Joist Bracing/Blocking Q's


is bracing required between ALL joists? I currently have 2x4 cross bracing midspan, and blocking where 2 joist members meet on a girder (2 joists make up the full with of the house, where the girdir is in the middle). There will be a large duct running the entire width of house through on joist bay, so there will not be room for blocking or bracing.

if running pipes/wiring, are the rules for bores and notches in blocking the same as for joists?

[not a bracing/blocking q] are rules for bores and notches in top/sill plates same as for studs?

batt insulation is not suppose to be compressed. So when installing against cross bracing, the bracing will create a gap in insulation. The other option is to push the insulation tight against the blocking to close the gap, but then of course you'd be compressing a triangle shaped portion of the insulation. Which is the better option? I see my current insulation is installed very loosely and there is a huge gap where the bracing is. Doesn't seem quite right to me.

acerunner is offline   Reply With Quote
Old 09-15-2010, 01:07 PM   #2
Member
 
Join Date: Jul 2010
Location: Ontario Canada, Toronto to be exact.
Posts: 1,373
Rewards Points: 500
Default

Joist Bracing/Blocking Q's


Cross bridging is often specified on plans if joist span is over 8'. It gets nailed on top, the subfloor is installed, and then the bottom gets secured.

epson is offline   Reply With Quote
Old 09-15-2010, 01:57 PM   #3
Member
 
Join Date: Dec 2009
Location: San Francisco
Posts: 445
Rewards Points: 250
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by epson View Post
Cross bridging is often specified on plans if joist span is over 8'. It gets nailed on top, the subfloor is installed, and then the bottom gets secured.
you're thinking the metal bracing like this which would be difficult to work around:


what I have is the 2x4 bracing nailed to the side of the joists like this:


there are already a few that must have been knocked out by an electrician to run wires and were never replaced. I will be replacing those. But my remodel includes running a large duct through a joist bay that would be too large to use bracing. So my question is would that be ok? Maybe I can use strapping instead?

acerunner is offline   Reply With Quote
Old 09-15-2010, 02:37 PM   #4
Newbie
 
Join Date: Jun 2010
Posts: 20
Rewards Points: 10
Default

Joist Bracing/Blocking Q's


Has anyone tried the IBS2000 bracing systems yet?
behrend is offline   Reply With Quote
Old 09-15-2010, 04:22 PM   #5
Registered User
 
Join Date: Mar 2009
Posts: 9,968
Rewards Points: 2,000
Default

Joist Bracing/Blocking Q's


From your State Code:
Prevent rotation (blocking or hangers at ends) ________________________ 2308.8.2
Blocking at intermediate supports __________________________________ 2308.8.2
Joists >2X12 blocked or bridged max 8ft O.C. ________________________ 2308.8.5
No notches middle 1/3 of span ____________________________________ 2308.8.2
Bored holes min 2in from top or bottom or other notch or hole ____________ 2308.8.2
http://docs.google.com/viewer?a=v&q=...h1W5lElSFXE4_w

Notches and holes, Page 2: http://arch.umd.edu/Tech/Structural_..._Guide_A11.pdf

You don’t want a gap. Better to compress some of it with the rest meeting. No gap under floor: http://oikos.com/esb/38/floorinsulation.html

Gap metal or wood cross-bridging or it will squeek……

Gary
__________________
If any ads are present in my answer above, I do not condone/support/use the product or services listed, they are there against my permission.
Gary in WA is offline   Reply With Quote
Old 09-15-2010, 05:51 PM   #6
Member
 
Join Date: Dec 2009
Location: San Francisco
Posts: 445
Rewards Points: 250
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by GBR in WA View Post
From your State Code:
Prevent rotation (blocking or hangers at ends) ________________________ 2308.8.2
Blocking at intermediate supports __________________________________ 2308.8.2
Joists >2X12 blocked or bridged max 8ft O.C. ________________________ 2308.8.5
No notches middle 1/3 of span ____________________________________ 2308.8.2
Bored holes min 2in from top or bottom or other notch or hole ____________ 2308.8.2
http://docs.google.com/viewer?a=v&q=...h1W5lElSFXE4_w

Notches and holes, Page 2: http://arch.umd.edu/Tech/Structural_..._Guide_A11.pdf

You don’t want a gap. Better to compress some of it with the rest meeting. No gap under floor: http://oikos.com/esb/38/floorinsulation.html

Gap metal or wood cross-bridging or it will squeek……

Gary
thanks.

so is that a no to running ducts in the joist space since bracing is required? This is what was suggested by HVAC sub. He wanted to run cold air return in joist space, or more accurately, use joist space as cold air return plenum and line it with sheet metal.So unless I can install bracing inside the sheet metal?

