Questions on tile work


I'm in the middle of tiling my newly gutted and rebuilt bathroom. I have the tile down on the floor and by the time i get home tonight it will be 30 hours since they were set. I also plan to tile the lower half of the walls, but a couple questions have come to mind.

1. Should I grout the floor before setting the wall tile, or should i grout them at the same time?
2. This is most likely opinion-based only. Should I line of the seams of the wall times with the floor tiles, or offset them by some amount? (note: using the same tile for wall as floor)
3. Why is it that what started as a plan to replace just the shower unit of the bathroom ended up with me tearing down to wall stubs, and fllor and ceiling joists for the entire bathroom and rebuilding it back from there?

Haff is offline   Reply With Quote
Old 12-07-2009, 04:39 PM   #2
Remodeling Contractor
 
Join Date: Dec 2008
Location: Sandy Hook, CT
Posts: 3,590
Default

Questions on tile work


1. Makes no difference. I would finish the wall then finish the floor.
2. if the floor is even slightly out of level and you try to line up the joints it will show. I would not line up the joints.
3. must have had too much fun with demo.

Bob Mariani is offline   Reply With Quote
Old 12-08-2009, 01:35 PM   #3
Newbie
 
Join Date: Sep 2009
Posts: 19
Default

Questions on tile work


Thanks.

Another question. Should I mud and/or prime the drywall (densarmor+) under where the wall tiles will be? Or just stick them right to the dryway?
Haff is offline   Reply With Quote
Old 12-08-2009, 03:46 PM   #4
Remodeling Contractor
 
Join Date: Dec 2008
Location: Sandy Hook, CT
Posts: 3,590
Default

Questions on tile work


no drywall behind the tile. Use 1/2" cement backer board. Cover the seams with alkali-resistant tape and thinset over them. Then cover everything with a waterproofing membrane like Redgard.
Bob Mariani is offline   Reply With Quote
Old 12-09-2009, 01:00 PM   #5
Newbie
 
Join Date: Sep 2009
Posts: 19
Default

Questions on tile work


This isnt in the shower, this is for the rest of the bathroom. I've read here and elsewhere, and also talked to the tile company i bought from that mounting tile with adhesive to densarmor+ is a good way to go for areas that are not directly made wet. The drywall is allready up, do you really think cement board is needed?
Haff is offline   Reply With Quote
Old 12-09-2009, 02:51 PM   #6
Remodeling Contractor
 
Join Date: Dec 2008
Location: Sandy Hook, CT
Posts: 3,590
Default

Questions on tile work


if not in a wet area, you are fine
Bob Mariani is offline   Reply With Quote
Old 12-09-2009, 03:00 PM   #7
Newbie
 
Join Date: Sep 2009
Posts: 19
Default

Questions on tile work


Thanks.

Which brings me back to the question..... should i mud and/or prime? or just stick right to the drywall?
Haff is offline   Reply With Quote
Old 12-10-2009, 06:38 PM   #8
Member
 
Join Date: Aug 2008
Location: coastal georgia
Posts: 371
Default

Questions on tile work


All my Densarmor was mudded and primed prior to tile install.
7echo is offline   Reply With Quote
Old 12-12-2009, 09:52 PM   #9
Tileguy
 
Bud Cline's Avatar
 
Join Date: Mar 2006
Posts: 9,716
Default

Questions on tile work


DensArmor DOES NOT REQUIRE any priming or sealing or painting or mudding or anything prior to installing tile. THAT IS WHAT IT IS FOR!
__________________
My nomination for DIY Chatroom Project of the Month is: http://www.diychatroom.com/f49/gulf-island-building-34958/
Bud Cline is offline   Reply With Quote
Old 12-16-2009, 02:50 PM   #10
Newbie
 
Join Date: Dec 2009
Posts: 6
Default

Questions on tile work


Even though it does not require any priming or sealing, if you want to feel safe, you should go ahead and apply some.
trendstone is offline   Reply With Quote
Old 12-16-2009, 03:31 PM   #11
Remodeling Contractor
 
Join Date: Dec 2008
Location: Sandy Hook, CT
Posts: 3,590
Default

Questions on tile work


you mud and prime this for the only purpose of a smooth finish when painting. What would the purpose be to skim coat it under a tile installation. Wouldn't the thinset do the same thing?
Bob Mariani is offline   Reply With Quote
Old 12-17-2009, 07:01 PM   #12
Tileguy
 
Bud Cline's Avatar
 
Join Date: Mar 2006
Posts: 9,716
Default

Questions on tile work


Sealers on substrates can be deal killers for tile jobs. No sealers are necessary, they are in fact discouraged. In this case there is no need anyway.

__________________
My nomination for DIY Chatroom Project of the Month is: http://www.diychatroom.com/f49/gulf-island-building-34958/
Bud Cline is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
handling unsafe work by an electrician wuxingming57 Electrical 1 11-14-2009 07:07 PM
Sealing Porcelain Tile Questions eis61374 Flooring 2 03-23-2009 07:11 PM
Ceramic tile over existing (full mud) ceramic? rjniles Flooring 7 12-24-2008 06:12 PM
Tile roof questions/repairs help please xoroniox Roofing/Siding 3 12-17-2006 02:02 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.