24 x 24 x12 Footer


Do support a sagging beam in my basement, I am required to pour 2 -24 x 24 x 12 inch square footers. I have done the laborious work and have dug them out.

I need to schedule the BI to come out and look at them before pouring so I have a few questions:

Currently I just have a square cutout with dirt sides and a dirt floor, even though it is in the correct dimensions. I am unfamiliar with concrete work and would like advice on how to set up a "form". Also, the current slab I have poured in my basement is a bit unlevel. The new footer has to be perfectly level, so how could I achieve this?

I looked online and was having some difficultly finding information on this other than people asking for what size they needed, which I already have from the SE.

Thanks in advance.

Tom

__________________
Thomas


South Jersey - Camden County
tjbingha is offline   Reply With Quote
Old 01-10-2013, 01:08 PM   #2
"You can do anything"-Mom
 
brockmiera's Avatar
 
Join Date: Oct 2012
Location: Littleton, CO
Posts: 724
Default

24 x 24 x12 Footer


IF your slab is level and your footer has to be perfectly level then you need to extend the height of your footer above the height of the floor. to do this you will need to make forms. If you dont need to extend it past the top of the concrete then earth forming a footer should be find assuming you have the proper compaction. That is a question for your inspector though.

How far out of level are you? I'm not sure what your tolerances are but in most places you can use non shrink grout under a base plate to level up to 1/4". Or a lot of structural systems you can use a leveling plate. I think that you will find that very few footers are perfectly level.

brockmiera is offline   Reply With Quote
Old 01-10-2013, 01:22 PM   #3
Member
 
Join Date: Jun 2009
Location: hilton head & atlanta
Posts: 2,998
Default

24 x 24 x12 Footer


tommy, just nail some 1x4's together to form a box 24" x 24",,, put those into the holes for a snug fit - place a level on top of the forms & tap til the little bubble's in the ctr of the marks on the level's sight glass - that will achieve your goal of having these new footers perfectly level

i'm sure the information's someplace on the i-net but most people own & know how to use levels by the time they own a home no steel in your footers ?down here we use 2 mats of # 4 bar - ea mat at 90* to the other & 1/3rd & 2/3rds vertical evenly spaced horizontally
__________________

if you hear it from a guy in the apron store, be VERY suspicious the mtl/method will work,,, when it time to build something together, they won't answer phones NOR help
itsreallyconc is offline   Reply With Quote
Old 01-10-2013, 01:46 PM   #4
"You can do anything"-Mom
 
brockmiera's Avatar
 
Join Date: Oct 2012
Location: Littleton, CO
Posts: 724
Default

24 x 24 x12 Footer


Quote:
Originally Posted by itsreallyconc View Post
tommy, just nail some 1x4's together to form a box 24" x 24",,, put those into the holes for a snug fit - place a level on top of the forms & tap til the little bubble's in the ctr of the marks on the level's sight glass - that will achieve your goal of having these new footers perfectly level

i'm sure the information's someplace on the i-net but most people own & know how to use levels by the time they own a home no steel in your footers ?down here we use 2 mats of # 4 bar - ea mat at 90* to the other & 1/3rd & 2/3rds vertical evenly spaced horizontally
Make sure your building inspector and engineer of record are ok with you having a 22.5" x 22.5" footer for the first 3.5".
brockmiera is offline   Reply With Quote
Old 01-10-2013, 01:59 PM   #5
Member
 
Join Date: Jun 2009
Location: hilton head & atlanta
Posts: 2,998
Default

24 x 24 x12 Footer


my error,,, dimensions posted are INSIDE the box good catch, brock thanks !
__________________

if you hear it from a guy in the apron store, be VERY suspicious the mtl/method will work,,, when it time to build something together, they won't answer phones NOR help
itsreallyconc is offline   Reply With Quote
Old 01-10-2013, 02:33 PM   #6
Member
 
Join Date: Nov 2012
Location: Camden County, NJ
Posts: 121
Default

24 x 24 x12 Footer


The engineers specs did not call for any steel actually. I will double check but I did not see it. When pulling the permit they did not question it either.

Although these questions may seem elementary, I appreciate you guys answering them. Again, I have very very little experience with concrete but am attempting to use this as an opportunity to gain some.

The other question I have is when I remove the forms, I will have a 1x space that has no concrete. I would have had to cut through the slab to get my forms in place if I am understanding you correctly. What is to be done with this area?

Also, it is an unfinished basement and always will be. Am I able to put in a raised footer? As I mentioned earlier my slab is unlevel (sagging in the middle due to no footer under center pier). What is the proper way to do this? One part will have to be either under or over the current slab "line".

Thanks,

Tom
__________________
Thomas


South Jersey - Camden County
tjbingha is offline   Reply With Quote
Old 01-10-2013, 02:49 PM   #7
Member
 
Join Date: Jun 2009
Location: hilton head & atlanta
Posts: 2,998
Default

24 x 24 x12 Footer


experience is doing something correctly while ' lessons ' are gain'd from f'ing up being from camden is no excuse after removing the forms, fill that space w/mortar,,, i'd think you could have a raised footer,,, by "line" you mean elevation ( height of finished top ) of the 2 ? ? ?
__________________

if you hear it from a guy in the apron store, be VERY suspicious the mtl/method will work,,, when it time to build something together, they won't answer phones NOR help
itsreallyconc is offline   Reply With Quote
The Following User Says Thank You to itsreallyconc For This Useful Post:
tjbingha (01-10-2013)
Old 01-10-2013, 02:59 PM   #8
Member
 
Join Date: Nov 2012
Location: Camden County, NJ
Posts: 121
Default

24 x 24 x12 Footer


Already have had too many lessons in this house, don't need another one (see my project thread, haha).

