Go Back   DIY Chatroom Home Improvement Forum > Home Improvement > Electrical

CLICK HERE AND JOIN OUR COMMUNITY TODAY...IT'S FREE!

Reply
 
Thread Tools Search this Thread Display Modes
Old 03-06-2011, 11:14 AM   #1
Newbie
 
Join Date: Mar 2011
Posts: 4
Share |
Default

Garage Subpanel Wiring Question


Iím in the middle of wiring a 50amp subpanel in my attached garage for a welder and compressor (they won't be used at the same time so 50amp is sufficient). I have a couple of questions about using NM-B cable:

I plan to run about 30í of 6-3 Romex (NM-B) cable along the floor joists in the basement from the main panel to an existing opening in the wall between the basement and garage. For physical protection going through the wall and into the subpanel, Iíd like to remove the outer PVC jacket of the cable and run the three wires (plus ground) in ĺĒ EMT conduit for approx. 6í (see pictures below). Iíll use an EMT to Romex fitting or bushing to transition. Iíve read that NM-B uses THHN wires, so is removing the PVC sheathing for a 6í run like this ok to do?

On the same subject, I also need to continue running #6 wire in a conduit from the subpanel to an outlet in the garage. Iíd like to use the remaining NM-B cable since Iíll have some left over, but I donít want to try to run cable through a conduit. It seems like I should be able to remove the PVC jacket and run the wires individually, but the wires arenít individually labeled as being THHN, so I donít know if this is ok to do.

Everything will be inspected before the final connections are made, but any advice would be appreciated. Thanks




Joe85 is offline   Reply With Quote
Old 03-06-2011, 11:50 AM   #2
Member
 
Join Date: Nov 2007
Location: Nashua, NH, USA
Posts: 6,867
Default

Garage Subpanel Wiring Question


I would put a junction box at the end of the conduit, with all of the appropriate clamps and fittings to admit the Romex cable and from there run the wire ends minus the sheath into the conduit.

__________________
Stop wasting time re-adjusting the pattern. Have several lawn sprinklers, one for each pattern.
AllanJ is offline   Reply With Quote
Old 03-06-2011, 11:51 AM   #3
Licensed electrician
 
Join Date: Sep 2007
Location: Maryland
Posts: 7,415
Default

Garage Subpanel Wiring Question


The conductors inside NM type cable are not labeled as to their insulation and cannot be stripped of the overall sheath and used in conduit as you propose. You can transition in a junction box to individual conductors or continue the conduit to the other panel.
__________________
Answers based on the National Electrical Code. Local amendments may apply. Check with your local building officials.
Jim Port is online now   Reply With Quote
Old 03-06-2011, 12:23 PM   #4
Newbie
 
Join Date: Mar 2011
Posts: 4
Default

Garage Subpanel Wiring Question


Thanks for the replies. What you said about the rating of the wires makes sense for the sub-panel to outlet run, but I just want to be clear about the run between the main panel and sub-panel.....it would be a continuous run with the 6' of individual wires clearly belonging to the cable. So you're saying that the wires that belong to the cable aren't rated for individual use? Thanks
Joe85 is offline   Reply With Quote
Old 03-06-2011, 12:46 PM   #5
Member
 
Join Date: Dec 2010
Posts: 172
Default

Garage Subpanel Wiring Question


why not run a bigger conduit and not strip of the sheathing?
awdblazer is offline   Reply With Quote
Old 03-06-2011, 12:58 PM   #6
Newbie
 
Join Date: Mar 2011
Posts: 4
Default

Garage Subpanel Wiring Question


Quote:
why not run a bigger conduit and not strip of the sheathing?
That's probably what I'll end up doing, step up to 1" or 1 1/4" and run the full cable through. That'll teach me not to start working before asking the questions
Joe85 is offline   Reply With Quote
Old 03-06-2011, 01:25 PM   #7
Member
 
joed's Avatar
 
Join Date: Mar 2005
Location: Welland, Ontario
Posts: 7,398
Default

Garage Subpanel Wiring Question


Why not run the cable direct to the panel. It does not look to be 'subject to damage' being that high up on the wall.
__________________
Do not PM with questions that can be asked in a forum. I will not respond.
joed is online now   Reply With Quote
Old 03-06-2011, 01:37 PM   #8
Member
 
iminaquagmire's Avatar
 
Join Date: Jul 2010
Location: Chicagoland
Posts: 370
Default

Garage Subpanel Wiring Question


I'd put a junction box right there at the end of that last 90 and transition to your romex right there. BTW, there is nothing saying that you cannot run the romex in conduit, either sleeving for protection (24" or less before derating) or through the entire run. You must calculate conduit fill by using the widest dimension of the romex. 6-3 is round anyway though.
iminaquagmire is offline   Reply With Quote
Old 03-06-2011, 02:21 PM   #9
Newbie
 
Join Date: Mar 2011
Posts: 4
Default

Garage Subpanel Wiring Question


Quote:
Why not run the cable direct to the panel. It does not look to be 'subject to damage' being that high up on the wall.
I'm more concerned about where the cable goes through the wall. I don't want the Romex contacting the edge of one of the cinder blocks.

Quote:
I'd put a junction box right there at the end of that last 90 and transition to your romex right there. BTW, there is nothing saying that you cannot run the romex in conduit, either sleeving for protection (24" or less before derating) or through the entire run. You must calculate conduit fill by using the widest dimension of the romex. 6-3 is round anyway though.
1" EMT gives the right fill if I use the cable so that seems to be the best solution. The run from the sub-panel to the outlet is another 30' around the garage walls, so at this point I'm trying make the most of the cable I already have.
Joe85 is offline   Reply With Quote
Old 03-06-2011, 02:56 PM   #10
Licensed electrician
 
Join Date: Sep 2007
Location: Maryland
Posts: 7,415
Default

Garage Subpanel Wiring Question


Quote:
Originally Posted by AllanJ View Post
I would put a junction box at the end of the conduit, with all of the appropriate clamps and fittings to admit the Romex cable and from there run the wire ends minus the sheath into the conduit.
This would not be Code compliant. The cable is listed as an assembly. Stripping the outer sheath removes the listing as the condictors are now unidentified as to type.
__________________
Answers based on the National Electrical Code. Local amendments may apply. Check with your local building officials.
Jim Port is online now   Reply With Quote
Old 03-06-2011, 03:14 PM   #11
Electrical Contractor
 
kbsparky's Avatar
 
Join Date: Sep 2008
Location: Delmarva
Posts: 3,363
Default

Garage Subpanel Wiring Question


Simply install one of these on the end of your conduit, and you're all set!


__________________
-KB

Life is uncertain -- eat dessert first!!
kbsparky is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Critique my wiring plan for my garage tigereye Electrical 10 03-24-2009 09:55 PM
Legal to have subpanel in garage? gante Electrical 36 03-13-2009 03:27 PM
Yup, another subpanel wiring question! 737Pilot Electrical 3 12-17-2008 01:07 PM
subpanel question Brik Electrical 2 11-30-2008 05:31 AM
Wiring new detached garage/studio WShawn Electrical 4 07-21-2008 06:13 PM




Top of Page | View New Posts