What to leave open for inspection?


I picked up electrical and building permits for my remodel. The building inspectors wants to come by for only the final, before I put on the tape and mud on the drywall. My biggest issue is with the electrical inspector: I'm going to have entire spots where I can't hang drywall because I'm needing to keep the area open for electrical inspection. Is the inspector going to want to see exactly how I've attached the boxes, nailed the wire to the stud, etc? Or can I just put up the drywall and leave the wire hanging out? I have a full basement where you can trace all the wire back to the panel. Bare drywall is ugly, but a room of mixed drywall/bare insulation is even worse. I'd rather be able to just hang the drywall, call it done and move to the next room.

Advertisement

forkvoid is offline   Reply With Quote
Old 02-12-2009, 04:07 PM   #2
Member
 
Join Date: Jan 2009
Location: South of Boston, MA
Posts: 17,248
Rewards Points: 2,000
Default

What to leave open for inspection?


Where I am the electric inspection is seperate & before any insulation or sheetrock is installed. Better make sure

Advertisement

Scuba_Dave is offline   Reply With Quote
Old 02-12-2009, 04:08 PM   #3
Chicago, IL
 
Michael Thomas's Avatar
 
Join Date: Jan 2008
Location: Chicago, IL
Posts: 1,037
Rewards Points: 500
Default

What to leave open for inspection?


Odd. Around here their is always a pre-closeup and a final inspection.
Michael Thomas is offline   Reply With Quote
Old 02-12-2009, 04:15 PM   #4
Newbie
 
Join Date: Feb 2009
Location: Knoxville, TN
Posts: 8
Rewards Points: 10
Default

What to leave open for inspection?


Quote:
Originally Posted by Scuba_Dave View Post
Where I am the electric inspection is seperate & before any insulation or sheetrock is installed. Better make sure
The problem with going that route is that I'm doing the entire house. That would leave me a house without any insulation or drywall at all until the entire thing was ready for inspection.

Quote:
Originally Posted by Michael Thomas
Odd. Around here their is always a pre-closeup and a final inspection.
I spoke to the building inspector and he said he didn't want to waste my time with anything but a final inspection, since I'm not changing any framing or anything of the sort. I can't get hold of the electrical inspector(his voice mail says he only answers his phone between 8am and 8:30am Monday through Friday; he also does not return calls). How I routed the electrical wires, there's absolutely no reason to inspect anything but where the electrical is. Typically, there's two or three studs to either side that are open currently for his inspection.
forkvoid is offline   Reply With Quote
Old 02-12-2009, 06:06 PM   #5
Member
 
Join Date: Jan 2009
Location: South of Boston, MA
Posts: 17,248
Rewards Points: 2,000
Default

What to leave open for inspection?


Building Inspector can do what they want
Since the structure is existing the main issue is if you use the proper insulation

But electric is a whole nother ball game
They usually want to see rough 1st, then the final
Scuba_Dave is offline   Reply With Quote
Old 02-12-2009, 06:57 PM   #6
Newbie
 
Join Date: Feb 2009
Location: Knoxville, TN
Posts: 8
Rewards Points: 10
Default

What to leave open for inspection?


What constitutes a rough in? Just installing boxes or running cable but not hooking into the panel? Final would be installation of the sockets and hooking into the panel?
forkvoid is offline   Reply With Quote
Old 02-12-2009, 07:05 PM   #7
Member
 
Join Date: Jan 2009
Location: South of Boston, MA
Posts: 17,248
Rewards Points: 2,000
Default

What to leave open for inspection?


Rough for us is boxes installed, wire run, wire coming out of the boxes ready for devices/outlets/switched
I was told to have the neutrals & grounds landed = no hots
Not sure if that is how it is everywhere
Scuba_Dave is offline   Reply With Quote
Old 02-12-2009, 08:06 PM   #8
Newbie
 
Join Date: Feb 2009
Location: Knoxville, TN
Posts: 8
Rewards Points: 10
Default

What to leave open for inspection?


Okay that's what i have right now. I just want to know if they need to see the wires between the box and the subfloor.
forkvoid is offline   Reply With Quote
Old 02-12-2009, 08:30 PM   #9
Member
 
Join Date: Jan 2009
Location: South of Boston, MA
Posts: 17,248
Rewards Points: 2,000
Default

What to leave open for inspection?


