tibberous 04-06-2013 11:49 AM

Anchoring block to a footer
 
I am building a block garage but can't find a good video on how to tie the block to the footer. It looks like you drill bolts into the block, then holes into the footer, then epoxy them? Is this step even needed?

Daniel Holzman 04-06-2013 12:09 PM

Most of the time I see the block getting grouted, with a rebar or J bolt embedded in the foundation and grouted into the block. If you failed to install J bolts when you poured the foundation, you can epoxy them in later. I often see every other block getting J bolted, but the requirements will likely vary with local code.

jagans 04-06-2013 12:15 PM

1 Attachment(s)
You can simply embed a 2 x 4 on edge into the middle of your footer when you pour it and this will make a channel into which your mortar filled first course of CMU will key

concretemasonry 04-06-2013 12:38 PM

Determine where the anchor bolts and vertical rebar stubs(if any) will be. Mark the locations on the footing form or the footing if it is already poured.

Place the anchor bolts and rebar (if any) into the concrete when pouring and recheck the locations before everything is set.

If you need to fill any cores (containing rebar), use masonry grout (8"-11"slump - very wet) to get a better job than using concrete, plus it is code to use grout and not concrete.

If the footing is already poured, drill the locations for inserts and epoxy in place before laying block.

When you lay the first course in a full mortar bed (mortar under both the face shells and webs) and use "face shell"bedding for the remaining courses. The 2x4 "ditch is not needed if there are anchor bolts. Filling the first course solid is not necessary.

Dick

Canarywood1 04-06-2013 07:18 PM

+1 to what Dick said,2x4 channel is usually used only in a poured concrete foundation.

jagans 04-06-2013 09:29 PM

Garnted, no need to completely fill the block. As far as keying, my way seems a hell of a lot easier since you don't have a chance of the anchor bolts or rebar hitting a web in the block, but Im sure there is some reason that its not compliant with some ridiculous code. Rebar would make more sense in a poured wall where there are no block webs to worry about.

Canarywood1 04-07-2013 12:25 PM

Quote:

Originally Posted by jagans (Post 1153822)
Garnted, no need to completely fill the block. As far as keying, my way seems a hell of a lot easier since you don't have a chance of the anchor bolts or rebar hitting a web in the block, but Im sure there is some reason that its not compliant with some ridiculous code. Rebar would make more sense in a poured wall where there are no block webs to worry about.


Rebar must be in all cmu walls,not neccessary in a poured wall.