With Quote
Old 05-26-2009, 11:02 PM   #2
Concrete & Masonry
 
Join Date: Nov 2008
Location: Wisconsin
Posts: 2,720
Rewards Points: 0
Default

Basement addition foundation questions


Quote:
Originally Posted by hoggin03 View Post
I am putting a 16'x16' addition on my house. I have decided to go with a full basement addition under it, which will be connected to my existing unfinished basement. I have 8" thick poured walls with brick facing. The new addition will also be done with brick faced forms. I have a few questions about this process and the contractor seems to be pretty non-chalant about it, so I thought I'd get some other opinions.

1. How should the new addition be attached? Bolts, rebar? Should the existing walls be notched out and the new ones poured within them, or just butted up?
Definately rebar , probably #4 or #5's on 16-24" centers.

2. My existing foundation has Form-A-Drain on the inside and socked 3" tile/rock around the outside. My soil is very sandy, and I've never had a problem with leaking in the 5 years we've been here. I have never noticed the sump pump running, even during heavy rainfall periods. So, what should I do for drainage around the addition?
This is kind of an odd set-up, at least for my region. I've never seen a combo system with Form-a-Drain & 3" corragated. I would probably suggest just sticking with the 3" in this situation, or whatever your mason suggests.

3. What should I do for waterproofing on the new walls? The existing foundation has damproofing to grade.
A spray-on damproofing shoud be adequate in you situation.

I appreciate any info anyone can provide!
Most importantly, find a contractor you feel comfortable with, & all these concerns can be put behind you.

jomama45 is offline   Reply With Quote
Old 05-27-2009, 06:23 AM   #3
Member
 
Join Date: Dec 2008
Location: Wilmington, DE
Posts: 3,118
Rewards Points: 0
Default

Basement addition foundation questions


Good reply above, especially the last suggestion. But check local code, they have the final say. And find a contractor that builds to 'code +' specs. Building to code is just getting by, 'code +' goes a step further, and usually results in fewer porblems over time.
Just Bill is offline   Reply With Quote
Old 05-28-2009, 09:51 AM   #4
Newbie
 
Join Date: May 2009
Posts: 9
Rewards Points: 0
Default

Basement addition foundation questions


Thanks for the replies. Does anyone else have any input?
hoggin03 is offline   Reply With Quote
Old 05-28-2009, 05:48 PM   #5
Member
 
Join Date: May 2008
Posts: 567
Rewards Points: 0
Default

Basement addition foundation questions


rebar as post'd,,, those of us in the waterproofing trade'd probably choose a trowel'd-on coating of sonneborn sonolastic ( or equilavant ) protected by pvc dimpleboard ( miradrain ) leading down to 4" perf pipe in a filtercloth lined trench cover'd by 3/4" stone,,, the spec, far's i know, is still 3mil dampproofing ( roll'd on asphalt emulsion ) not acceptable for my home ESPECIALLY that cold joint ! ! !
yesitsconcrete is offline   Reply With Quote
Old 05-28-2009, 06:02 PM   #6
Newbie
 
Join Date: May 2009
Posts: 9
Rewards Points: 0
Default

Basement addition foundation questions


Quote:
Originally Posted by yesitsconcrete View Post
rebar as post'd,,, those of us in the waterproofing trade'd probably choose a trowel'd-on coating of sonneborn sonolastic ( or equilavant ) protected by pvc dimpleboard ( miradrain ) leading down to 4" perf pipe in a filtercloth lined trench cover'd by 3/4" stone,,, the spec, far's i know, is still 3mil dampproofing ( roll'd on asphalt emulsion ) not acceptable for my home ESPECIALLY that cold joint ! ! !
I gotta admit, you are a little above my pay grade here! I understand what you're saying about the rebar, perf pipe/stone for drainage, and rolled on asphalt; but the stuff about sonneborn sonolastic and dimpleboard is a little out of my league. If you could give me some more info on that it would be much appreciated!
hoggin03 is offline   Reply With Quote
Old 05-28-2009, 08:44 PM   #7
Member
 
Join Date: Oct 2008
Location: Wisconsin
Posts: 228
Rewards Points: 0
Default

Basement addition foundation questions


I would have your concrete contractor drill rebar dowels into the existing footings and walls in order to make sure your new foundation moves with the existing foundation. Also, even though you mention you don't have a water problem, I would install a vertical waterstop at the cold joint between new/old walls. You can get a peel and stick bentoninte (sp?) waterstop specifically for this application.
__________________
Some advice you receive on the internet can be worth exactly what you paid for it - be careful.
stubborn1 is offline   Reply With Quote
Old 05-29-2009, 07:28 AM   #8
Member
 
Join Date: May 2008
Posts: 567
Rewards Points: 0
Default

Basement addition foundation questions


that's why we have google bentonite - w r grace - sonneborn - miradrain - sonolastic - euclid chemical ( euco ),,, none of the above're avail at the apron stores - that's why its above your pay grade pro const supply houses carry these products,,, good luck ! ! !

yesitsconcrete is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Garage addition concrete questions Jim Hart Building & Construction 5 05-21-2009 11:18 AM
How much to to pour 30 x 40 foundation 6 ft. basement anyone thanks sharppick Building & Construction 3 04-24-2009 10:07 PM
subpanel mounting on concrete basement foundation wall bulk88 Electrical 12 03-10-2009 01:38 PM
Custom Shower addition plumbing questions alxv Plumbing 1 10-09-2008 02:34 PM
Concrete Block Foundation Questions project_guy Building & Construction 1 05-09-2008 09:16 AM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.