I understand notch/bore restrictions in joists and studs, but my question is if bores and notches in blocking & top/sill plates fall into these restrictions or if there are separate restrictions.
acerunner is offline   Reply With Quote
Old 09-16-2010, 08:18 AM   #7
Member
 
Join Date: Jul 2010
Location: Ontario Canada, Toronto to be exact.
Posts: 1,373
Rewards Points: 500
Default

Joist Bracing/Blocking Q's


Actually acerunner I was talking about your second picture.
epson is offline   Reply With Quote
Old 09-16-2010, 10:20 AM   #8
Member
 
Join Date: Dec 2009
Location: San Francisco
Posts: 445
Rewards Points: 250
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by epson View Post
Actually acerunner I was talking about your second picture.
ok. when you said nailed to the top, I thought you meant top edge of the joist, where it will be sandwiched between joist and subfloor, which must be the metal type.
acerunner is offline   Reply With Quote
Old 09-16-2010, 10:22 AM   #9
Member
 
Join Date: Jul 2010
Location: Ontario Canada, Toronto to be exact.
Posts: 1,373
Rewards Points: 500
Default

Joist Bracing/Blocking Q's


No problem
epson is offline   Reply With Quote
Old 09-16-2010, 11:35 AM   #10
Registered User
 
Join Date: Mar 2009
Posts: 9,968
Rewards Points: 2,000
Default

Joist Bracing/Blocking Q's


"so is that a no to running ducts in the joist space since bracing is required?" ------- Yes, I have seen the block removed and used for HVAC, many, many times. As long as it passes inspection.

"So unless I can install bracing inside the sheet metal?"----- No, that would cause air turbulence.

"I understand notch/bore restrictions in joists and studs, but my question is if bores and notches in blocking & top/sill plates fall into these restrictions or if there are separate restrictions." ------ No restrictions. Some science: http://books.google.com/books?id=DWs...olumns&f=false

Top plates: pp.15: http://www.awc.org/helpoutreach/ecou...seV09-2007.pdf

Gary
__________________
If any ads are present in my answer above, I do not condone/support/use the product or services listed, they are there against my permission.

Last edited by Gary in WA; 09-16-2010 at 03:50 PM.
Gary in WA is offline   Reply With Quote
Old 09-17-2010, 08:41 AM   #11
Member
 
Join Date: Jul 2010
Location: Ontario Canada, Toronto to be exact.
Posts: 1,373
Rewards Points: 500
Default

Joist Bracing/Blocking Q's


What we have done and supplied in the past was use a 3’’ x 2’ x 1/4’’ thick plate with 6 holes either side to except ½’’ lag bolts and we had no issues as per your reference to page 15.
epson is offline   Reply With Quote
Old 09-17-2010, 09:50 AM   #12
Member
 
Join Date: Dec 2009
Location: San Francisco
Posts: 445
Rewards Points: 250
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by epson View Post
What we have done and supplied in the past was use a 3’’ x 2’ x 1/4’’ thick plate with 6 holes either side to except ½’’ lag bolts and we had no issues as per your reference to page 15.
1/4" is awfully thick. How do you install wall coverings in that area?
acerunner is offline   Reply With Quote
Old 09-17-2010, 09:52 AM   #13
Member
 
Join Date: Jul 2010
Location: Ontario Canada, Toronto to be exact.
Posts: 1,373
Rewards Points: 500
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by acerunner View Post
1/4" is awfully thick. How do you install wall coverings in that area?
By using furring strips
epson is offline   Reply With Quote
Old 09-17-2010, 04:04 PM   #14
Member
 
Join Date: Dec 2009
Location: San Francisco
Posts: 445
Rewards Points: 250
Default

Joist Bracing/Blocking Q's


Quote:
Originally Posted by GBR in WA View Post
on page 21 of that doc. "And when wider studs are used it's important that they rest completely on a plate. The code requires for the plate to be at least as wide as the studs."

I have a few walls that are furred out around footings as shown in drawing below. Would that be a violation?
Attached Images
 
acerunner is offline   Reply With Quote
Old 09-17-2010, 06:01 PM   #15
Registered User
 
Join Date: Mar 2009
Posts: 9,968
Rewards Points: 2,000
Default

Joist Bracing/Blocking Q's


Are the walls bearing or just to add insulation behind and hide the concrete footing? How wide is the bottom plate?

Gary

__________________
If any ads are present in my answer above, I do not condone/support/use the product or services listed, they are there against my permission.
Gary in WA is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Supporting joist under cracked tile JT31 Building & Construction 2 08-26-2010 08:00 AM
Jacking and Sistering Floor Joist Captain.Sassy Building & Construction 17 08-11-2010 01:30 PM
Space between joist and beam on deck schveiguy Building & Construction 11 09-08-2009 09:15 AM
one rotted deck joist to replace, need advice dougq Building & Construction 10 07-07-2009 02:18 PM
replacing rotted sill plate and rim joist behind a deck ledger board tommyt Building & Construction 2 08-11-2008 07:38 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.