Also, Camden County is a big county. If I was from Camden, do you think you would still be alive after a comment like that? I mean, I know you are from the ATL but still...

Thanks and I will let you know how it goes...and so I am clear by "mortar" you are referring to the cement mix that I am using or a totally different animal?
__________________
Thomas


South Jersey - Camden County
tjbingha is offline   Reply With Quote
Old 01-10-2013, 03:12 PM   #9
Member
 
Join Date: Jun 2009
Location: hilton head & atlanta
Posts: 2,998
Default

24 x 24 x12 Footer


wuz in nj for 8yrs - otherwise i wouldn't have learnt to wear unlaced work boots i'd use leftover conc mix & strain out some rock ( small crushed stone ) IF it were my bsmt,,, some of the pther ' purists ' may disagree but they don't know my bride, nagzilla
__________________

if you hear it from a guy in the apron store, be VERY suspicious the mtl/method will work,,, when it time to build something together, they won't answer phones NOR help
itsreallyconc is offline   Reply With Quote
Old 01-10-2013, 04:00 PM   #10
Member
 
GBrackins's Avatar
 
Join Date: Apr 2012
Location: Fairhaven, Massachusetts
Posts: 2,800
Default

24 x 24 x12 Footer


if I understand your post correctly you are required to install 24" wide x24" long x12" deep footings to provide proper bearing for a column to support the beam, is this correct? if you have a dirt floor in the basement and not a concrete slab I'd just dig a square hole that is 24" x 24" to a depth of 12" and place the concrete in the hole up to the top of the hole. no form work needed.

I'd probably use 2-#5 rebars in each direction in the bottom of the hole (3" up from the dirt bottom) put a brick under the bars. won't hurt.

Should you desire to place a concrete floor in the basement in the future you would not have the footing in the way.

Just my humble thoughts, many ways to accomplish the same goal. Good luck!
__________________
Gary

"You get what you pay for, and sometimes free costs more!"
GBrackins is offline   Reply With Quote
Old 01-10-2013, 04:07 PM   #11
Member
 
Join Date: Nov 2012
Location: Camden County, NJ
Posts: 121
Default

24 x 24 x12 Footer


GBrack - I have a concrete slab. 2 inches thick, unlevel. But yes, your understanding of the issue is correct.

Thanks,

Tom
__________________
Thomas


South Jersey - Camden County
tjbingha is offline   Reply With Quote
Old 01-10-2013, 05:08 PM   #12
Member
 
GBrackins's Avatar
 
Join Date: Apr 2012
Location: Fairhaven, Massachusetts
Posts: 2,800
Default

24 x 24 x12 Footer


cut out the slab to size and then dig 12" below the bottom of the concrete slab, still no form work. place concrete for footing up to bottom of slab. once column is installed use grout to fill in the area of the slab you cut out, this will lock in the base of the column.
__________________
Gary

"You get what you pay for, and sometimes free costs more!"
GBrackins is offline   Reply With Quote
Old 01-10-2013, 08:07 PM   #13
Member
 
Join Date: Nov 2007
Location: Nashua, NH, USA
Posts: 6,838
Default

24 x 24 x12 Footer


It would be better to dig the hole deep enough so the entirety of the 12 inch high footer is even with and/or below the main slab. This way you or the next person to own the house won't have the footer sticking up when trying to finish the basement floor.

Additional concrete and mortar can be added at a later date to cover the footing and level things out.
__________________
Stop wasting time re-adjusting the pattern. Have several lawn sprinklers, one for each pattern.
AllanJ is offline   Reply With Quote
Old 01-12-2013, 08:54 AM   #14
Concrete & Masonry
 
Join Date: Nov 2008
Location: Wisconsin
Posts: 2,679
Default

24 x 24 x12 Footer


The last tow posts are exactly how we do it here, but we also use adjustable columns, and it's important to support the "heft" of the column with concrete to take load off of the screw jack...........
jomama45 is offline   Reply With Quote
Old 01-12-2013, 09:25 AM   #15
Member
 
Join Date: Jun 2009
Location: hilton head & atlanta
Posts: 2,998
Default

24 x 24 x12 Footer


jo, we also use adjustables but i'd always thought the main reason for conc filling the steel columns was fire resistance as steel bends & collapses when exposed to hi heat,,, conc allows the steel to resist more the hot effects... isn't the main support still the screw on top of the column ?

__________________

if you hear it from a guy in the apron store, be VERY suspicious the mtl/method will work,,, when it time to build something together, they won't answer phones NOR help
itsreallyconc is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Short Retaining Wall - Footer jkim8520 Landscaping & Lawn Care 3 06-03-2011 10:27 AM
Brick footer brknardo Building & Construction 0 09-18-2010 06:37 AM
How far from egress should I place a footer LarryV Building & Construction 7 08-27-2009 08:49 PM
Footer deere2440 Building & Construction 7 03-01-2008 08:54 PM
Undercut footer billinak Building & Construction 3 03-18-2005 06:34 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.