Questions about Electrical Rough-In Inspection....


I am doing a 600 sq ft basement finishing job that I pulled permits for. There is a rough in electrical inspection and a final. I just have a few questions for the rough-in inspection.

What do they typical expect as far as installing the breaker and the wire that goes into the panel box? Do I put the breaker in and just not hook it up or leave the wire curled up outside of the box?

I also have a bunch of HALO recessed lights installed....can I strip and install the wires in the little easy hook-up connectors that you just push the bare wire into? Or should I just leave the wire not-connected?

I also have a sub-panel 100AMP box installed in the garage off the main panel in the house (previous work). The electrician just installed the 100AMP wire to the bottom of the joists (I only have 7 inch nominal joists and putting a hole big enough in them for that big of a wire would have weakened them). Is this going to be a problem during the inspection?

Thanks for all the tips. Any help you can provide would be great.

AllGoNoShow is offline   Reply With Quote
Old 05-14-2013, 01:25 PM   #2
Lic Electrical Inspector
 
electures's Avatar
 
Join Date: Dec 2009
Location: The Great Police State of New Jersey
Posts: 1,617
Default

Questions about Electrical Rough-In Inspection....


Please refer to post #13 in this thread. This is what I like. Your EI may be different.

__________________
All responses based on the 2011 NEC.
If you live in New Jersey click here. All other states click here.
Please check with local, county and state officials as laws may vary.
Sizing motors here. Online motor calculator here. Online calculators here.
electures is offline   Reply With Quote
Old 05-14-2013, 02:44 PM   #3
Special User
 
Join Date: Jul 2012
Location: Idaho, US
Posts: 551
Default

Questions about Electrical Rough-In Inspection....


The idea of a rough inspection is, to catch and fix any mistakes that would be hard to correct after drywall goes up. So really what matters most is stapling, drilling, securing boxes to studs, pulling the right kinds of wire into boxes with enough free length, etc. Anything that can still be fixed after drywall goes up probably doesn't need to be done on rough. So generally, devices and breakers are not installed.

Every inspector is different, but I might suggest making up the ground connections in the wall boxes and in the panel. The reason some (not all) inspectors like to see grounds made up on rough, is it's hard to see them once the switches and receptacles are in the box. (Especially for metal boxes that have to be bonded via the ground wire.)
__________________
The above post is for entertainment purposes only. Its contents may, and probably will, lead to legal liability and damage or loss of property, life, or limb. Use at your own risk.
tylernt is offline   Reply With Quote
Old 05-14-2013, 02:53 PM   #4
Member
 
Join Date: May 2013
Posts: 164
Default

Questions about Electrical Rough-In Inspection....


Your local inspector will tell you exactly what they want to see. This is an open wall inspection and primarily to see if wire is sized correctly secured as needed and stud plates where needed.
usair is offline   Reply With Quote
Old 05-14-2013, 07:11 PM   #5
Member
 
Join Date: Aug 2006
Posts: 118
Default

Questions about Electrical Rough-In Inspection....


Thanks for the tips. I will have to give the electrical inspector a call to get some details on what he wants.

As far as putting a new wire for a circuit in a panel....does it matter if I use a side knockout or one of the top knock outs? All my wires now come in the top but it would be easier to use a side one for these circuits.
AllGoNoShow is offline   Reply With Quote
Old 05-14-2013, 07:27 PM   #6
Special User
 
Join Date: Jul 2012
Location: Idaho, US
Posts: 551
Default

Questions about Electrical Rough-In Inspection....


Side knockouts are unusual because there's usually a stud there, but nothing prevents you from using one for branch circuits (feeders have some limitations on bending them).

Try to pick a knockout that won't be right on top of a neutral or ground bus.

__________________
The above post is for entertainment purposes only. Its contents may, and probably will, lead to legal liability and damage or loss of property, life, or limb. Use at your own risk.
tylernt is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Various electrical questions joeh Electrical 1 01-04-2012 07:34 AM
Schedule 40 PVC in Chicago? franwalker Electrical 56 12-20-2011 10:04 PM
Electrical Inspection Question Redsy Electrical 7 09-02-2011 02:55 PM
Ontario Electrical - potlights at rough in ??? anotherguy2010 Electrical 9 01-04-2011 08:38 PM
Electrical Inspection mike6679 Electrical 5 01-09-2010 10:35 AM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.