How many man-hours for drywall/tapping?


Could anyone give me a ballpart figure on how long it will take to hang drywall on a approx 1000 sq ft. area and how long to tape in terms of man hours...

Just want to have an idea in order to let my Boss know when I will finish my drywall/tapping in the basement...

KUIPORNG is offline   Reply With Quote
Old 12-12-2006, 08:48 AM   #2
Oldguy
 
Rehabber's Avatar
 
Join Date: Dec 2005
Location: Calif (the left coast)
Posts: 498
Default

How many man-hours for drywall/tapping?


It depends on how many openings, how many joints, are you doing walls and ceiling? What is your your skill level?

__________________
If you think you can, or if you think you can't, you're probably right.

ASE certified master auto tech, Retired.
Rehabber is offline   Reply With Quote
Old 12-12-2006, 09:32 AM   #3
Member
 
Join Date: Jan 2006
Location: Toronto, Canada
Posts: 1,861
Default

How many man-hours for drywall/tapping?


just consider it a lot of openings and joints.... just consider how long it will take for a professional to do... I will multiple a factor against it to adjust to my skill level...
KUIPORNG is offline   Reply With Quote
Old 12-12-2006, 09:45 AM   #4
Member
 
yummy mummy's Avatar
 
Join Date: Sep 2006
Location: Canada
Posts: 1,725
Default

How many man-hours for drywall/tapping?


Is the BOSS, your wife?
yummy mummy is offline   Reply With Quote
Old 12-12-2006, 09:46 AM   #5
Member
 
Join Date: Jan 2006
Location: Toronto, Canada
Posts: 1,861
Default

How many man-hours for drywall/tapping?


Of course...
KUIPORNG is offline   Reply With Quote
Old 12-12-2006, 09:54 AM   #6
Member
 
yummy mummy's Avatar
 
Join Date: Sep 2006
Location: Canada
Posts: 1,725
Default

How many man-hours for drywall/tapping?


As she should be.
yummy mummy is offline   Reply With Quote
Old 12-12-2006, 11:53 AM   #7
Lic. Builder/GC/Remodeler
 
AtlanticWBConst.'s Avatar
 
Join Date: May 2006
Location: New England
Posts: 7,556
Default

How many man-hours for drywall/tapping?


Quote:
Originally Posted by KUI****G View Post
Could anyone give me a ballpart figure on how long it will take to hang drywall on a approx 1000 sq ft. area and how long to tape in terms of man hours...

Just want to have an idea in order to let my Boss know when I will finish my drywall/tapping in the basement...

By my figures: 1000 SF of sheetrock is about 21 twelve foot sheets.

That is not much work.

Two professional hangers could hang that in 1/2 day easily, assuming some soffits and multiple corners. (example, we once had a crew of 5 guys hang a basement of 50 sheets in 2 and 1/2 hours)
Then, corner bead and tape it with 3 coats by the end of the first day..... (9-10 hour day using quick dry durabond for the 1st and 2nd coats)
...Then to come back another day to sand (after drying), 'touch up' the work and then clean up.

So: one long day and one 2-3 hour day to sand - (that is again for 2 professional drywallers)

Home owner to do the same job: several days to hang it.
DIY taping: up to 1 week to tape and finish coat, lots of sanding and also all the clean up.

(Really, I have seen this take that amount of time by DIYers)
AtlanticWBConst. is offline   Reply With Quote
Old 12-12-2006, 02:14 PM   #8
Member
 
Join Date: Jan 2006
Location: Toronto, Canada
Posts: 1,861
Default

How many man-hours for drywall/tapping?


This is fast ...

I give up my idea of going to work as a GC after hearing that...
KUIPORNG is offline   Reply With Quote
Old 12-12-2006, 02:52 PM   #9
DIY'er
 
Join Date: Sep 2006
Location: Glastonbury, CT
Posts: 206
Default

How many man-hours for drywall/tapping?


In support of Atlantic's statement...
I have several DIY "projects" worth of experience drywalling and it took me about 2 weeks of solid work to hang, tape and finish about 450 square ft. in my basement. For the ceiling I had a 1 helper one day and a second helper for a couple hours the second day...I think I did four passes on the joints and in some areas, namely the couple of butt joints, I had to do five to get it to look good. I rented a porter and cable sander to attach to my shop vac and that was definetly worth the money. Especially for the ceiling sanding...Have to be careful if you do rent one, as they can get away from you...
If I had used the setting type joint compound for all the passes could have finished sooner but I felt I needed a break anyway so for the last couple passes I used premix. I had to wait for it to fully cure...but at that point, like I said, I welcomed the break.
Hope that helps...
__________________
Doug Russell

"What if the hokey pokey really IS what its all about."
dougrus is offline   Reply With Quote
Old 12-12-2006, 03:06 PM   #10
Member
 
Join Date: Jan 2006
Location: Toronto, Canada
Posts: 1,861
Default

How many man-hours for drywall/tapping?


My cousin who currently live with me for a little while said it will take me one more year to finish the basement as he saw my progress, I will try to prove to him otherwise... I do have a full time job... but my children and wife is not around... so I will work faster... from what Dougrus said, it takes approx 5 man weeks to finish 1000 sq. ft... that is approx 200 man hours with my skill level discount... it probably means it should be about done by the time she is back to Canada in March... then it is tiling... doors... painting... well summar target seems to be reasonable...

KUIPORNG is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
2 hours one hardwood step KUIPORNG Flooring 7 04-25-2007 02:31 PM
24 hours curing time enought? KUIPORNG Flooring 4 02-28-2007 08:23 AM
Why no water hours after friend pulled our pump? sheriffherself Plumbing 4 11-19-2006 07:10 AM
Ok to wait 74 hours between coats? J187 Painting 5 06-23-2006 04:37 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.