Only 1 inspection violation to correct-HELP!


First I'll say thanks to everyone who posts &/or responds here!
As the title says, I need to complete 1 issue in order to pass my County Concealment Inspection on a 4-year homeowner basement project.
I admit, I am soooo confused over this last issue!!!
Any & all responses appreciated in advance; Here Goes:

Basement slab, fiberglass neoangle shower receptor already set in place & drain connected (had plumber help me). I "framed-in" a shower seat 3' wide X 18" deep, all press. treated studs, added 3/4 ply for 1st layer of seat top. Then applied Hardi-Backer on top of 3/4 ply & secured in place properly. Then installed DuRock on ALL walls that will be inside of the entire perimeter of shower&seat bump out, leaving a slight opening 5" up from seat top @ the 2 inside framed corners. (This I did from a great suggestion I found on-line which then allows for a place to perform an "ouside fold & tack" of the proposed PVC shower liner @ these 2 inside corners.)
The missing PVC shower liner is the only violation that I was issued from the my local inspection division.

So my dilemma is this: When I secure the PVC shower liner membrane on top of the cement board using the ASTM approved PVC shower liner glue that I purchased what do I do @ the vertical face of the shower seat. I was already informed by my County Inspector that the PVC membrane should continue from the seat all the way to approximately 1/2" over the top lip of the fiberglass shower receptor.
So my question is regarding the front vertical face of the framed shower seat.
Do I install the PVC membrane behind the vertical front cement board allowing it to petrude just under the cement board's bottom which would end just above the fiberglass receptor lip. (If I do it this way how do I properly secure the cement board to the front vertical surface??)
--OR--
Do I install the cement board securely to the front vertical framing and then glue the PVC membrane to the cement board with the membrane ending the required 1/2" below the end of the cement board. (If I do it this way, how do the tiles stick to it??)
(Any advice from a professional tiler would be also be helpful to this weary DIY'er.)
THANKS (P.S. Also, please nobody try to tell me @ this point to do away with the framework & build a CMU style.)
By the way, there is a sump pump "directly behind" this shower seat in an open unfinished area to remain.


Last edited by DragonInspector; 04-08-2009 at 06:01 PM.
DragonInspector is offline   Reply With Quote
Old 04-08-2009, 11:15 PM   #2
Member
 
Join Date: Feb 2009
Location: Seattle, Washington
Posts: 344
Rewards Points: 0
Default

Only 1 inspection violation to correct-HELP!


A picture sure would help. The liner must be under the cbu.


Last edited by Mop in Hand; 04-08-2009 at 11:18 PM.
Mop in Hand is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
what to do for plumbing rough inspection? red86yota Plumbing 5 09-12-2010 04:39 PM
Home Inspectors / Non Disclosed Issues PreSale AndrewF Off Topic 14 02-06-2009 10:18 PM
How do I pick the correct coaxial cable? fwmcbigfoot Home Theater 1 12-30-2008 09:45 AM
State Vehicle Inspection - ARGGH Leah Frances Off Topic 14 04-05-2008 12:59 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.