Is this remodeling contract complete enough?


My wife and I have a 30 year old house with some early deterioration of a few of the wooden window frames. But the windows and storm windows seem to be working fine: no excessive heating and cooling bills, and noise transmission is very little. We have talked to various contractors, who have discussed with us several different levels of upgrade: all the way from minor retouch of a few windows to complete replacement of all the storm windows and frames. Currently we are favoring (feel free to try to change our minds) one contractor (Bill) who suggested the idea of "casing out" all of our current windows. He was recommended to us, and his discussion of the steps he would use makes us think he would do a good job. But since we really don't know what questions we should be asking, I thought it would be good to post most details of the contract here, to let anybody who has more experience at this give us their input. What should I be asking about that isn't mentioned below? Thanks!

He broke the proposal up into pieces, so we could choose only the first, or only the first two, or all three parts:

#1: Remove Existing Front Entry door and Storm door and haul away; install new smooth fiberglass entry door #607 as discussed with Keith at K&K, including hardware and lock-set. Deposit of $620 is required to place order. Total: $1460.

$2: Case out exterior wood trim on Front lower triple DH window unit and 4 DH windows on RT side of home. Remove existing storm windows and re-hang after sills cased all the way into interior sill. Total: $895.

#3: Case out 13 additional windows remaining on the rear, 1st and 2nd floors, L/S (Left side) 2nd floor and Front 2nd floor. Total: $1625.

PS: Replace bad wood as needed to properly nail case-out and charge time and material for extra work.


Last edited by babybowen; 05-14-2008 at 11:14 AM. Reason: Correction
babybowen is offline   Reply With Quote
Old 05-18-2008, 01:19 PM   #2
Member
 
Join Date: Mar 2008
Posts: 323
Default

Is this remodeling contract complete enough?


Make sure the contractor specifies the types of materials he will use -- can make a huge difference in quality.

Allison1888 is offline   Reply With Quote
Old 05-18-2008, 04:14 PM   #3
Newbie
 
Join Date: May 2008
Location: Camp Hill. PA
Posts: 12
Default

Is this remodeling contract complete enough?


Good point!
babybowen is offline   Reply With Quote
Old 05-18-2008, 06:50 PM   #4
Member
 
Join Date: Apr 2008
Posts: 78
Default

Is this remodeling contract complete enough?


ALWAYS have a completion date. After the completion date it should start costing the contractor money, at least $100 per day.
UFoPilot is offline   Reply With Quote
Old 05-24-2008, 03:23 PM   #5
Member
 
Jay123's Avatar
 
Join Date: May 2008
Location: North of Atlanta
Posts: 621
Default

Is this remodeling contract complete enough?


And if the contractor finishes before the completion date...you should pay him $100 for each day.

J
Jay123 is offline   Reply With Quote
Old 05-24-2008, 05:20 PM   #6
Member
 
Join Date: Dec 2007
Posts: 207
Default

Is this remodeling contract complete enough?


There is a potential big problem. He has left a Time and Materials (T&M) clause active, so you don't know if there will be a big or small up charge. Ask previous customers if he has a habit of working slow or having large extra dollars beyond his initial contract.

To be fair, T&M is probably the way I would approach this job, as we have no idea of how much or little bad wood will be there. Sometimes replacement is the only way to get fairly firm numbers on a job like this.
kgphoto is offline   Reply With Quote
Old 05-24-2008, 06:05 PM   #7
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Default

Is this remodeling contract complete enough?


Quote:
Originally Posted by UFoPilot View Post
ALWAYS have a completion date. After the completion date it should start costing the contractor money, at least $100 per day.
What about bad weather delays?
AtlanticWBConst. is offline   Reply With Quote
Old 05-24-2008, 07:26 PM   #8
Drywall and Painting Pro
 
Sir MixAlot's Avatar
 
Join Date: Apr 2008
Location: Melbourne Beach, Florida
Posts: 481
Blog Entries: 1
Default

Is this remodeling contract complete enough?


Quote:
Originally Posted by Jay123 View Post
And if the contractor finishes before the completion date...you should pay him $100 for each day.

J
I like the way you think J.
Sir MixAlot is offline   Reply With Quote
Old 05-24-2008, 07:28 PM   #9
Member
 
Jay123's Avatar
 
Join Date: May 2008
Location: North of Atlanta
Posts: 621
Default

Is this remodeling contract complete enough?


Fair...is...fair...no?


J
Jay123 is offline   Reply With Quote
Old 05-24-2008, 10:21 PM   #10
Electrical Contractor
 
jbfan's Avatar
 
Join Date: Jun 2004
Location: Newnan GA
Posts: 5,670
Default

Is this remodeling contract complete enough?


Quote:
Originally Posted by Jay123 View Post
Fair...is...fair...no?


J
Supossed to be!
__________________
Yes I am a Pirate, 200 years too late. "Jimmy Buffett"
jbfan is offline   Reply With Quote
Old 05-30-2008, 11:55 AM   #11
Newbie
 
Join Date: May 2008
Location: Camp Hill. PA
Posts: 12
Default

Is this remodeling contract complete enough?


Good point! Thanks!
babybowen is offline   Reply With Quote
Old 05-30-2008, 11:56 AM   #12
Newbie
 
Join Date: May 2008
Location: Camp Hill. PA
Posts: 12
Default

Is this remodeling contract complete enough?


Yes, I wondered about this. Good point. I will have to ask for more details on this part. Thanks!
babybowen is offline   Reply With Quote
Old 05-30-2008, 11:57 AM   #13
Newbie
 
Join Date: May 2008
Location: Camp Hill. PA
Posts: 12
Default

Is this remodeling contract complete enough?


Cute. Probably a good way to get things done fast, though!
babybowen is offline   Reply With Quote
Old 05-30-2008, 11:58 AM   #14
Newbie
 
Join Date: May 2008
Location: Camp Hill. PA
Posts: 12
Default

Is this remodeling contract complete enough?


Hmm. Not too much bad weather here in summer, but if he works in the fall, some provision for these would be fair. Thanks.
babybowen is offline   Reply With Quote
Old 05-30-2008, 01:05 PM   #15
Registered User
 
Termite's Avatar
 
Join Date: Apr 2008
Posts: 6,520
Default

Is this remodeling contract complete enough?


How about permits and inspections? Some cities require window/flashing inspections, some don't. Are you responsible for obtaining them or is he? I often see remodelers that won't correct code violations on their dime because they don't mention permitting in the contract. In some cities unpermitted work can lead to fines, and I hate seeing homeowners getting stuck eating them.

Termite is offline   Reply With Quote
Reply

Tags
contract details, door replacement, window capping


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Ethics? Contractor and Employer responsibilities boodog Off Topic 6 10-08-2007 09:07 AM
Seeking Advice On Building Contract RichardE General DIY Discussions 5 04-25-2007 01:19 AM
How much does laminate flooring expand or contract peter1 Flooring 5 03-27-2007 07:23 AM
my painter did not fallow the contract jaskoo Painting 17 11-19-2006 01:21 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.