I have wire running along the floor joist - 2nd floor
I cut the piece of plywood, but its not secured in place
So that can be opened for inspection
But in my sunroom I had the subfloor down - since the walls were built on top of the sub-floor. It wasn't a problem

Its up to your Inspector on what they want

Not sure what others maybe have encountered?
Scuba_Dave is offline   Reply With Quote
Old 02-12-2009, 09:09 PM   #10
Learning by Doing
 
Leah Frances's Avatar
 
Join Date: Jan 2008
Location: Easton, Maryland
Posts: 3,156
Rewards Points: 2,000
Blog Entries: 7
Default

What to leave open for inspection?


Set your alarm clock and get up and CALL THE INSPECTOR AND ASK HIM. The electrical inspector in your jurisdiction is the only one who knows the answers to these questions.
__________________
If I could only remember to THINK about what I was doing before I did it.
Leah Frances is offline   Reply With Quote
Old 02-12-2009, 10:29 PM   #11
Newbie
 
Join Date: Feb 2009
Location: Knoxville, TN
Posts: 8
Rewards Points: 10
Default

What to leave open for inspection?


Quote:
Originally Posted by Leah Frances View Post
Set your alarm clock and get up and CALL THE INSPECTOR AND ASK HIM. The electrical inspector in your jurisdiction is the only one who knows the answers to these questions.
I've been trying. It goes to voice mail. He does not return calls. I suspect the only time I'm going to see him is when I schedule an inspection through the main office.
forkvoid is offline   Reply With Quote
Old 02-12-2009, 10:53 PM   #12
Member
 
Join Date: Feb 2009
Location: Plant City, Florida
Posts: 46
Rewards Points: 25
Default

What to leave open for inspection?


Quote:
Originally Posted by forkvoid View Post
Okay that's what i have right now. I just want to know if they need to see the wires between the box and the subfloor.
If he is a good inspector and does his job, he will want to see all of your work, BEFORE it is covered up.

A good inspector will look closer at a homeowners work than a professionals work, because the HO usually don't know what they are doing.
bwalley is offline   Reply With Quote
Old 02-13-2009, 11:23 AM   #13
Newbie Bill
 
Join Date: Dec 2008
Location: Alberta, Canada
Posts: 1,056
Rewards Points: 500
Default

What to leave open for inspection?


Quote:
Originally Posted by forkvoid View Post
I've been trying. It goes to voice mail. He does not return calls. I suspect the only time I'm going to see him is when I schedule an inspection through the main office.
Can the main office give you a guideline as to what stage the inspector wants to see?

If not I would just schedule an inspection and see where it goes.
drtbk4ever is offline   Reply With Quote
Old 02-13-2009, 04:09 PM   #14
Drywall contractor
 
Join Date: Jul 2008
Location: Lilburn, GA
Posts: 2,116
Rewards Points: 1,044
Default

What to leave open for inspection?


Again, it's based on where you live. In the various counties in the metro Atlanta, electric is generally inspected before insulation. Some counties after, but all before drywall.
__________________
If you can read this, thank a teacher. If you can read this in English, thank a soldier. Support our troops.
bjbatlanta is offline   Reply With Quote
Old 02-13-2009, 04:13 PM   #15
Newbie
 
Join Date: Feb 2009
Location: Knoxville, TN
Posts: 8
Rewards Points: 10
Default

What to leave open for inspection?


I was able to get hold of another inspector for the city(but still cannot get hold of the one I was assigned). He said since I'm doing an entire house, they are willing to come out multiple times to do rough-in and final of sections of the house, instead of the entire house at once(which would leave me with a house with no electric). I've already got one room insulated and mostly drywalled, except for the portions where electrical is. I'm not going to insulate any other rooms until I have him come out and do a rough-in, at which point I'll get more specifics of what he will allow me to do.

Thanks for your responses, guys.

Advertisement

forkvoid is offline   Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Open Stairs in Basement ngerhard Building & Construction 4 07-10-2009 07:30 PM
Which should open first GFCI or breaker jamiedolan Electrical 14 01-19-2009 04:03 PM
Stop a door from drifting open? Sliding Man Carpentry 17 11-16-2008 04:18 PM
closed cell vs open cell foam insulation amonalisa Building & Construction 1 11-06-2008 10:39 PM
garage door open light deck hand Electrical 3 01-22-2008 09:29 AM




Top of Page | View New Posts