I am almost done with my underground power project, and getting ready to put the three required PVC conduit lines in the trench: one 2" and two 1" for power, cable, and telco.

Since I don't ever want to dig that stuff up again, I want to future-proof it if possible by placing any additional conduit lines in there if it makes sense. For instance, fiber might be a reality in the next 10yrs, and I see that special conduit liners are sometimes used for this so my existing lines may not be suitable. I also wonder if a metalized conduit line and/or a tracer wire make sense.

tns1 is offline   Reply With Quote
Old 07-17-2009, 04:36 PM   #2
Electrical Contractor
 
jbfan's Avatar
 
Join Date: Jun 2004
Location: Newnan GA
Posts: 5,634
Default

Underground services -


If something comes up in the furture, it can replace either the phone or cable.
The problem I see is forgetting where both ends of the pipes are 10 years from now.

__________________
Yes I am a Pirate, 200 years too late. "Jimmy Buffett"
jbfan is offline   Reply With Quote
Old 07-17-2009, 05:45 PM   #3
Member
 
Join Date: Oct 2007
Posts: 2,294
Default

Underground services -


I wouldn't bother with a tracer wire as the power, phone and cable can all be easily traced.

Put an extra 1" in there and you will sleep better at night
220/221 is offline   Reply With Quote
Old 07-17-2009, 06:05 PM   #4
Member
 
Join Date: Jan 2009
Location: South of Boston, MA
Posts: 17,248
Default

Underground services -


When mine was buried they did (3) 3" conduits
Seems overkill looking back

When I buried a line to my cabana I put in (2) extra 1.5" since I had it kicking around
Scuba_Dave is offline   Reply With Quote
Old 07-19-2009, 05:07 PM   #5
Member
 
Join Date: Jun 2009
Location: San Diego, CA
Posts: 195
Default

Underground services -


The Poco here gave me paperwork describing the trenching and conduit requirements. Part of that describes how the cable and telco conduit will exit my trench and run right up the side of the existing utility pole. The power conduit is different though. It is described as running up a standoff of some kind which will be attaced to the utility pole and keep the conduit parallel, but at a 7" distance from the pole.

Part of the reason for my project is to remove the unsightly lines hanging over my front yard. I had figured I could even paint the exposed conduit the same color as the pole to help it blend in. I'd like to see what one of these standoff things looks like installed, to see if it is even uglier than what I have already.
tns1 is offline   Reply With Quote
Old 07-19-2009, 05:22 PM   #6
Member
 
Code05's Avatar
 
Join Date: May 2009
Location: Easton MD
Posts: 1,841
Default

Underground services -


Stand offs in the elec trade are usually these:
http://www.minerallac.com/Hangers.htm
Code05 is offline   Reply With Quote
Old 07-20-2009, 12:52 AM   #7
Member
 
Join Date: Jun 2009
Location: San Diego, CA
Posts: 195
Default

Underground services -


Looking at the paperwork, it is either called a riser, or a ladder arm. These hold the conduit at a distance of 7.5" from the pole. Since all three conduits are attached to the same quadrant of the pole, I can only guess the riser is used to maintain the separation of power line from cable and telco lines also running vertically up the pole, and the same reason there is a 12" separation required in the trench.

Any pics of this type of setup?

tns1 is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
New Underground Gas Line steve f Plumbing 20 03-04-2011 08:15 PM
Underground service entrance cable requirements. kgt55 Electrical 9 06-22-2009 06:55 AM
Underground Container vs. Sewer? gante Plumbing 3 03-18-2009 07:25 PM
Converting duplex to single family--what to do with electric services? zamoti Electrical 32 01-29-2009 03:16 PM
Rough underground plumbing for basement bathroom JTK Plumbing 1 07-23-2008 08:30 AM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.