We are installing our HVAC ductwork and I want to get some opinions on the best way to work around the center beam in our basement. The center beam is about 20" tall and the main trunk line will go on the East side of the center beam. Then we have 3 6" ducts we need to connect to the truck that are on the West side of the center beam. Is there any problems if we run the West side ducts to the center beam then drop them down about 24" (or enough to clear the center beam) and then go back up on the other side of the center beam to the main trunk line? Will this 24" drop and raise hurt the efficiency of the system?

Anybody have any other ideas how to work around this center beam and maintain an efficient system?

Here is a picture of one of the West side ducts we need to connect to the trunk which will be on the other side of the center beam shown in the picture. Also is a picture of the center beam will must work around.




Build is offline   Reply With Quote
Old 06-15-2009, 01:41 PM   #2
Member
 
Join Date: Dec 2008
Location: West Michigan
Posts: 440
Default

Ductwork Around Center Beam


You could run the duct the way you are suggesting but use as few elbows as possible because it will cut down your airflow quite a bit.
I suggest, if its feasible, cutting out the joist space above the beam enough to get the runs through.

SKIP4661 is offline   Reply With Quote
Old 06-15-2009, 01:59 PM   #3
Newbie
 
Join Date: May 2009
Posts: 22
Default

Ductwork Around Center Beam


When you say the "joist space above the beam" you mean the board at the end of the floor joist right (the board perpendicular to the floor joist)?

Is that an option? That board is a 2" x 10" and I know if it was an actual floor joist that would not be an option b/c a 6" hole in a 10" board is a definite no-no.

The red cirle marks the hole right?


Last edited by Build; 06-15-2009 at 02:05 PM.
Build is offline   Reply With Quote
Old 06-15-2009, 02:05 PM   #4
Member
 
Join Date: Dec 2008
Location: West Michigan
Posts: 440
Default

Ductwork Around Center Beam


If that 2 by 10 is supported by the center beam, which it appears to be, it shouldn't be a problem to cut out the joist space.
Yes the red spot would be ideal.

Last edited by SKIP4661; 06-15-2009 at 02:07 PM.
SKIP4661 is offline   Reply With Quote
Old 06-15-2009, 02:12 PM   #5
Newbie
 
Join Date: May 2009
Posts: 22
Default

Ductwork Around Center Beam


I agree that would be the ideal way. I just did not think that was an option. There is another 2" x 10" on the other so we would actually have to cut through two 2" x 10"s. That would take a bit of work but is very doable and would definitely be the ideal route for the ducts.

Is there any codes or regulations regarding cuts like that? I know when it comes to floor joists there are certain requirements that must be followed.
Build is offline   Reply With Quote
Old 06-15-2009, 09:08 PM   #6
Member
 
Join Date: Dec 2008
Location: West Michigan
Posts: 440
Default

Ductwork Around Center Beam


You could check with your local building inspector, he would know for sure.
SKIP4661 is offline   Reply With Quote
Old 06-16-2009, 10:56 AM   #7
Member
 
Join Date: Mar 2009
Location: Pennsylvania
Posts: 719
Default

Ductwork Around Center Beam


You could come out of the trunk line end cap with round and run it to the end of the basement go under then back up and run tight to the ceiling down the side that way you would not be cutting any supports and will still maintain your flow and the only low spot would be the end of the basement you could box out.

Another way is to transition to oval duct to cut down on the hole height giving you more strength, I would also cut blocks to fit next to the hole to give more support to the beam you are cutting.

SULTINI is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Jacking up house, full length joists raised beam off of center colums. Suggestions? slowjo Building & Construction 9 Today 06:56 AM
Floor "bells" over the center carrier beam... RyanUsesThis Flooring 8 05-11-2009 05:00 AM
Beam Replacement? Steve Dailey Carpentry 5 05-19-2008 08:46 PM
Drilling into Center Beam leted_82 Building & Construction 2 03-06-2007 08:52 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.