subfloor gone bad

My living room has some cracks where it shows the problem of the subfloor. As shown in the pics, where the subfloor planks meet, there is unevenness and it has caused the vinyl tile to peel off. I believe it is the support of the subfloor that has gone bad.

My question is if there is any easy solution to make the floor even again? Or, do I have to totally take off the subfloor and redo it? Hopefully not....
Attached Thumbnails
subfloor gone bad-pc210809.jpg   subfloor gone bad-pc210810.jpg  


hohadcr is offline   Reply With Quote
Old 01-06-2010, 06:16 AM   #2
Join Date: Dec 2008
Location: Wilmington, DE
Posts: 3,118
Rewards Points: 2,000

Probably noting wrong with the subfloor, other than maybe needing to be screwed down tightly. You have asphalt or vinyl tiles over a plywood joint. Over time, that joint expands/contracts, but the tile does not, hence the crack. You need to scrape up the old tile and start over, but not with the subfloor, IMHO.


Just Bill is offline   Reply With Quote
Old 01-06-2010, 08:10 AM   #3
hohadcr's Avatar
Join Date: Jul 2009
Location: Canada
Posts: 297
Rewards Points: 306

it doesn't show well in the pics, but i can see where the plywood meets, the two ends are not on the same level. Do I just screw the higher one down? When I stepped on them, both seemed solid.
hohadcr is offline   Reply With Quote
Old 01-06-2010, 03:06 PM   #4
CrossWorks's Avatar
Join Date: Apr 2008
Location: Maine
Posts: 163
Rewards Points: 150

There may be a few reasons why this happened. What comes to mind at this point is the following:

>The floor joist edge is probably "wayned"...a.k.a has a bad edge. Meaning the edge of the floor joist was not a complete 1-1/2" as it should be, because of low grading of lumber from the mill. And so because of this. when the subfloor was being installed, the plywood obviously did meet evenly. This should only be in a 4 foot section.

> Or...when they were putting the sub-floor down with glue, they never completed the entire process before sunset, and so at that point, went home (Glue dried overnight) then the next day finished putting the rest of the plywood down (on dried glue at that connection) and moved on.

Option 1:My suggestion since that tile looks like it can be easily found and replaced is this: Move the washer and dryer out of the way, remove one row of tile on the "high side" (tile directly over joint) going at least one tile width beyond the 4' marks. Then remove two rows of tile on lower side. Add screws to the high side edge of plywood and get floor leveler and trowel that at the joint and taper it away from where the machines sit (ie...onto the lower plywood) With 2 rows of tile removed on the lower side, that should leave plenty of room to taper the leveling compound.

To be frank with you, that should of never been installed directly on the sub-floor. Proper installation would be to have at least a 1/4" AC fir plywood down on the existing subfloor. Because any installer putting that down prior to putting the tile down "WOULD" of used leveler before tile installation. That's why I believe this tile was initially installed directly on the 3/4" sub-floor.

Option 2:To do it right: rip all the tile out, put down 1/4" ac plywood, use leveler at all joints and "then" tile.

Obviously option 1 is your quick/least expensive fix. Looks like you'll be replacing 15 pieces of tile in the end.

Good Luck
A great personality will open many doors in life,
but it's your character that keeps them open!
"Where Every Nail Has a Purpose!"

Last edited by CrossWorks; 01-06-2010 at 03:09 PM.
CrossWorks is offline   Reply With Quote
Old 01-06-2010, 07:23 PM   #5
Join Date: Mar 2007
Location: Long Island, NY
Posts: 11,188
Rewards Points: 5,336

You have a few problems with the vinyl tile installation. Starting with the subfloor. It's not the substrate you would put the tile onto. As stated before, you would put down a 1/4" AC or luan ply. You would fill in all the screw holes and fill the seams so the surface was very smooth and level. If you need to rescrew the present subfloor or sand the high spots, make sure the base is tight and level. This makes putting the second layer on an easier task. Prep work will give you the outcome you want. Skimp on that and you'll be doing the floor every 3-4 years.
Ron6519 is offline   Reply With Quote

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off

Top of Page | View New Posts


Search Engine Friendly URLs by vBSEO 3.6.1