QUESTION: I'm pouring a concrete step that requires five 60-pound bags of premixed concrete. Is it okay to mix and pour one bag at a time? It takes me about five minutes to mix each bag. I'm pretty sure it doesn't matter from a structural perspective, but I do worry that it might make a difference in how nice a result I get when I trowel the face of the step smooth.

Thanks for your help!

*******************************

BACKGROUND FOR THOSE WHO WANT IT:

I'm adding a concrete step atop an existing concrete landing and I've read plenty of advice on the process of making forms, pouring, troweling, and edging the steps, and removing the face board on the risers in order to trowel the step faces.

czissman is offline   Reply With Quote
Old 03-08-2012, 11:13 AM   #2
Civil Engineer
 
Join Date: Mar 2009
Location: Boston
Posts: 4,170
Default

OK to to mix and pour one bag at a time for a concrete step?


Unless you place concrete in extreme heat, it is not going to start setting up for at least half an hour, so you are fine placing one bag at a time. Just make sure you prepare the mix according the recipe on the bag, do not use too much water.

Daniel Holzman is offline   Reply With Quote
Old 03-08-2012, 02:04 PM   #3
Member
 
Join Date: Jul 2008
Location: NW of D.C.
Posts: 5,990
Default

OK to to mix and pour one bag at a time for a concrete step?


And thoroughly rinse the container between batches. The steps may take a month to reach full compressive strength.
Yoyizit is offline   Reply With Quote
Old 03-08-2012, 02:39 PM   #4
Member
 
Join Date: Apr 2011
Posts: 30
Default

OK to to mix and pour one bag at a time for a concrete step?


Thanks for your replies & tips! That puts one of two worries to rest.
czissman is offline   Reply With Quote
Old 03-08-2012, 02:58 PM   #5
Member
 
joed's Avatar
 
Join Date: Mar 2005
Location: Welland, Ontario
Posts: 7,454
Default

OK to to mix and pour one bag at a time for a concrete step?


I never rinse my container/wheelbarrow between batches. Clean up when you are done.
__________________
Do not PM with questions that can be asked in a forum. I will not respond.
joed is offline   Reply With Quote
Old 03-08-2012, 04:25 PM   #6
Member
 
Join Date: Jul 2008
Location: NW of D.C.
Posts: 5,990
Default

OK to to mix and pour one bag at a time for a concrete step?


Quote:
Originally Posted by joed View Post
I never rinse my container/wheelbarrow between batches. Clean up when you are done.
Doesn't it cause the new batch to set up too fast?
Yoyizit is offline   Reply With Quote
Old 03-08-2012, 07:00 PM   #7
Member
 
joed's Avatar
 
Join Date: Mar 2005
Location: Welland, Ontario
Posts: 7,454
Default

OK to to mix and pour one bag at a time for a concrete step?


Don't wait that long. Dump it start a new batch. Old batch has no effect on new batch. I don't mix a lot in a wheelbarrow. I normally use a mixer and would waste too much water and time to clean out after every load. It would also make a big mess of the work area with all that water.

__________________
Do not PM with questions that can be asked in a forum. I will not respond.
joed is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off





Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.