How long to drywall 2900 sq ft?


Getting ready to drywall the basement, a buddy thinks it will take two weeks to get it done, hanging, taping, sanding...

this is ceiling and wall space

does this sound reasonable? how long would a pro crew take to do something like this usually? Just wondering for comparision
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 12-06-2012, 02:47 PM   #2
Member
 
Join Date: Nov 2011
Location: Hartfield VA
Posts: 24,483
Default

How long to drywall 2900 sq ft?


Crews I've work with could do it in about 4 days and it would be paint ready.
joecaption is online now   Reply With Quote
Old 12-06-2012, 02:52 PM   #3
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,273
Default

How long to drywall 2900 sq ft?


Quote:
Originally Posted by joecaption View Post
Crews I've work with could do it in about 4 days and it would be paint ready.
so two weeks for two people with an ok amount of experience (did about 400 sq ft before on my own but took my time) doing about 110 sheets doesn't sound too far off?
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 12-06-2012, 06:39 PM   #4
retired union carpenter
 
Join Date: Nov 2011
Location: PA
Posts: 323
Send a message via Yahoo to coupe
Default

How long to drywall 2900 sq ft?


2900 square feet,ceiling and wall space. if my math is correct?=61 12' sheets or 90 8' sheets. 3 guys who know how to hang and work together, should be able to complete hanging in 5 1/2-7 hours. 2 guys hanging the other measuring,cutting,glueing, and keeping floor clean. it's going to take 3 1/2-4 days to tape, coat, and sand it ready to paint. assuming, framing is correct, all nailers in, and everything is fairly square and straight? of course corner beads will take longer.

good luck
__________________
as always, just my thoughts
good luck....coupe/Larry
take what helps? ignore the rest.
coupe is offline   Reply With Quote
Old 12-06-2012, 06:54 PM   #5
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,273
Default

How long to drywall 2900 sq ft?


starting to sound like it will take me more time to get the drywall downstairs then put it up
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 12-07-2012, 05:44 AM   #6
DIY staff
 
Join Date: Sep 2009
Location: Kane county,Illinois
Posts: 20,387
Default

How long to drywall 2900 sq ft?


Without experience , the hanging will take you a while----the crank up drywall jacks are very helpful --but double or triple the time used compared with two pro hangers hand lifting a sheet to the ceiling.

Do you have a Roto Zip for cutting the openings or will you be premeasuring and precutting the holes?

That will add to your time----

Read up on hanging----butt boards will save you time----having a finish gun and spare 2x4s to quickly add missing blocking is a time saver----

A real drywall screw gun is a time saver----

Learning how to cut using a tape measure and a knife held to the tip will be faster and more accurate than a chalk line----

Keeping a drywall rasp in your pouch will make small adjustments quick--and keep all cuts straight ---

A drywall jack is faster than a flat bar and a block of wood for lifting wall sheets----
__________________
New members: Adding your location to your profile helps in many ways.--M--
oh'mike is offline   Reply With Quote
The Following User Says Thank You to oh'mike For This Useful Post:
Ed911 (12-29-2012)
Old 12-07-2012, 07:32 AM   #7
Member
 
Join Date: Sep 2012
Location: outside ocala fl
Posts: 2,835
Default

How long to drywall 2900 sq ft?


Not knowing what tools you have, or how much experience you have, or the lay out, how many angles you have, do you have long unobstructed runs or is it cut up. How good are you at finishing. This almost makes it impossible to give a good answer. Not really trying to sound like a smart a#$ but it will take how long it takes, worry more about quality than time. After you get going you can probably guess your time frame better than we can. Good luck and let us know how it goes.
ToolSeeker is offline   Reply With Quote
Old 12-07-2012, 12:36 PM   #8
Member
 
Join Date: Oct 2009
Location: Indiana, PA
Posts: 1,273
Default

How long to drywall 2900 sq ft?


well this is me (who has a little bit of experience) working along with someone who has a good amount of work experience in drywall... together we have all the tools, just didn't know if two weeks was what it would normally take for a job like this.. always good to have others opinions on things, if I just listened to one person's idea all the time I'd have lots of problems *lol*
__________________
House Information: Build 1996, 1500 sq ft basement, 1500 sq ft 1st floor, 800 sq ft 2nd floor, 560 sq ft unfinished attic space on 2nd floor. Insulation: Attic blown fiberglass, walls R-19, Basement R-19. HVAC: Trane xc95m fully modulating furnace, single zone, Trane XL20i commiunicating AC unit, TCONT900 Communicating thermostat.
BlueBSH is offline   Reply With Quote
Old 12-08-2012, 08:08 PM   #9
automated tool pro
 
Join Date: Jun 2011
Location: Asheville NC
Posts: 164
Default

How long to drywall 2900 sq ft?


two weeks with limited experience....yes
three is a little ridiculous.
drywallfinisher is offline   Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Similar Threads
Thread Thread Starter Forum Replies Last Post
Drywall question. DerWookie Drywall & Plaster 11 11-08-2011 07:08 AM
Drywall Dust Question izzyant88 Building & Construction 2 10-28-2011 09:32 PM
Drywall Dust Question izzyant88 Drywall & Plaster 1 10-28-2011 08:15 PM
Matching new drywall to old textured drywall pennshaq Drywall & Plaster 1 05-23-2010 09:30 AM
Good ways to run pegboard up to drywall? upthemaiden Drywall & Plaster 1 03-09-2009 01:12 PM




Top of Page | View New Posts

Copyright © 2003-2014 Escalate Media. All Rights Reserved.